Islanding scheme for power transmission utilities

Manohar Singh, K. Meera, Paritosh Joshi, Prem Prakash
{"title":"Islanding scheme for power transmission utilities","authors":"Manohar Singh, K. Meera, Paritosh Joshi, Prem Prakash","doi":"10.1109/CERA.2017.8343303","DOIUrl":null,"url":null,"abstract":"Mostly power utilities are connected with national grid at multiple grid interconnection points. Any unattended major disturbance in the national grid, may lead to tripping of inter-/intra-regional transmission lines and loss of generating units. These trippings/loss of generating units further results in load/generation mismatch in the national grid and finally leads to grid failure event. In order to minimize the occurrence of complete grid blackouts in India, regional protection committees are advising the power utilities to install a local defense mechanism to isolate their power network during grid disturbances. Defense mechanism will isolate the local network from the national grid well before grid collapse point to cater essential electric demand in local network with the help of local generation. As per the guideline issued from the regional power committee, an under frequency islanding schemes needs to be designed. The islanding schemes presented in this article works on the principle of load shedding corresponding to different rates of change of frequency and flat under frequency response. The designed protection scheme is implemented and its dynamic performance is assessed in the Delhi Transmission utility. The rate of change of the frequency will be sensed at load dispatch center and predefined load shedding takes place in online mode at 33/66 kV feeder to maintain the load generation balance in the islands(s) within the acceptable stability limits.","PeriodicalId":286358,"journal":{"name":"2017 6th International Conference on Computer Applications In Electrical Engineering-Recent Advances (CERA)","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2017-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2017 6th International Conference on Computer Applications In Electrical Engineering-Recent Advances (CERA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CERA.2017.8343303","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

Abstract

Mostly power utilities are connected with national grid at multiple grid interconnection points. Any unattended major disturbance in the national grid, may lead to tripping of inter-/intra-regional transmission lines and loss of generating units. These trippings/loss of generating units further results in load/generation mismatch in the national grid and finally leads to grid failure event. In order to minimize the occurrence of complete grid blackouts in India, regional protection committees are advising the power utilities to install a local defense mechanism to isolate their power network during grid disturbances. Defense mechanism will isolate the local network from the national grid well before grid collapse point to cater essential electric demand in local network with the help of local generation. As per the guideline issued from the regional power committee, an under frequency islanding schemes needs to be designed. The islanding schemes presented in this article works on the principle of load shedding corresponding to different rates of change of frequency and flat under frequency response. The designed protection scheme is implemented and its dynamic performance is assessed in the Delhi Transmission utility. The rate of change of the frequency will be sensed at load dispatch center and predefined load shedding takes place in online mode at 33/66 kV feeder to maintain the load generation balance in the islands(s) within the acceptable stability limits.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
输变电设施孤岛方案
大多数电力公司通过多个并网点与国家电网连接。国家电网中任何无人值守的重大扰动都可能导致区域间/区域内输电线路的跳闸和发电机组的损失。这些发电机组的跳闸/损耗进一步导致国家电网的负荷/发电量不匹配,最终导致电网故障事件。为了最大限度地减少印度电网全面停电的发生,地区保护委员会建议电力公司安装一个本地防御机制,在电网受到干扰时隔离他们的电网。防御机制将在电网崩溃点之前将本地电网与国家电网隔离开来,借助本地发电来满足本地电网的基本电力需求。根据地区电力委员会发布的指导方针,需要设计一个低频孤岛方案。本文提出的孤岛方案的工作原理是根据不同的频率变化率进行减载,并在频率响应下保持平稳。设计的保护方案在德里输电系统中实施,并对其动态性能进行了评估。负荷调度中心将感应频率的变动率,并在33/66千伏馈线上以在线模式进行预先设定的减载,以保持各岛屿的负荷产生平衡在可接受的稳定范围内。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Solar PV fed standalone DC microgrid with hybrid energy storage system Control-oriented parametrized models for microbial fuel cells Wind resource assessment and energy analysis for wind energy projects Per phase power balancing in grid connected cascaded H-bridge multilevel converter for solar PV application Modified soft-switching scheme for charge-pump based IDB converter
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1