The Multi-Skilled Resource-Constrained Project Scheduling Problem: A Systematic Review and an Exploration of Future Landscapes

IF 1.4 Q4 ENGINEERING, INDUSTRIAL Management Systems in Production Engineering Pub Date : 2024-02-26 DOI:10.2478/mspe-2024-0012
Zied Bahroun, R. As'ad, Moayad Tanash, Raed Athamneh
{"title":"The Multi-Skilled Resource-Constrained Project Scheduling Problem: A Systematic Review and an Exploration of Future Landscapes","authors":"Zied Bahroun, R. As'ad, Moayad Tanash, Raed Athamneh","doi":"10.2478/mspe-2024-0012","DOIUrl":null,"url":null,"abstract":"\n The Multi-skilled Resource Constrained Project Scheduling Problem (MS-RCPSP) is a complex and multi-faceted problem that involves scheduling activities whilst considering various resource constraints. These constraints include limited availability of workers, equipment, and materials, with each activity requiring a minimal set of skills to be executed. Furthermore, for a better resemblance to reality, workers/machines are assumed to be multi-skilled/multi-purpose posing another dimension of complexity to the problem. The objective is to minimize project duration, cost, or other relevant criteria while accounting for the inherent resources flexibility. This paper provides a systematic review of the literature pertaining to MS-RCPSP, and an in-depth analysis of 171 papers published between 2000 and 2021 inclusive. The conducted bibliometric analysis identifies the top contributing authors, most influential papers, existing research tendencies, and thematic research topics within the field. In addition, this review highlights different aspects of the MS-RCPSP, spanning the significance of performance measures, solution approaches, application areas, and the incorporation of time constraints. While project completion time, cost, and tardiness are common performance indicators, other measures such as multi-skilled staff assignment and schedule robustness are also deemed important. Although various methods have been employed to solve the MS-RCPSP including exact and approximate approaches, the selection of the most-suited approach depends on the problem’s scale, complexity, and constraints, necessitating careful consideration of each method’s strengths and weaknesses. Interestingly, several studies have jointly addressed resource and time constraints in the context of MS-RCPSP, often considering tardiness, and have proposed different algorithms, models, and metaheuristics to tackle these challenges. This paper clearly highlights research gaps and promising avenues for future research. This work provides valuable insights for project managers to effectively schedule tasks in the presence of multiple flexible resources.","PeriodicalId":44097,"journal":{"name":"Management Systems in Production Engineering","volume":null,"pages":null},"PeriodicalIF":1.4000,"publicationDate":"2024-02-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Management Systems in Production Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2478/mspe-2024-0012","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 0

Abstract

The Multi-skilled Resource Constrained Project Scheduling Problem (MS-RCPSP) is a complex and multi-faceted problem that involves scheduling activities whilst considering various resource constraints. These constraints include limited availability of workers, equipment, and materials, with each activity requiring a minimal set of skills to be executed. Furthermore, for a better resemblance to reality, workers/machines are assumed to be multi-skilled/multi-purpose posing another dimension of complexity to the problem. The objective is to minimize project duration, cost, or other relevant criteria while accounting for the inherent resources flexibility. This paper provides a systematic review of the literature pertaining to MS-RCPSP, and an in-depth analysis of 171 papers published between 2000 and 2021 inclusive. The conducted bibliometric analysis identifies the top contributing authors, most influential papers, existing research tendencies, and thematic research topics within the field. In addition, this review highlights different aspects of the MS-RCPSP, spanning the significance of performance measures, solution approaches, application areas, and the incorporation of time constraints. While project completion time, cost, and tardiness are common performance indicators, other measures such as multi-skilled staff assignment and schedule robustness are also deemed important. Although various methods have been employed to solve the MS-RCPSP including exact and approximate approaches, the selection of the most-suited approach depends on the problem’s scale, complexity, and constraints, necessitating careful consideration of each method’s strengths and weaknesses. Interestingly, several studies have jointly addressed resource and time constraints in the context of MS-RCPSP, often considering tardiness, and have proposed different algorithms, models, and metaheuristics to tackle these challenges. This paper clearly highlights research gaps and promising avenues for future research. This work provides valuable insights for project managers to effectively schedule tasks in the presence of multiple flexible resources.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
多技能资源受限项目调度问题:系统回顾与未来展望
多技能资源受限项目调度问题(MS-RCPSP)是一个复杂的、多方面的问题,涉及到在考虑各种资源限制的同时对活动进行调度。这些约束条件包括工人、设备和材料的有限可用性,以及每项活动都需要最低限度的技能才能执行。此外,为了更好地贴近现实,假定工人/机器是多技能/多用途的,这又给问题带来了复杂性。目标是在考虑固有资源灵活性的同时,尽量缩短项目工期、降低成本或其他相关标准。本文对有关 MS-RCPSP 的文献进行了系统回顾,并对 2000 年至 2021 年(含 2021 年)期间发表的 171 篇论文进行了深入分析。通过文献计量分析,确定了该领域的主要贡献作者、最有影响力的论文、现有研究趋势和专题研究主题。此外,本综述还强调了 MS-RCPSP 的不同方面,包括绩效衡量标准的重要性、解决方法、应用领域以及时间限制的纳入。虽然项目完成时间、成本和迟到是常见的绩效指标,但多技能人员分配和进度稳健性等其他指标也被视为重要指标。虽然解决 MS-RCPSP 的方法多种多样,包括精确法和近似法,但选择最合适的方法取决于问题的规模、复杂性和约束条件,因此有必要仔细考虑每种方法的优缺点。有趣的是,在 MS-RCPSP 的背景下,有几项研究共同解决了资源和时间限制问题,通常还考虑了延迟问题,并提出了不同的算法、模型和元启发式方法来应对这些挑战。本文明确强调了研究空白和未来研究的前景。这项工作为项目经理在存在多种灵活资源的情况下有效安排任务提供了宝贵的见解。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
4.30
自引率
13.30%
发文量
48
审稿时长
10 weeks
期刊最新文献
Analysis of the Possibility of Modeling Gas Separators using Computational Fluid Dynamics Process of Incubators in Morocco: Overview of the “Forsa” Program Research of Green Innovation of Companies of Countries with Different Levels of Technological Development of Production Work-Life Balance in SME Sector and Large Enterprises Bibliometric Analysis and Systematic Literature Review in Social Manufacturing
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1