A green project scheduling with material ordering problem considering cost constraints and quality of materials

IF 3.6 2区 工程技术 Q1 ENGINEERING, CIVIL Engineering, Construction and Architectural Management Pub Date : 2024-06-18 DOI:10.1108/ecam-01-2024-0004
Omid Kebriyaii, Ali Heidari, Mohammad Khalilzadeh, Dragan Pamucar
{"title":"A green project scheduling with material ordering problem considering cost constraints and quality of materials","authors":"Omid Kebriyaii, Ali Heidari, Mohammad Khalilzadeh, Dragan Pamucar","doi":"10.1108/ecam-01-2024-0004","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as one of the key project success factors.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>In this paper, a three-objective mathematical model is presented for green project scheduling with materials ordering problems considering rental resources. The first objective is to minimize the total cost of the project site and logistics. The second objective is to minimize the environmental impacts of producing materials and the third objective is to maximize the total quality of materials. Since costs trigger several challenges in projects, cost constraints are considered in this model for the first time and also the cost of delay in supplying of materials by the suppliers has been deducted from the project costs. Subsequently, the model was implemented in a real case and solved by the Lagrangian Relaxation algorithm as an exact method on GAMS software for model validation.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>Based on sensitivity analysis of some parameters, the findings indicate that the cost constraint and lead time have considerable effects on the project duration. Also, integrating project scheduling and material ordering improves the robustness of the project schedule.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>The primary contributions of the present research can be stated as follows: considering the cost constraints in the project scheduling with material ordering problem, incorporating the rental resources and taking the quality levels of materials as well as the environmental impacts into account.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":"21 1","pages":""},"PeriodicalIF":3.6000,"publicationDate":"2024-06-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-01-2024-0004","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0

Abstract

Purpose

Integrating project scheduling and material ordering problems is vital in realistically estimating project cost and duration. Also, the quality level of materials is important as one of the key project success factors.

Design/methodology/approach

In this paper, a three-objective mathematical model is presented for green project scheduling with materials ordering problems considering rental resources. The first objective is to minimize the total cost of the project site and logistics. The second objective is to minimize the environmental impacts of producing materials and the third objective is to maximize the total quality of materials. Since costs trigger several challenges in projects, cost constraints are considered in this model for the first time and also the cost of delay in supplying of materials by the suppliers has been deducted from the project costs. Subsequently, the model was implemented in a real case and solved by the Lagrangian Relaxation algorithm as an exact method on GAMS software for model validation.

Findings

Based on sensitivity analysis of some parameters, the findings indicate that the cost constraint and lead time have considerable effects on the project duration. Also, integrating project scheduling and material ordering improves the robustness of the project schedule.

Originality/value

The primary contributions of the present research can be stated as follows: considering the cost constraints in the project scheduling with material ordering problem, incorporating the rental resources and taking the quality levels of materials as well as the environmental impacts into account.

查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
考虑成本约束和材料质量的绿色项目材料订购调度问题
目的将项目调度与材料订购问题结合起来,对于实际估算项目成本和工期至关重要。此外,材料的质量水平作为项目成功的关键因素之一也非常重要。设计/方法/途径本文提出了一个考虑到租赁资源的绿色项目调度与材料订购问题的三目标数学模型。第一个目标是最大限度地降低项目场地和物流的总成本。第二个目标是使材料生产对环境的影响最小,第三个目标是使材料的总质量最大化。由于成本会给项目带来诸多挑战,因此该模型首次考虑了成本约束,同时还从项目成本中扣除了供应商延迟供应材料的成本。随后,在实际案例中实施了该模型,并通过拉格朗日松弛算法作为一种精确方法在 GAMS 软件上进行求解,以验证模型的有效性。原创性/价值本研究的主要贡献如下:在项目进度安排与材料订购问题中考虑成本约束,纳入租赁资源,考虑材料质量水平以及环境影响。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
Engineering, Construction and Architectural Management
Engineering, Construction and Architectural Management Business, Management and Accounting-General Business,Management and Accounting
CiteScore
8.10
自引率
19.50%
发文量
226
期刊介绍: ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process. ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.
期刊最新文献
Production-oriented approach for optimal mass-customisation of floor panel layouts in cross-laminated timber (CLT) buildings A decision-support system for choosing between traditional and alternative project delivery methods for bundled projects Traversing the complexity of digital construction and beyond through soft skills: experiences of Malaysian architects Blockchain-enhanced computer vision approach for remote safety inspection in construction A novel approach for integrating BIM and green building rating systems in the construction projects design phase
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1