{"title":"长输油气管道山区自动焊陡坡施工技术探讨","authors":"郝 振乾, 赵 章勇, 郝 琦, 杜 冲","doi":"10.26789/szgc.v7i4.929","DOIUrl":null,"url":null,"abstract":"广西LNG配套外输管道桂林支线工程(三标段)项目,主要工作量有55.44km长的管线,管径DN800,焊接工艺为组合自动焊,其中标段内有8km的山地施工,其中有三处爬坡角度均大于30°,垂直高差100m左右,属于山地陡坡的特殊施工。陡坡施工中管沟开挖、运布管、焊接、防塌棚的架设等施工工序难度较大,安全风险高,陡坡施工也受到阴雨天气等因素的制约。","PeriodicalId":58331,"journal":{"name":"城乡建设","volume":"25 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-04-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"城乡建设","FirstCategoryId":"1087","ListUrlMain":"https://doi.org/10.26789/szgc.v7i4.929","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
长输油气管道山区自动焊陡坡施工技术探讨
广西LNG配套外输管道桂林支线工程(三标段)项目,主要工作量有55.44km长的管线,管径DN800,焊接工艺为组合自动焊,其中标段内有8km的山地施工,其中有三处爬坡角度均大于30°,垂直高差100m左右,属于山地陡坡的特殊施工。陡坡施工中管沟开挖、运布管、焊接、防塌棚的架设等施工工序难度较大,安全风险高,陡坡施工也受到阴雨天气等因素的制约。
本文章由计算机程序翻译,如有差异,请以英文原文为准。