{"title":"提出了一种利用EVM和成本历史数据提高项目成本可预测性的方法","authors":"A. D. Souza","doi":"10.1109/ICSE.2013.6606740","DOIUrl":null,"url":null,"abstract":"This paper proposes an extension of the Earned Value Management - EVM technique through the integration of historical cost performance data of processes under statistical control as a means to improve the predictability of the cost of projects. The proposed technique was evaluated through a case-study in industry, which evaluated the implementation of the proposed technique in 22 software development projects Hypotheses tests with 95% significance level were performed, and the proposed technique was more accurate and more precise than the traditional technique for calculating the Cost Performance Index - CPI and Estimates at Completion - EAC.","PeriodicalId":322423,"journal":{"name":"2013 35th International Conference on Software Engineering (ICSE)","volume":"6 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2013-05-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"9","resultStr":"{\"title\":\"A proposal for the improvement of project's cost predictability using EVM and historical data of cost\",\"authors\":\"A. D. Souza\",\"doi\":\"10.1109/ICSE.2013.6606740\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper proposes an extension of the Earned Value Management - EVM technique through the integration of historical cost performance data of processes under statistical control as a means to improve the predictability of the cost of projects. The proposed technique was evaluated through a case-study in industry, which evaluated the implementation of the proposed technique in 22 software development projects Hypotheses tests with 95% significance level were performed, and the proposed technique was more accurate and more precise than the traditional technique for calculating the Cost Performance Index - CPI and Estimates at Completion - EAC.\",\"PeriodicalId\":322423,\"journal\":{\"name\":\"2013 35th International Conference on Software Engineering (ICSE)\",\"volume\":\"6 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2013-05-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"9\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2013 35th International Conference on Software Engineering (ICSE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICSE.2013.6606740\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2013 35th International Conference on Software Engineering (ICSE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICSE.2013.6606740","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
A proposal for the improvement of project's cost predictability using EVM and historical data of cost
This paper proposes an extension of the Earned Value Management - EVM technique through the integration of historical cost performance data of processes under statistical control as a means to improve the predictability of the cost of projects. The proposed technique was evaluated through a case-study in industry, which evaluated the implementation of the proposed technique in 22 software development projects Hypotheses tests with 95% significance level were performed, and the proposed technique was more accurate and more precise than the traditional technique for calculating the Cost Performance Index - CPI and Estimates at Completion - EAC.