{"title":"普拉斯基高架公路UHPC接缝填筑施工问题及解决方案","authors":"Michael D. Mcdonagh, A. Foden","doi":"10.21838/UHPC.9629","DOIUrl":null,"url":null,"abstract":"The redecking of the Pulaski Skyway is the largest implementation of ultra-high performance concrete (UHPC) in North America to date. Approximately 90,000 m² (1 million ft²) of deck was replaced with precast concrete panels connected with field-placed UHPC, using a total volume of more than 5,000 cubic yards (3,800 cubic meters) of UHPC. The construction of the new deck took place over the course of four years in a temperate climate with hot summers and cold winters. The very large quantity of deck, the large volumes of field-placed UHPC, and multiple years of construction with all possible weather and temperature conditions created challenges to successful UHPC placement. \nThis paper discusses the types of problems that arose and the solutions that were developed during the course of the redecking construction project. The problems included placement issues related to pumping, fiber segregation issues deriving from low ambient temperature, cracking due to early age loading, and underfilled pockets and joints due to leaking or blown-out forms. The distinct issues encountered are set out in detail, along with the solutions and the methods that were employed to find the solutions, with a discussion on the reasoning behind the selection made in each case. \nThe information presented is intended to serve as a resource for engineers and construction inspectors undertaking UHPC joint fill projects, providing substantive explanations of the sort of UHPC construction problems that can arise and examples of means utilized to address them.","PeriodicalId":170570,"journal":{"name":"Second International Interactive Symposium on UHPC","volume":"89 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-06-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"UHPC Joint Fill Construction Problems and Solutions on the Pulaski Skyway\",\"authors\":\"Michael D. Mcdonagh, A. Foden\",\"doi\":\"10.21838/UHPC.9629\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The redecking of the Pulaski Skyway is the largest implementation of ultra-high performance concrete (UHPC) in North America to date. Approximately 90,000 m² (1 million ft²) of deck was replaced with precast concrete panels connected with field-placed UHPC, using a total volume of more than 5,000 cubic yards (3,800 cubic meters) of UHPC. The construction of the new deck took place over the course of four years in a temperate climate with hot summers and cold winters. The very large quantity of deck, the large volumes of field-placed UHPC, and multiple years of construction with all possible weather and temperature conditions created challenges to successful UHPC placement. \\nThis paper discusses the types of problems that arose and the solutions that were developed during the course of the redecking construction project. The problems included placement issues related to pumping, fiber segregation issues deriving from low ambient temperature, cracking due to early age loading, and underfilled pockets and joints due to leaking or blown-out forms. The distinct issues encountered are set out in detail, along with the solutions and the methods that were employed to find the solutions, with a discussion on the reasoning behind the selection made in each case. \\nThe information presented is intended to serve as a resource for engineers and construction inspectors undertaking UHPC joint fill projects, providing substantive explanations of the sort of UHPC construction problems that can arise and examples of means utilized to address them.\",\"PeriodicalId\":170570,\"journal\":{\"name\":\"Second International Interactive Symposium on UHPC\",\"volume\":\"89 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-06-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Second International Interactive Symposium on UHPC\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21838/UHPC.9629\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Second International Interactive Symposium on UHPC","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21838/UHPC.9629","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

普拉斯基高架公路的重新铺装是迄今为止北美最大的超高性能混凝土(UHPC)实施。大约90000平方米(100万平方英尺)的甲板被预制混凝土板取代,与现场放置的UHPC连接,使用了超过5000立方码(3800立方米)的UHPC。新甲板的建造在温和的气候中进行了四年,夏季炎热,冬季寒冷。大量的甲板,大量的现场放置的UHPC,以及多年的施工,所有可能的天气和温度条件都给UHPC的成功放置带来了挑战。本文论述了重甲板施工工程中出现的问题类型及解决方案。这些问题包括与泵送相关的位置问题、低环境温度导致的纤维离析问题、过早加载导致的裂缝问题,以及由于泄漏或爆裂导致的空腔和接头填充不足。详细列出了遇到的不同问题,以及解决方案和用于找到解决方案的方法,并讨论了在每种情况下做出选择的原因。所提供的信息旨在为从事超高压砼联合填筑项目的工程师和施工检查员提供资源,对可能出现的超高压砼施工问题类型提供实质性解释,并举例说明用于解决这些问题的方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
UHPC Joint Fill Construction Problems and Solutions on the Pulaski Skyway
The redecking of the Pulaski Skyway is the largest implementation of ultra-high performance concrete (UHPC) in North America to date. Approximately 90,000 m² (1 million ft²) of deck was replaced with precast concrete panels connected with field-placed UHPC, using a total volume of more than 5,000 cubic yards (3,800 cubic meters) of UHPC. The construction of the new deck took place over the course of four years in a temperate climate with hot summers and cold winters. The very large quantity of deck, the large volumes of field-placed UHPC, and multiple years of construction with all possible weather and temperature conditions created challenges to successful UHPC placement. This paper discusses the types of problems that arose and the solutions that were developed during the course of the redecking construction project. The problems included placement issues related to pumping, fiber segregation issues deriving from low ambient temperature, cracking due to early age loading, and underfilled pockets and joints due to leaking or blown-out forms. The distinct issues encountered are set out in detail, along with the solutions and the methods that were employed to find the solutions, with a discussion on the reasoning behind the selection made in each case. The information presented is intended to serve as a resource for engineers and construction inspectors undertaking UHPC joint fill projects, providing substantive explanations of the sort of UHPC construction problems that can arise and examples of means utilized to address them.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
New Connection Details to Connect Precast Cap Beams to Precast Columns Using Ultra High Performance Concrete (UHPC) For Seismic and Non-Seismic Regions Acceptance Criteria for Composite UHPC Panel Systems to Show Compliance with the Building Codes in the USA UHPC Facades — The New Use For The New Material The Next Generation of UHPC Caltrans Implementation of UHPC Connections for ABC Projects
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1