发电系统生产成本计算

M. Mazumdar
{"title":"发电系统生产成本计算","authors":"M. Mazumdar","doi":"10.1109/PICA.1995.515292","DOIUrl":null,"url":null,"abstract":"This paper considers the problem of computing the expected value of generating system production costs. First, using a stochastic model for the frequency and duration of generation outage, it provides an efficient Monte Carlo procedure for the evaluation of the Baleriaux formula. Secondly, it points out the need for using a stochastic model for estimating production costs with time-dependent constraints via Monte Carlo. Lastly, it considers a model where the chronological load also has a random component and obtains an expression for expected production costs for this situation.","PeriodicalId":294493,"journal":{"name":"Proceedings of Power Industry Computer Applications Conference","volume":"60 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1995-05-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"15","resultStr":"{\"title\":\"Computation of power generation system production costs\",\"authors\":\"M. Mazumdar\",\"doi\":\"10.1109/PICA.1995.515292\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This paper considers the problem of computing the expected value of generating system production costs. First, using a stochastic model for the frequency and duration of generation outage, it provides an efficient Monte Carlo procedure for the evaluation of the Baleriaux formula. Secondly, it points out the need for using a stochastic model for estimating production costs with time-dependent constraints via Monte Carlo. Lastly, it considers a model where the chronological load also has a random component and obtains an expression for expected production costs for this situation.\",\"PeriodicalId\":294493,\"journal\":{\"name\":\"Proceedings of Power Industry Computer Applications Conference\",\"volume\":\"60 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1995-05-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"15\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of Power Industry Computer Applications Conference\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/PICA.1995.515292\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of Power Industry Computer Applications Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PICA.1995.515292","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 15

摘要

本文研究了发电系统生产成本期望值的计算问题。首先,利用发电中断频率和持续时间的随机模型,为巴勒里奥公式的评估提供了一种有效的蒙特卡罗方法。其次,指出了使用蒙特卡罗随机模型来估计具有时间依赖约束的生产成本的必要性。最后,它考虑了一个时间负荷也具有随机分量的模型,并得到了这种情况下预期生产成本的表达式。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Computation of power generation system production costs
This paper considers the problem of computing the expected value of generating system production costs. First, using a stochastic model for the frequency and duration of generation outage, it provides an efficient Monte Carlo procedure for the evaluation of the Baleriaux formula. Secondly, it points out the need for using a stochastic model for estimating production costs with time-dependent constraints via Monte Carlo. Lastly, it considers a model where the chronological load also has a random component and obtains an expression for expected production costs for this situation.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Development of the Intercontrol Center Communications Protocol (ICCP) [power system control] Hydropower generation management under uncertainty via scenario analysis and parallel computation Optimal fuzzy inference for short-term load forecasting Long-term/mid-term resource optimization of a hydro-dominant power system using interior point method The design of next generation SCADA systems
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1