A. Samudra, Suhariyanto Suhariyanto, Susapto Susapto
{"title":"印尼国际伊斯兰大学图书馆建设项目规划","authors":"A. Samudra, Suhariyanto Suhariyanto, Susapto Susapto","doi":"10.55404/jos-mrk.2021.02.03.256-260","DOIUrl":null,"url":null,"abstract":"The Indonesian International Islamic University Depok Library Building Construction Project has area of 16495 m2. This library has 8 floors, which is located in the middle of the city. So, the mobilization of tools and materials become easier. The purpose of this study is to make project planning in terms of organizational structure, site layout, traffic management, strategy and implementation methods, quality, safety, occupational health and environment (K3L); Project Implementation Budget Plan and project scheduling. The data used are shop drawings, Work Plan and Conditions, and HSD Depok City 2020. Planning a project schedule using the Barchart method with the help of MS. Project 2016. This planning produces a line type organizational structure where the leaders and subordinates are in one line of command; Site Layout by using 1 unit tower crane; Traffic Management planning using a one gate system; The implementation strategy uses 2 zones; The implementation method uses Bottom Up, starting from zone 1 then proceed to zone 2 until the 8th floor; Quality plan based on the application of SOP (Standard Operating Procedure); The HSE plan includes hazard identification, an HSE equipment plan, and an HSE implementation schedule; The project duration plan is 43 weeks, and the Implementation Budget Plan is Rp. 151,141,347,875.","PeriodicalId":337938,"journal":{"name":"Jurnal JOS-MRK","volume":"56 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-09-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"PERENCANAAN PROYEK PEMBANGUNAN GEDUNG PERPUSTAKAAN UNIVERSITAS ISLAM INTERNASIONAL INDONESIA DEPOK\",\"authors\":\"A. Samudra, Suhariyanto Suhariyanto, Susapto Susapto\",\"doi\":\"10.55404/jos-mrk.2021.02.03.256-260\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The Indonesian International Islamic University Depok Library Building Construction Project has area of 16495 m2. This library has 8 floors, which is located in the middle of the city. So, the mobilization of tools and materials become easier. The purpose of this study is to make project planning in terms of organizational structure, site layout, traffic management, strategy and implementation methods, quality, safety, occupational health and environment (K3L); Project Implementation Budget Plan and project scheduling. The data used are shop drawings, Work Plan and Conditions, and HSD Depok City 2020. Planning a project schedule using the Barchart method with the help of MS. Project 2016. This planning produces a line type organizational structure where the leaders and subordinates are in one line of command; Site Layout by using 1 unit tower crane; Traffic Management planning using a one gate system; The implementation strategy uses 2 zones; The implementation method uses Bottom Up, starting from zone 1 then proceed to zone 2 until the 8th floor; Quality plan based on the application of SOP (Standard Operating Procedure); The HSE plan includes hazard identification, an HSE equipment plan, and an HSE implementation schedule; The project duration plan is 43 weeks, and the Implementation Budget Plan is Rp. 151,141,347,875.\",\"PeriodicalId\":337938,\"journal\":{\"name\":\"Jurnal JOS-MRK\",\"volume\":\"56 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-09-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal JOS-MRK\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.55404/jos-mrk.2021.02.03.256-260\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal JOS-MRK","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.55404/jos-mrk.2021.02.03.256-260","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
印尼国际伊斯兰大学德波克图书馆大楼建设项目,建筑面积16495平方米。这座图书馆有8层,位于城市的中心。因此,工具和材料的动员变得更加容易。本研究的目的是在组织结构、场地布局、交通管理、策略和实施方法、质量、安全、职业健康和环境(K3L)方面进行项目规划;项目实施预算计划和项目进度安排。使用的数据是车间图纸,工作计划和条件,以及HSD Depok City 2020。在ms project 2016的帮助下,使用Barchart方法规划项目进度。这种规划产生了一种直线型的组织结构,在这种结构中,领导和下属处于同一指挥线;采用1台塔吊进行现场布置;使用一门系统的交通管理规划;实施策略使用2个区域;实施方法为自下而上,从1区开始,再到2区,直到8楼;基于SOP(标准操作程序)的质量计划;HSE计划包括危害识别、HSE设备计划和HSE实施时间表;项目持续时间计划为43周,执行预算计划为151,141,347,875卢比。
PERENCANAAN PROYEK PEMBANGUNAN GEDUNG PERPUSTAKAAN UNIVERSITAS ISLAM INTERNASIONAL INDONESIA DEPOK
The Indonesian International Islamic University Depok Library Building Construction Project has area of 16495 m2. This library has 8 floors, which is located in the middle of the city. So, the mobilization of tools and materials become easier. The purpose of this study is to make project planning in terms of organizational structure, site layout, traffic management, strategy and implementation methods, quality, safety, occupational health and environment (K3L); Project Implementation Budget Plan and project scheduling. The data used are shop drawings, Work Plan and Conditions, and HSD Depok City 2020. Planning a project schedule using the Barchart method with the help of MS. Project 2016. This planning produces a line type organizational structure where the leaders and subordinates are in one line of command; Site Layout by using 1 unit tower crane; Traffic Management planning using a one gate system; The implementation strategy uses 2 zones; The implementation method uses Bottom Up, starting from zone 1 then proceed to zone 2 until the 8th floor; Quality plan based on the application of SOP (Standard Operating Procedure); The HSE plan includes hazard identification, an HSE equipment plan, and an HSE implementation schedule; The project duration plan is 43 weeks, and the Implementation Budget Plan is Rp. 151,141,347,875.