{"title":"关键路径法在项目管理信息系统中的实施及What - If分析","authors":"Zulfiandri, Farah Dhia Yasmin, Rinda Hesti Kusumaningtyas","doi":"10.1109/CITSM56380.2022.9935912","DOIUrl":null,"url":null,"abstract":"Project management is the process of planning, im-plementing, monitoring and closing projects so that the project runs according to the target. One company that requires project management is PT. Triprima Karya which offers construction project consulting services. In the company there are problems, namely there are still delays in several projects which result in de-lays in project payments so that it can harm the company. The purpose of this research is to implement the critical path method and what if analysis to anticipate project delays at PT Triprima Karya. The methods used for delay analysis are Critical Path Method and What If Analysis. The results of the research are based on the critical path method, the critical path on the project is the Preliminary work (A), Preparatory work (B), Construction work (C), Mechanical and plumbing work (E), Electrical work (F), Power connection new electricity (H). And if activity A is delayed for 7 days, based on the results of what if analysis calculations, the activities that can be accelerated are Preparatory work (B) with an additional number of 5 workers and 8 hours, Construction work (C) with an additional 1 worker and 0, 9 hours, Mechanical and plumbing work (E) with an additional number of 1 worker and 1 hour, Electrical work (F) with an additional 1 worker and 1.1 hours New electrical power connection (H) with an additional number of 3 workers and 4 hours.","PeriodicalId":342813,"journal":{"name":"2022 10th International Conference on Cyber and IT Service Management (CITSM)","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-09-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Implementation of Critical Path Method and What If Analysis in Project Management Information System\",\"authors\":\"Zulfiandri, Farah Dhia Yasmin, Rinda Hesti Kusumaningtyas\",\"doi\":\"10.1109/CITSM56380.2022.9935912\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Project management is the process of planning, im-plementing, monitoring and closing projects so that the project runs according to the target. One company that requires project management is PT. Triprima Karya which offers construction project consulting services. In the company there are problems, namely there are still delays in several projects which result in de-lays in project payments so that it can harm the company. The purpose of this research is to implement the critical path method and what if analysis to anticipate project delays at PT Triprima Karya. The methods used for delay analysis are Critical Path Method and What If Analysis. The results of the research are based on the critical path method, the critical path on the project is the Preliminary work (A), Preparatory work (B), Construction work (C), Mechanical and plumbing work (E), Electrical work (F), Power connection new electricity (H). And if activity A is delayed for 7 days, based on the results of what if analysis calculations, the activities that can be accelerated are Preparatory work (B) with an additional number of 5 workers and 8 hours, Construction work (C) with an additional 1 worker and 0, 9 hours, Mechanical and plumbing work (E) with an additional number of 1 worker and 1 hour, Electrical work (F) with an additional 1 worker and 1.1 hours New electrical power connection (H) with an additional number of 3 workers and 4 hours.\",\"PeriodicalId\":342813,\"journal\":{\"name\":\"2022 10th International Conference on Cyber and IT Service Management (CITSM)\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-09-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2022 10th International Conference on Cyber and IT Service Management (CITSM)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CITSM56380.2022.9935912\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2022 10th International Conference on Cyber and IT Service Management (CITSM)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CITSM56380.2022.9935912","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
项目管理是计划、实施、监视和结束项目的过程,使项目按照目标运行。一个需要项目管理的公司是PT. Triprima Karya,它提供建筑项目咨询服务。公司存在一些问题,即有几个项目仍然存在延迟,导致项目付款延迟,从而对公司造成损害。本研究的目的是在Triprima Karya PT实施关键路径方法和如果分析来预测项目延迟。用于延迟分析的方法有关键路径法和假设分析法。研究结果基于关键路径法,项目的关键路径为前期工作(A),前期准备工作(B),施工工作(C),机械和管道工作(E),电气工作(F),电源连接新电(H)。如果活动A延迟7天,根据分析计算的结果,可以加速的活动是准备工作(B),增加5名工人和8小时。建筑工程(C)增聘1名工人及0.9小时;机械及水管工程(E)增聘1名工人及1小时;电力工程(F)增聘1名工人及1.1小时;新接电工程(H)增聘3名工人及4小时。
Implementation of Critical Path Method and What If Analysis in Project Management Information System
Project management is the process of planning, im-plementing, monitoring and closing projects so that the project runs according to the target. One company that requires project management is PT. Triprima Karya which offers construction project consulting services. In the company there are problems, namely there are still delays in several projects which result in de-lays in project payments so that it can harm the company. The purpose of this research is to implement the critical path method and what if analysis to anticipate project delays at PT Triprima Karya. The methods used for delay analysis are Critical Path Method and What If Analysis. The results of the research are based on the critical path method, the critical path on the project is the Preliminary work (A), Preparatory work (B), Construction work (C), Mechanical and plumbing work (E), Electrical work (F), Power connection new electricity (H). And if activity A is delayed for 7 days, based on the results of what if analysis calculations, the activities that can be accelerated are Preparatory work (B) with an additional number of 5 workers and 8 hours, Construction work (C) with an additional 1 worker and 0, 9 hours, Mechanical and plumbing work (E) with an additional number of 1 worker and 1 hour, Electrical work (F) with an additional 1 worker and 1.1 hours New electrical power connection (H) with an additional number of 3 workers and 4 hours.