{"title":"孟加拉国电网变电站可靠性评估","authors":"M. I. Hossain, Rumana Binte Faruque, A. Chowdhury","doi":"10.1109/ICECE.2014.7027015","DOIUrl":null,"url":null,"abstract":"Determination of the reliability of a substation is important as it helps locate weak points that may be contributing to overall power system unreliability. This paper evaluates reliability of 230 kV grid substations in Bangladesh subject to protection failures. The problem belongs to the dynamic reliability evaluation field. Event tree analysis is used as the main method. Fault tree analysis is used to get the input of the event tree. Reliability of five grid substations are calculated. Ishurdi grid substation is found to have a mean time to failure of only six months, which will affect seriously the design and safety of the proposed nuclear power station at Rooppur sited closely nearby.","PeriodicalId":335492,"journal":{"name":"8th International Conference on Electrical and Computer Engineering","volume":"40 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2014-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Reliability evaluation of grid substations in Bangladesh power system\",\"authors\":\"M. I. Hossain, Rumana Binte Faruque, A. Chowdhury\",\"doi\":\"10.1109/ICECE.2014.7027015\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Determination of the reliability of a substation is important as it helps locate weak points that may be contributing to overall power system unreliability. This paper evaluates reliability of 230 kV grid substations in Bangladesh subject to protection failures. The problem belongs to the dynamic reliability evaluation field. Event tree analysis is used as the main method. Fault tree analysis is used to get the input of the event tree. Reliability of five grid substations are calculated. Ishurdi grid substation is found to have a mean time to failure of only six months, which will affect seriously the design and safety of the proposed nuclear power station at Rooppur sited closely nearby.\",\"PeriodicalId\":335492,\"journal\":{\"name\":\"8th International Conference on Electrical and Computer Engineering\",\"volume\":\"40 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2014-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"8th International Conference on Electrical and Computer Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICECE.2014.7027015\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"8th International Conference on Electrical and Computer Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICECE.2014.7027015","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

确定变电站的可靠性非常重要,因为它有助于定位可能导致整个电力系统不可靠性的薄弱环节。本文对孟加拉国230千伏电网变电站在保护失效情况下的可靠性进行了评估。该问题属于动态可靠性评估领域。以事件树分析法为主要分析方法。故障树分析用于获取事件树的输入。计算了5个并网变电站的可靠度。Ishurdi电网变电站的平均故障时间仅为6个月,这将严重影响附近鲁普尔核电站的设计和安全。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Reliability evaluation of grid substations in Bangladesh power system
Determination of the reliability of a substation is important as it helps locate weak points that may be contributing to overall power system unreliability. This paper evaluates reliability of 230 kV grid substations in Bangladesh subject to protection failures. The problem belongs to the dynamic reliability evaluation field. Event tree analysis is used as the main method. Fault tree analysis is used to get the input of the event tree. Reliability of five grid substations are calculated. Ishurdi grid substation is found to have a mean time to failure of only six months, which will affect seriously the design and safety of the proposed nuclear power station at Rooppur sited closely nearby.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Empirical prediction of optical transitions in metallic armchair SWCNTs Dynamics of fullerene self-insertion into carbon nanotubes in water Diffusion tensor based global tractography of human brain fiber bundles Biomass quality analysis for power generation Video-based affinity group detection using trajectories of multiple subjects
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1