{"title":"复杂环境下大坝超大型弧形闸门安装技术研究","authors":"Zhou Ruoyu, Meichun Gou","doi":"10.11648/j.ajwse.20230901.12","DOIUrl":null,"url":null,"abstract":": Taking the installation construction of super large radial gates of Nam theun1 hydropower station in Laos as an example, due to the lag of civil construction period and the dam structure","PeriodicalId":423224,"journal":{"name":"American Journal of Water Science and Engineering","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-03-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Research on Installation Technology of Super Large Radial Gate of Dam in Complex Environment\",\"authors\":\"Zhou Ruoyu, Meichun Gou\",\"doi\":\"10.11648/j.ajwse.20230901.12\",\"DOIUrl\":null,\"url\":null,\"abstract\":\": Taking the installation construction of super large radial gates of Nam theun1 hydropower station in Laos as an example, due to the lag of civil construction period and the dam structure\",\"PeriodicalId\":423224,\"journal\":{\"name\":\"American Journal of Water Science and Engineering\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-03-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"American Journal of Water Science and Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.11648/j.ajwse.20230901.12\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"American Journal of Water Science and Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.11648/j.ajwse.20230901.12","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Research on Installation Technology of Super Large Radial Gate of Dam in Complex Environment
: Taking the installation construction of super large radial gates of Nam theun1 hydropower station in Laos as an example, due to the lag of civil construction period and the dam structure