{"title":"结合实验和基于风险的检测(RBI)研究以及先进无损检测技术的管道完整性管理成本仿真优化","authors":"Cong Nhat Tran, Vandy Ly, Trong Nghiem Nguyen, Anh Tuan Dang, Hữu Hải Ngô","doi":"10.47800/pvj.2022.03-03","DOIUrl":null,"url":null,"abstract":"Subsea pipeline integrity management requires frequent launching of intelligent pig which involves very high risk and cost, especially if using subsea pig receiver. BIENDONG POC has conducted simulation in combination with experimental, risk-based inspection (RBI) studies and advanced non-destructive testing (NDT) by phonon diagnostic technique (PDT). These solutions substitutes the intelligent pigging activity and helps BIENDONG POC save over USD 32 million worth of cost and avoid a long production shutdown. ","PeriodicalId":294988,"journal":{"name":"Petrovietnam Journal","volume":"68 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-04-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Optimisation of pipeline integrity management cost by simulation in combination with experimental and risk-based inspection (RBI) study and advanced NDT\",\"authors\":\"Cong Nhat Tran, Vandy Ly, Trong Nghiem Nguyen, Anh Tuan Dang, Hữu Hải Ngô\",\"doi\":\"10.47800/pvj.2022.03-03\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Subsea pipeline integrity management requires frequent launching of intelligent pig which involves very high risk and cost, especially if using subsea pig receiver. BIENDONG POC has conducted simulation in combination with experimental, risk-based inspection (RBI) studies and advanced non-destructive testing (NDT) by phonon diagnostic technique (PDT). These solutions substitutes the intelligent pigging activity and helps BIENDONG POC save over USD 32 million worth of cost and avoid a long production shutdown. \",\"PeriodicalId\":294988,\"journal\":{\"name\":\"Petrovietnam Journal\",\"volume\":\"68 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-04-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Petrovietnam Journal\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.47800/pvj.2022.03-03\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Petrovietnam Journal","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.47800/pvj.2022.03-03","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Optimisation of pipeline integrity management cost by simulation in combination with experimental and risk-based inspection (RBI) study and advanced NDT
Subsea pipeline integrity management requires frequent launching of intelligent pig which involves very high risk and cost, especially if using subsea pig receiver. BIENDONG POC has conducted simulation in combination with experimental, risk-based inspection (RBI) studies and advanced non-destructive testing (NDT) by phonon diagnostic technique (PDT). These solutions substitutes the intelligent pigging activity and helps BIENDONG POC save over USD 32 million worth of cost and avoid a long production shutdown.