CPM方法和第一次在雅加达北部的教会帐篷建设项目中使用

Glisina Dwinoor Rembulan, Sun Yuhao
{"title":"CPM方法和第一次在雅加达北部的教会帐篷建设项目中使用","authors":"Glisina Dwinoor Rembulan, Sun Yuhao","doi":"10.31289/jime.v7i2.9648","DOIUrl":null,"url":null,"abstract":"PT. TCI is a company operating in the construction sector which handles the construction of several projects, one of which is the Tabernacle Church project. In carrying out the project work, several factors/problems arose, resulting in an extension of the project foundation construction stage and increasing the project period and costs. The use of the CPM and PERT methods for implementing the foundation construction of the GKT project using the planned and actual schedules has been able to optimize the work, namely 123 days using the planned schedule and 150 days using the actual schedule. These results have found the critical path, so that by applying the CPM and PERT methods in this project, an estimated schedule can be obtained to speed up the project. The cost difference using the CPM, PERT and CPM-PERT methods for the planned schedule is IDR 304,000,000 (Three Hundred and Four Million Rupiah) , Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah) and Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah). The difference in costs using the CPM, PERT, CPM-PERT method for the actual schedule is IDR 344,000,000 (Three Hundred Forty Four Million Rupiah), IDR 304,000,000 (Three Hundred Forty Four Million Rupiah) and IDR 304,000,000 (Three Hundred Forty Four Million Rupiah). These costs will be the contractor's profit.","PeriodicalId":479709,"journal":{"name":"JIME (Journal of Industrial and Manufacture Engineering)","volume":"69 8","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-11-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Penerapan Metode CPM dan PERT Pada Proyek Konstruksi Gereja Kemah Tabernake PIK 2 Jakarta Utara\",\"authors\":\"Glisina Dwinoor Rembulan, Sun Yuhao\",\"doi\":\"10.31289/jime.v7i2.9648\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"PT. TCI is a company operating in the construction sector which handles the construction of several projects, one of which is the Tabernacle Church project. In carrying out the project work, several factors/problems arose, resulting in an extension of the project foundation construction stage and increasing the project period and costs. The use of the CPM and PERT methods for implementing the foundation construction of the GKT project using the planned and actual schedules has been able to optimize the work, namely 123 days using the planned schedule and 150 days using the actual schedule. These results have found the critical path, so that by applying the CPM and PERT methods in this project, an estimated schedule can be obtained to speed up the project. The cost difference using the CPM, PERT and CPM-PERT methods for the planned schedule is IDR 304,000,000 (Three Hundred and Four Million Rupiah) , Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah) and Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah). The difference in costs using the CPM, PERT, CPM-PERT method for the actual schedule is IDR 344,000,000 (Three Hundred Forty Four Million Rupiah), IDR 304,000,000 (Three Hundred Forty Four Million Rupiah) and IDR 304,000,000 (Three Hundred Forty Four Million Rupiah). These costs will be the contractor's profit.\",\"PeriodicalId\":479709,\"journal\":{\"name\":\"JIME (Journal of Industrial and Manufacture Engineering)\",\"volume\":\"69 8\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-11-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"JIME (Journal of Industrial and Manufacture Engineering)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31289/jime.v7i2.9648\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"JIME (Journal of Industrial and Manufacture Engineering)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31289/jime.v7i2.9648","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

PT. TCI是一家在建筑领域经营的公司,负责几个项目的建设,其中一个是会幕教堂项目。在开展项目工作中,出现了一些因素/问题,导致项目基础建设阶段延长,项目工期和成本增加。利用CPM和PERT方法实施GKT项目的基础施工,使用计划和实际进度,可以优化工作,即使用计划进度123天,使用实际进度150天。这些结果找到了关键路径,因此,在该项目中应用CPM和PERT方法,可以得到一个估计的进度,以加快项目的进度。在计划进度中使用CPM、PERT和CPM-PERT方法的成本差异为3.04亿印尼盾(3.04亿印尼盾)、2.64亿印尼盾(2.64亿印尼盾)和2.64亿印尼盾(2.64亿印尼盾)。使用CPM, PERT, CPM-PERT方法对实际进度的成本差异为344,000,000印尼盾(三亿四千四百万印尼盾),304,000,000印尼盾(三亿四千四百万印尼盾)和304,000,000印尼盾(三亿四千四百万印尼盾)。这些费用将成为承包商的利润。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Penerapan Metode CPM dan PERT Pada Proyek Konstruksi Gereja Kemah Tabernake PIK 2 Jakarta Utara
PT. TCI is a company operating in the construction sector which handles the construction of several projects, one of which is the Tabernacle Church project. In carrying out the project work, several factors/problems arose, resulting in an extension of the project foundation construction stage and increasing the project period and costs. The use of the CPM and PERT methods for implementing the foundation construction of the GKT project using the planned and actual schedules has been able to optimize the work, namely 123 days using the planned schedule and 150 days using the actual schedule. These results have found the critical path, so that by applying the CPM and PERT methods in this project, an estimated schedule can be obtained to speed up the project. The cost difference using the CPM, PERT and CPM-PERT methods for the planned schedule is IDR 304,000,000 (Three Hundred and Four Million Rupiah) , Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah) and Rp. 264,000,000 (Two Hundred and Sixty Four Million Rupiah). The difference in costs using the CPM, PERT, CPM-PERT method for the actual schedule is IDR 344,000,000 (Three Hundred Forty Four Million Rupiah), IDR 304,000,000 (Three Hundred Forty Four Million Rupiah) and IDR 304,000,000 (Three Hundred Forty Four Million Rupiah). These costs will be the contractor's profit.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Supply Chain Analysis of Traditional Fish Catches of Bagan Deli City Medan and Bagan Percut of Deli Serdang District Perawatan Preventif Mesin Pompa Air Penggunaan Metode Balanced Scorecard (BSC) untuk Pengukuran Kinerja pada UMKM XYZ Pemilihan Pemasok dan Alokasi Order Optimum pada Komoditas Hasil Laut Menggunakan Analytical Hierarchy Process dan Multi Objective Linear Programming Perancangan Tata Letak Pabrik Mie Lethek UD Garuda dengan Metode DBD, ALDEP, CORELAP dan MST
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1