{"title":"桩基工程延期的性能分析","authors":"Steven Shui, Andri Irfan Rifai, Mulia Pamadi","doi":"10.29138/ijebd.v6i1.2158","DOIUrl":null,"url":null,"abstract":"Purpose: Delays are common in construction projects. The term \"project delay\" refers to a project's completion date later than anticipated. Lack of performance by contractors or project managers in resolving issues can result in project delays. The factors that cause project delays must be considered to reduce delays. This study aims to examine the elements contributing to Batam island’s pile foundation construction delays. \nFindings: The factor of delays is an important key of the analysis to prevent delays in future projects \nDesign/methodology/approach: This research uses a case study at Batam Island. The analysis is done with SPSS 26 program. \nResearch limitations/implications: Analysis of delay caused by pile foundation in Batam island. \nPractical implications: Analysis of the delay caused by a project according to the result of the questionnaire. \nOriginality/value: Original Paper \nPaper type: A Case Study","PeriodicalId":53091,"journal":{"name":"IJEBD International Journal of Entrepreneurship and Business Development","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-01-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The Analysis Performance of Project Delays in Pile Foundation Work\",\"authors\":\"Steven Shui, Andri Irfan Rifai, Mulia Pamadi\",\"doi\":\"10.29138/ijebd.v6i1.2158\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose: Delays are common in construction projects. The term \\\"project delay\\\" refers to a project's completion date later than anticipated. Lack of performance by contractors or project managers in resolving issues can result in project delays. The factors that cause project delays must be considered to reduce delays. This study aims to examine the elements contributing to Batam island’s pile foundation construction delays. \\nFindings: The factor of delays is an important key of the analysis to prevent delays in future projects \\nDesign/methodology/approach: This research uses a case study at Batam Island. The analysis is done with SPSS 26 program. \\nResearch limitations/implications: Analysis of delay caused by pile foundation in Batam island. \\nPractical implications: Analysis of the delay caused by a project according to the result of the questionnaire. \\nOriginality/value: Original Paper \\nPaper type: A Case Study\",\"PeriodicalId\":53091,\"journal\":{\"name\":\"IJEBD International Journal of Entrepreneurship and Business Development\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-01-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IJEBD International Journal of Entrepreneurship and Business Development\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.29138/ijebd.v6i1.2158\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IJEBD International Journal of Entrepreneurship and Business Development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29138/ijebd.v6i1.2158","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

用途:建设项目的延误是很常见的。“项目延迟”是指项目完成日期晚于预期。承包商或项目经理在解决问题方面表现不佳可能导致项目延误。必须考虑导致项目延迟的因素,以减少延迟。本研究旨在探讨造成巴淡岛桩基施工延误的因素。研究结果:延误因素是分析防止未来项目延误的重要关键设计/方法/方法:本研究采用巴丹岛的案例研究。使用SPSS 26软件进行分析。研究局限/启示:巴淡岛桩基延误分析。实际意义:根据问卷调查的结果分析项目造成的延误。原创性/价值:原创论文论文类型:案例研究
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
The Analysis Performance of Project Delays in Pile Foundation Work
Purpose: Delays are common in construction projects. The term "project delay" refers to a project's completion date later than anticipated. Lack of performance by contractors or project managers in resolving issues can result in project delays. The factors that cause project delays must be considered to reduce delays. This study aims to examine the elements contributing to Batam island’s pile foundation construction delays. Findings: The factor of delays is an important key of the analysis to prevent delays in future projects Design/methodology/approach: This research uses a case study at Batam Island. The analysis is done with SPSS 26 program. Research limitations/implications: Analysis of delay caused by pile foundation in Batam island. Practical implications: Analysis of the delay caused by a project according to the result of the questionnaire. Originality/value: Original Paper Paper type: A Case Study
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
审稿时长
5 weeks
期刊最新文献
The Influence of Financial Literacy, Attitude toward Debt, Risk Perception, and Religiosity on Financial Satisfaction (Study on Bank Employees in East Java) Optimizing Customer Segments of SMEs by Transforming Business Model Canvas Application Failure Mode Effect Analysis for Risk Management in New Costumer Acceptance Project in Garment Industry with approaching Project Management Body of Knowledge The Effect of Online Customer Reviews on Purchase Intention With Customer Trust as A Variable in Purchase Decision on Sociolla Consumers Factors Influencing Tax Compliance Intention Among Self-Employed in Kelantan, Malaysia
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1