IT项目中的资源分配:使用进度优化

Michael A. Chilton
{"title":"IT项目中的资源分配:使用进度优化","authors":"Michael A. Chilton","doi":"10.12821/IJISPM020303","DOIUrl":null,"url":null,"abstract":"Resource allocation is the process of assigning resources to tasks throughout the life of a project. Despite sophisticated software packages devoted to keeping track of tasks, resources and resource assignments, it is often the case that project managers find some resources over-allocated and therefore unable to complete the assigned work in the allotted amount of time. Most scheduling software has provisions for leveling resources, but the techniques for doing so simply add time to the schedule and may cause delays in tasks that are critical to the project in meeting deadlines. This paper presents a software application that ensures that resources are properly balanced at the beginning of the project and eliminates the situation in which resources become over-allocated. It can be used in a multi-project environment and reused throughout the project as tasks, resource assignments and availability, and the project scope change. The application utilizes the bounded enumeration technique to formulate an optimal schedule for which both the task sequence and resource availability are taken into account. It is run on a database server to reduce the running time and make it a viable application for practitioners.","PeriodicalId":43984,"journal":{"name":"IJISPM-International Journal of Information Systems and Project Management","volume":null,"pages":null},"PeriodicalIF":2.2000,"publicationDate":"2022-02-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Resource allocation in IT projects: using schedule optimization\",\"authors\":\"Michael A. Chilton\",\"doi\":\"10.12821/IJISPM020303\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Resource allocation is the process of assigning resources to tasks throughout the life of a project. Despite sophisticated software packages devoted to keeping track of tasks, resources and resource assignments, it is often the case that project managers find some resources over-allocated and therefore unable to complete the assigned work in the allotted amount of time. Most scheduling software has provisions for leveling resources, but the techniques for doing so simply add time to the schedule and may cause delays in tasks that are critical to the project in meeting deadlines. This paper presents a software application that ensures that resources are properly balanced at the beginning of the project and eliminates the situation in which resources become over-allocated. It can be used in a multi-project environment and reused throughout the project as tasks, resource assignments and availability, and the project scope change. The application utilizes the bounded enumeration technique to formulate an optimal schedule for which both the task sequence and resource availability are taken into account. It is run on a database server to reduce the running time and make it a viable application for practitioners.\",\"PeriodicalId\":43984,\"journal\":{\"name\":\"IJISPM-International Journal of Information Systems and Project Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":2.2000,\"publicationDate\":\"2022-02-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IJISPM-International Journal of Information Systems and Project Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.12821/IJISPM020303\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IJISPM-International Journal of Information Systems and Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12821/IJISPM020303","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 2

摘要

资源分配是在项目的整个生命周期中将资源分配给任务的过程。尽管复杂的软件包致力于跟踪任务、资源和资源分配,但项目经理经常发现一些资源分配过度,因此无法在分配的时间内完成分配的工作。大多数调度软件都有平衡资源的规定,但是这样做的技术只是将时间添加到调度中,并且可能导致对项目在最后期限内完成至关重要的任务的延迟。本文介绍了一个软件应用程序,它确保资源在项目开始时得到适当的平衡,并消除了资源过度分配的情况。它可以在多项目环境中使用,并在整个项目中作为任务、资源分配和可用性以及项目范围变化而重用。应用程序利用有界枚举技术来制定一个同时考虑了任务序列和资源可用性的最优调度。它在数据库服务器上运行,以减少运行时间,并使其成为从业者的可行应用程序。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Resource allocation in IT projects: using schedule optimization
Resource allocation is the process of assigning resources to tasks throughout the life of a project. Despite sophisticated software packages devoted to keeping track of tasks, resources and resource assignments, it is often the case that project managers find some resources over-allocated and therefore unable to complete the assigned work in the allotted amount of time. Most scheduling software has provisions for leveling resources, but the techniques for doing so simply add time to the schedule and may cause delays in tasks that are critical to the project in meeting deadlines. This paper presents a software application that ensures that resources are properly balanced at the beginning of the project and eliminates the situation in which resources become over-allocated. It can be used in a multi-project environment and reused throughout the project as tasks, resource assignments and availability, and the project scope change. The application utilizes the bounded enumeration technique to formulate an optimal schedule for which both the task sequence and resource availability are taken into account. It is run on a database server to reduce the running time and make it a viable application for practitioners.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
6.30
自引率
18.20%
发文量
99
审稿时长
12 weeks
期刊最新文献
Digitalization of revenue mobilization in an emerging economy: the new Institutional Theory perspective Software developers reasoning behind adoption and use of software development methods – a systematic literature review The characteristics of successful military IT projects: a cross-country empirical study An agile portfolio management model for the insurance sector: the APMI model Towards a framework for developing visual analytics in supply chain environments
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1