{"title":"额尔比勒市公路建设项目工期评估及工期管理技术","authors":"Aksana Jihad Mohammed","doi":"10.31272/jeasd.27.4.7","DOIUrl":null,"url":null,"abstract":"Successful people utilize their time judiciously. The challenge of completing construction projects within the estimated time frame is the biggest concern among practitioners.     In this research two aspects have been highlighted, first; the most significant factor of time overrun in construction projects performed by Erbil Municipality during road construction. The second aspect is the time management methods held by the project team.  A random sampling technique was used to administer 126 questionnaires to professionals such as Project managers, Engineers, and contractors working on road construction projects for Erbil municipality.  On the other hand, a case study has been conducted for 70 constructed projects during 2018-2022 for the evaluation of time management techniques in road construction projects by identifying the process of monitoring, software packages that are used for that, the progress of work, and investigating how progress records are kept in Erbil City municipality projects. The results revealed that the most significant factor for time overrun was the economic crisis which led to the failure to pay contractors' dues in a timely manner, followed by the unreasonable time frame for the completion of projects. Used techniques and software packages for time management were identified It is revealed that there is no specific method for managing time. Multiple methods are used depending on the situation.","PeriodicalId":33282,"journal":{"name":"Journal of Engineering and Sustainable Development","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"EVALUATION OF TIME OVERRUNS AND TIME MANAGEMENT TECHNIQUES IN ROAD CONSTRUCTION PROJECTS IN ERBIL CITY\",\"authors\":\"Aksana Jihad Mohammed\",\"doi\":\"10.31272/jeasd.27.4.7\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Successful people utilize their time judiciously. The challenge of completing construction projects within the estimated time frame is the biggest concern among practitioners.     In this research two aspects have been highlighted, first; the most significant factor of time overrun in construction projects performed by Erbil Municipality during road construction. The second aspect is the time management methods held by the project team.  A random sampling technique was used to administer 126 questionnaires to professionals such as Project managers, Engineers, and contractors working on road construction projects for Erbil municipality.  On the other hand, a case study has been conducted for 70 constructed projects during 2018-2022 for the evaluation of time management techniques in road construction projects by identifying the process of monitoring, software packages that are used for that, the progress of work, and investigating how progress records are kept in Erbil City municipality projects. The results revealed that the most significant factor for time overrun was the economic crisis which led to the failure to pay contractors' dues in a timely manner, followed by the unreasonable time frame for the completion of projects. Used techniques and software packages for time management were identified It is revealed that there is no specific method for managing time. Multiple methods are used depending on the situation.\",\"PeriodicalId\":33282,\"journal\":{\"name\":\"Journal of Engineering and Sustainable Development\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Engineering and Sustainable Development\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31272/jeasd.27.4.7\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Engineering and Sustainable Development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31272/jeasd.27.4.7","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

成功人士明智地利用时间。在预计的时间范围内完成建设项目的挑战是从业者最关心的问题。在这项研究中,突出了两个方面:第一;埃尔比勒市在道路建设期间实施的建设项目中最重要的时间超支因素。第二个方面是项目团队掌握的时间管理方法。采用随机抽样技术,向埃尔比勒市道路建设项目的项目经理、工程师和承包商等专业人员发放了126份问卷。另一方面,在2018-2022年期间,对70个已建设项目进行了案例研究,通过确定监测过程、用于监测的软件包、工作进度,并调查埃尔比勒市市政项目的进度记录是如何保存的,来评估道路建设项目的时间管理技术。结果显示,造成工期超支的最重要因素是经济危机,经济危机导致承包商未能及时支付应付款,其次是项目完工时间框架不合理。确定了用于时间管理的技术和软件包。结果表明,没有具体的时间管理方法。根据情况使用多种方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
EVALUATION OF TIME OVERRUNS AND TIME MANAGEMENT TECHNIQUES IN ROAD CONSTRUCTION PROJECTS IN ERBIL CITY
Successful people utilize their time judiciously. The challenge of completing construction projects within the estimated time frame is the biggest concern among practitioners.     In this research two aspects have been highlighted, first; the most significant factor of time overrun in construction projects performed by Erbil Municipality during road construction. The second aspect is the time management methods held by the project team.  A random sampling technique was used to administer 126 questionnaires to professionals such as Project managers, Engineers, and contractors working on road construction projects for Erbil municipality.  On the other hand, a case study has been conducted for 70 constructed projects during 2018-2022 for the evaluation of time management techniques in road construction projects by identifying the process of monitoring, software packages that are used for that, the progress of work, and investigating how progress records are kept in Erbil City municipality projects. The results revealed that the most significant factor for time overrun was the economic crisis which led to the failure to pay contractors' dues in a timely manner, followed by the unreasonable time frame for the completion of projects. Used techniques and software packages for time management were identified It is revealed that there is no specific method for managing time. Multiple methods are used depending on the situation.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
0.70
自引率
0.00%
发文量
74
审稿时长
50 weeks
期刊最新文献
A Review of Biogas Production from Small-Scale Anaerobic Digestion Plants Performance Assessments of Direct Contact Serpentine Tube Based Photovoltaic Thermal Module: An Experimental Comparison Comparative Performance of Point-to-Point Multiple Input Multiple Output System under Weibull and Rayleigh Fading Channels Improvement of Air Compressor Cooling with Intercooler Fine Pruning Environmental Monitoring of Land Use/ Land Cover by Integrating Remote Sensing and Machine Learning Algorithms
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1