{"title":"灌溉水利用改善计划(P3-TGAI)中Swakelola项目调度优化","authors":"Musa Mardwiana Thohir, Anak Agung Bagus Dinariyana Dwi Putranta, A. Sudiarno","doi":"10.12962/j23546026.y2020i6.11161","DOIUrl":null,"url":null,"abstract":"—The Irrigation Water Utilization Improvement Program (P3-TGAI) is a program implemented by the Balai Besar Wilayah Sungai Brantas (BBWS) which aims to improve irrigation networks by building tertiary/small canals. Kediri, Trenggalek, Tulungagung, Blitar are one of the regional packages that received the program. In the implementation of P3-TGAI in the area, there were problems with the completion of the program. Monitoring and controlling program are needed to ensure the implementation timeliness. Critical Path Method (CPM) analysis is a method used to estimate the minimum duration of a project by connecting each activity and determine the duration of each activity. This method is carried out through the stages of collecting secondary and primary data to identify internal and external factors that affect the speed of the program. Project management analysis method is used to approach the monitoring and controlling program so that it is timely. The expected result from CPM analysis is to get an optimal program design schedule for the implementation of P3-TGAI.","PeriodicalId":14533,"journal":{"name":"IPTEK Journal of Proceedings Series","volume":"24 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-10-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Scheduling Optimization of Swakelola Projects in The Irrigation Water Utilization Improvement Program (P3-TGAI)\",\"authors\":\"Musa Mardwiana Thohir, Anak Agung Bagus Dinariyana Dwi Putranta, A. Sudiarno\",\"doi\":\"10.12962/j23546026.y2020i6.11161\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"—The Irrigation Water Utilization Improvement Program (P3-TGAI) is a program implemented by the Balai Besar Wilayah Sungai Brantas (BBWS) which aims to improve irrigation networks by building tertiary/small canals. Kediri, Trenggalek, Tulungagung, Blitar are one of the regional packages that received the program. In the implementation of P3-TGAI in the area, there were problems with the completion of the program. Monitoring and controlling program are needed to ensure the implementation timeliness. Critical Path Method (CPM) analysis is a method used to estimate the minimum duration of a project by connecting each activity and determine the duration of each activity. This method is carried out through the stages of collecting secondary and primary data to identify internal and external factors that affect the speed of the program. Project management analysis method is used to approach the monitoring and controlling program so that it is timely. The expected result from CPM analysis is to get an optimal program design schedule for the implementation of P3-TGAI.\",\"PeriodicalId\":14533,\"journal\":{\"name\":\"IPTEK Journal of Proceedings Series\",\"volume\":\"24 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-10-15\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"IPTEK Journal of Proceedings Series\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.12962/j23546026.y2020i6.11161\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"IPTEK Journal of Proceedings Series","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12962/j23546026.y2020i6.11161","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
摘要
-灌溉用水利用改善计划(P3-TGAI)是由巴莱州务大臣Wilayah Sungai Brantas (BBWS)实施的一项计划,旨在通过建设三级/小型运河来改善灌溉网络。Kediri, trengalek, Tulungagung, Blitar是接受该计划的区域包之一。在该地区实施P3-TGAI的过程中,项目的完成存在问题。需要有监控程序来保证实施的及时性。关键路径法(Critical Path Method, CPM)分析是一种通过连接各个活动来估计项目最小持续时间并确定每个活动持续时间的方法。该方法是通过收集次要和原始数据的阶段来确定影响程序速度的内部和外部因素。采用项目管理分析方法对监控方案进行分析,使其具有及时性。CPM分析的预期结果是为P3-TGAI的实现提供一个最优的程序设计时间表。
Scheduling Optimization of Swakelola Projects in The Irrigation Water Utilization Improvement Program (P3-TGAI)
—The Irrigation Water Utilization Improvement Program (P3-TGAI) is a program implemented by the Balai Besar Wilayah Sungai Brantas (BBWS) which aims to improve irrigation networks by building tertiary/small canals. Kediri, Trenggalek, Tulungagung, Blitar are one of the regional packages that received the program. In the implementation of P3-TGAI in the area, there were problems with the completion of the program. Monitoring and controlling program are needed to ensure the implementation timeliness. Critical Path Method (CPM) analysis is a method used to estimate the minimum duration of a project by connecting each activity and determine the duration of each activity. This method is carried out through the stages of collecting secondary and primary data to identify internal and external factors that affect the speed of the program. Project management analysis method is used to approach the monitoring and controlling program so that it is timely. The expected result from CPM analysis is to get an optimal program design schedule for the implementation of P3-TGAI.