{"title":"公共建筑建设项目风险管理实践研究——以东沃勒加区为例","authors":"Zelalem Mebrate","doi":"10.11648/J.AJCE.20210903.12","DOIUrl":null,"url":null,"abstract":"This research work was tries to study the risk management practice on public building construction projects and aims to identify the level that use of risk management practice especially in the public building. The data collection method was a combination of interview and questionnaire. Samples were purposively selected from clients, consultants, and contractors representatives who are now actively participating in public building construction projects. For this study, the data was collected using both primary and secondary sources. Depending on the data that was gathered from the respondent to test the level of awareness, identifying the Risk that affect the performance of public building construction project and major risk management practice on public building construction project are considered and the RII was used to rank the factors. This data was analyzed using SPSS of version 22 to perform descriptive statistics. A total of 75 questionnaires were targeted to be distributed and out of those 50 which is 66.67% are successfully responded. The finding from this study revealed that, about (52%) of the project progress is lagging from the schedule. Regarding the awareness of the risk management, (94%) of the respondents where confirmed that they have awareness of risk management ideologies and they are confident enough to implement their knowledge while, (6%) of them have no concept about the risk management. The top five risks that affect the performance of construction project have been identified and ranked. Accordingly; market condition, unexpected inflation, local taxes, inadequate production of raw materials, and the economic condition of country are the top five identified associated project risks.","PeriodicalId":7606,"journal":{"name":"American Journal of Civil Engineering","volume":"70 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-05-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Study on Risk Management Practices on Public Building Construction Project: In Case of Eastern Wollega Zone\",\"authors\":\"Zelalem Mebrate\",\"doi\":\"10.11648/J.AJCE.20210903.12\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"This research work was tries to study the risk management practice on public building construction projects and aims to identify the level that use of risk management practice especially in the public building. The data collection method was a combination of interview and questionnaire. Samples were purposively selected from clients, consultants, and contractors representatives who are now actively participating in public building construction projects. For this study, the data was collected using both primary and secondary sources. Depending on the data that was gathered from the respondent to test the level of awareness, identifying the Risk that affect the performance of public building construction project and major risk management practice on public building construction project are considered and the RII was used to rank the factors. This data was analyzed using SPSS of version 22 to perform descriptive statistics. A total of 75 questionnaires were targeted to be distributed and out of those 50 which is 66.67% are successfully responded. The finding from this study revealed that, about (52%) of the project progress is lagging from the schedule. Regarding the awareness of the risk management, (94%) of the respondents where confirmed that they have awareness of risk management ideologies and they are confident enough to implement their knowledge while, (6%) of them have no concept about the risk management. The top five risks that affect the performance of construction project have been identified and ranked. Accordingly; market condition, unexpected inflation, local taxes, inadequate production of raw materials, and the economic condition of country are the top five identified associated project risks.\",\"PeriodicalId\":7606,\"journal\":{\"name\":\"American Journal of Civil Engineering\",\"volume\":\"70 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-05-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"American Journal of Civil Engineering\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.11648/J.AJCE.20210903.12\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"American Journal of Civil Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.11648/J.AJCE.20210903.12","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Study on Risk Management Practices on Public Building Construction Project: In Case of Eastern Wollega Zone
This research work was tries to study the risk management practice on public building construction projects and aims to identify the level that use of risk management practice especially in the public building. The data collection method was a combination of interview and questionnaire. Samples were purposively selected from clients, consultants, and contractors representatives who are now actively participating in public building construction projects. For this study, the data was collected using both primary and secondary sources. Depending on the data that was gathered from the respondent to test the level of awareness, identifying the Risk that affect the performance of public building construction project and major risk management practice on public building construction project are considered and the RII was used to rank the factors. This data was analyzed using SPSS of version 22 to perform descriptive statistics. A total of 75 questionnaires were targeted to be distributed and out of those 50 which is 66.67% are successfully responded. The finding from this study revealed that, about (52%) of the project progress is lagging from the schedule. Regarding the awareness of the risk management, (94%) of the respondents where confirmed that they have awareness of risk management ideologies and they are confident enough to implement their knowledge while, (6%) of them have no concept about the risk management. The top five risks that affect the performance of construction project have been identified and ranked. Accordingly; market condition, unexpected inflation, local taxes, inadequate production of raw materials, and the economic condition of country are the top five identified associated project risks.