双排桩挡土结构在电力工程中的应用

Hai-rong Ding, Jun-yong Rao
{"title":"双排桩挡土结构在电力工程中的应用","authors":"Hai-rong Ding, Jun-yong Rao","doi":"10.1109/ICETCE.2011.5776240","DOIUrl":null,"url":null,"abstract":"Advantage and analysis models of double-row piles retaining structure are described in this paper. Based on project practice of double-row piles retaining structure in Huaneng Fuzhou power plant, multi-schemes of supporting and retaining structure have been contrasted and the optimal scheme is recommended. To deal with the soil loss between piles, scheme of small interval and small diameter pipes shall be employed and jet grouting shall be used to improve the soil between piles, so that the soil shall be self-stable on the front surface. The success of the project ensures the operation of the existing power plant and construction of the building plant, which is one avail application case for reference of similar project.","PeriodicalId":6340,"journal":{"name":"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)","volume":"258 1","pages":"5782-5786"},"PeriodicalIF":0.0000,"publicationDate":"2011-04-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Application of double-row piles retaining structure in electric power engineering\",\"authors\":\"Hai-rong Ding, Jun-yong Rao\",\"doi\":\"10.1109/ICETCE.2011.5776240\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Advantage and analysis models of double-row piles retaining structure are described in this paper. Based on project practice of double-row piles retaining structure in Huaneng Fuzhou power plant, multi-schemes of supporting and retaining structure have been contrasted and the optimal scheme is recommended. To deal with the soil loss between piles, scheme of small interval and small diameter pipes shall be employed and jet grouting shall be used to improve the soil between piles, so that the soil shall be self-stable on the front surface. The success of the project ensures the operation of the existing power plant and construction of the building plant, which is one avail application case for reference of similar project.\",\"PeriodicalId\":6340,\"journal\":{\"name\":\"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)\",\"volume\":\"258 1\",\"pages\":\"5782-5786\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-04-22\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICETCE.2011.5776240\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2011 International Conference on Electric Technology and Civil Engineering (ICETCE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICETCE.2011.5776240","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

介绍了双排桩支护结构的优点及分析模型。结合华能福州电厂双排桩支护结构的工程实践,对多种支护结构方案进行了对比,并推荐了最优方案。针对桩间土的流失,采用小间距、小管径管道方案,并采用喷射注浆b应使用对桩间土进行改良,使桩间土在前表面自稳。工程的成功为现有电厂的正常运行和新建电厂的建设提供了保障,为类似工程提供了有益的借鉴。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Application of double-row piles retaining structure in electric power engineering
Advantage and analysis models of double-row piles retaining structure are described in this paper. Based on project practice of double-row piles retaining structure in Huaneng Fuzhou power plant, multi-schemes of supporting and retaining structure have been contrasted and the optimal scheme is recommended. To deal with the soil loss between piles, scheme of small interval and small diameter pipes shall be employed and jet grouting shall be used to improve the soil between piles, so that the soil shall be self-stable on the front surface. The success of the project ensures the operation of the existing power plant and construction of the building plant, which is one avail application case for reference of similar project.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Analying the transverse distribution coefficient of the cracking hollow slab bridge Thermodynamics of MgO-MgCl2-H2O system A nonlinear analysis for the lateral girder response of footbridges induced by pedestrians Research status and development of theoretical calculation method on surrounding rock pressure of tunnel Influence of mix proportion of asphalt mixture on Marshall Index
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1