基于时间研究分析的土方工程效率与效益

M. Šopić, Antonio Bogdan, I. Marović
{"title":"基于时间研究分析的土方工程效率与效益","authors":"M. Šopić, Antonio Bogdan, I. Marović","doi":"10.5592/co/senet.2022.22","DOIUrl":null,"url":null,"abstract":"Construction generally takes place in very variable and dynamic conditions due to the presence of machinery, transport of materials, movement of workers, and the progress of construction. In order to solve the problem of site variable and dynamic conditions, two major research topics may stand out, more precisely, off-site performance planning and on-site performance tracking and monitoring. Earthworks commonly involve extensive utilization of various construction machines, mainly excavators and tipper (or dump) trucks. Tracking and monitoring of earthworks, based on collected quality data from the construction site, are necessary to detect discrepancies between the planned and actual work efficiency of construction machinery. The main topic of this paper is the time study analysis of one of the standard technological processes in earthworks – loading and transporting materials by tipper trucks. On-site data were obtained using the stopwatch method with the purpose of determining the actual work efficiency of the tipper truck. This paper aims to propose a research framework for clear insight into the progress effectiveness of earthworks and the actual work efficiency of the tipper truck. The purpose of applying the research framework is to form a base for tracking and monitoring the work of tipper trucks so the right decisions can be made in a timely manner. Such can enhance earthworks progress by using the appropriate number of tipper trucks and their better utilization.","PeriodicalId":64912,"journal":{"name":"建设监理","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-07-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Efficiency Versus Efectiveness in Earthworks Based on Time Study Analysis\",\"authors\":\"M. Šopić, Antonio Bogdan, I. Marović\",\"doi\":\"10.5592/co/senet.2022.22\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Construction generally takes place in very variable and dynamic conditions due to the presence of machinery, transport of materials, movement of workers, and the progress of construction. In order to solve the problem of site variable and dynamic conditions, two major research topics may stand out, more precisely, off-site performance planning and on-site performance tracking and monitoring. Earthworks commonly involve extensive utilization of various construction machines, mainly excavators and tipper (or dump) trucks. Tracking and monitoring of earthworks, based on collected quality data from the construction site, are necessary to detect discrepancies between the planned and actual work efficiency of construction machinery. The main topic of this paper is the time study analysis of one of the standard technological processes in earthworks – loading and transporting materials by tipper trucks. On-site data were obtained using the stopwatch method with the purpose of determining the actual work efficiency of the tipper truck. This paper aims to propose a research framework for clear insight into the progress effectiveness of earthworks and the actual work efficiency of the tipper truck. The purpose of applying the research framework is to form a base for tracking and monitoring the work of tipper trucks so the right decisions can be made in a timely manner. Such can enhance earthworks progress by using the appropriate number of tipper trucks and their better utilization.\",\"PeriodicalId\":64912,\"journal\":{\"name\":\"建设监理\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-06\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"建设监理\",\"FirstCategoryId\":\"1087\",\"ListUrlMain\":\"https://doi.org/10.5592/co/senet.2022.22\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"建设监理","FirstCategoryId":"1087","ListUrlMain":"https://doi.org/10.5592/co/senet.2022.22","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

由于机械的存在、材料的运输、工人的移动和施工的进度,施工通常发生在非常多变和动态的条件下。为了解决现场可变和动态条件的问题,两大研究课题可能会脱颖而出,更准确地说,场外性能规划和现场性能跟踪与监测。土方工程通常涉及大量使用各种建筑机械,主要是挖掘机和自卸车。根据从施工现场收集的质量数据,对土方工程进行跟踪和监测,以发现工程机械的计划工作效率与实际工作效率之间的差异。本文的主要课题是对土方工程中自卸车装卸物料这一标准工艺流程进行时间研究分析。采用秒表法获取现场数据,以确定自卸车的实际工作效率。本文旨在提出一个研究框架,以便清晰地了解土方工程的进度有效性和自卸车的实际工作效率。应用研究框架的目的是为跟踪和监测自卸车的工作形成一个基础,以便及时做出正确的决策。使用适当数目的自卸车及善用自卸车,可加快土方工程的进度。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Efficiency Versus Efectiveness in Earthworks Based on Time Study Analysis
Construction generally takes place in very variable and dynamic conditions due to the presence of machinery, transport of materials, movement of workers, and the progress of construction. In order to solve the problem of site variable and dynamic conditions, two major research topics may stand out, more precisely, off-site performance planning and on-site performance tracking and monitoring. Earthworks commonly involve extensive utilization of various construction machines, mainly excavators and tipper (or dump) trucks. Tracking and monitoring of earthworks, based on collected quality data from the construction site, are necessary to detect discrepancies between the planned and actual work efficiency of construction machinery. The main topic of this paper is the time study analysis of one of the standard technological processes in earthworks – loading and transporting materials by tipper trucks. On-site data were obtained using the stopwatch method with the purpose of determining the actual work efficiency of the tipper truck. This paper aims to propose a research framework for clear insight into the progress effectiveness of earthworks and the actual work efficiency of the tipper truck. The purpose of applying the research framework is to form a base for tracking and monitoring the work of tipper trucks so the right decisions can be made in a timely manner. Such can enhance earthworks progress by using the appropriate number of tipper trucks and their better utilization.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
8035
期刊最新文献
An Integrated Solution for increased Circularity in Buidings: A Method Framework for Research on Communication in Multicultural Projects: The Case of Pelješac Bridge What are the Special Usances in Construction? Impact of Project Manager and Team Member Characteristics on Their Personal Growth and Satisfaction The Importance of Urban Spatial Grid Data in the Building Valuation Process
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1