{"title":"收费公路建设项目延误风险模型的概念框架","authors":"G. A. Pratama, Y. Latief","doi":"10.31763/aet.v1i2.676","DOIUrl":null,"url":null,"abstract":"In the realization of the medium-term development plan in 2014-2019 (RPJMN), toll road construction development was only reached 51 percent. construction projects had complex and dynamic nature, which caused delays, construction risk assessment that considers risk as a system was done before, for example, using techniques such as SD, Fuzzy DEMATEL, STEEP-SD, DEMATEL-ANP, and SD-DEMATEL, but the technique still has some shortcomings. in indonesia, research related to this matter is still rarely done, to address this concern, we propose a conceptual framework that can be used to develop a delay risk model for toll road construction project especially in indonesia. for this purpose, we introduce the system dynamic-fuzzy dematel-anp (sd-fdanp) method. the results of the development of the sd-fdanp method can be used as a guideline that can help achieve behavioral knowledge of delays and the success of risk assessment in toll road infrastructure development projects.","PeriodicalId":21010,"journal":{"name":"Research Journal of Applied Sciences, Engineering and Technology","volume":"25 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-04-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Developing a delay risk model for toll road construction project: A conceptual framework\",\"authors\":\"G. A. Pratama, Y. Latief\",\"doi\":\"10.31763/aet.v1i2.676\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In the realization of the medium-term development plan in 2014-2019 (RPJMN), toll road construction development was only reached 51 percent. construction projects had complex and dynamic nature, which caused delays, construction risk assessment that considers risk as a system was done before, for example, using techniques such as SD, Fuzzy DEMATEL, STEEP-SD, DEMATEL-ANP, and SD-DEMATEL, but the technique still has some shortcomings. in indonesia, research related to this matter is still rarely done, to address this concern, we propose a conceptual framework that can be used to develop a delay risk model for toll road construction project especially in indonesia. for this purpose, we introduce the system dynamic-fuzzy dematel-anp (sd-fdanp) method. the results of the development of the sd-fdanp method can be used as a guideline that can help achieve behavioral knowledge of delays and the success of risk assessment in toll road infrastructure development projects.\",\"PeriodicalId\":21010,\"journal\":{\"name\":\"Research Journal of Applied Sciences, Engineering and Technology\",\"volume\":\"25 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-04-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Research Journal of Applied Sciences, Engineering and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31763/aet.v1i2.676\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Research Journal of Applied Sciences, Engineering and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31763/aet.v1i2.676","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Developing a delay risk model for toll road construction project: A conceptual framework
In the realization of the medium-term development plan in 2014-2019 (RPJMN), toll road construction development was only reached 51 percent. construction projects had complex and dynamic nature, which caused delays, construction risk assessment that considers risk as a system was done before, for example, using techniques such as SD, Fuzzy DEMATEL, STEEP-SD, DEMATEL-ANP, and SD-DEMATEL, but the technique still has some shortcomings. in indonesia, research related to this matter is still rarely done, to address this concern, we propose a conceptual framework that can be used to develop a delay risk model for toll road construction project especially in indonesia. for this purpose, we introduce the system dynamic-fuzzy dematel-anp (sd-fdanp) method. the results of the development of the sd-fdanp method can be used as a guideline that can help achieve behavioral knowledge of delays and the success of risk assessment in toll road infrastructure development projects.