尼日尔三角洲发展委员会在尼日利亚尼日尔三角洲地区授予的公路完工项目超时的定性研究

F. Ogbeide, J. Ehiorobo, O. Izinyon, I. Ilaboya
{"title":"尼日尔三角洲发展委员会在尼日利亚尼日尔三角洲地区授予的公路完工项目超时的定性研究","authors":"F. Ogbeide, J. Ehiorobo, O. Izinyon, I. Ilaboya","doi":"10.36263/nijest.2021.01.0269","DOIUrl":null,"url":null,"abstract":"Time overrun of completed road projects awarded by the Niger Delta Development Commission (NDDC) in the Niger Delta Region of Nigeria from its inception in 2000 up to 2015 was studied. Out of 3315 roads awarded, only 1081 roads representing 31.65 percent were completed within the review period. The qualitative study was carried out on randomly selected completed 162 road projects for analysis, and a conceptual model of time series was developed. In developing the regression model, both dependent and independent variables were subjected to normality tests assessed by skewness coefficient, kurtosis value, Jarque-Bera test, residual probability plot, heteroscedasticity test and the variance inflation factor. Also, with knowledge of total road projects awarded by the Commission, it is now possible to predict proportions of roads experiencing schedule overruns.","PeriodicalId":11002,"journal":{"name":"Day 1 Tue, March 23, 2021","volume":"111 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-02-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A Qualitative Study of Time Overrun of Completed Road Projects Awarded by the Niger Delta Development Commission in the Niger Delta Region of Nigeria\",\"authors\":\"F. Ogbeide, J. Ehiorobo, O. Izinyon, I. Ilaboya\",\"doi\":\"10.36263/nijest.2021.01.0269\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Time overrun of completed road projects awarded by the Niger Delta Development Commission (NDDC) in the Niger Delta Region of Nigeria from its inception in 2000 up to 2015 was studied. Out of 3315 roads awarded, only 1081 roads representing 31.65 percent were completed within the review period. The qualitative study was carried out on randomly selected completed 162 road projects for analysis, and a conceptual model of time series was developed. In developing the regression model, both dependent and independent variables were subjected to normality tests assessed by skewness coefficient, kurtosis value, Jarque-Bera test, residual probability plot, heteroscedasticity test and the variance inflation factor. Also, with knowledge of total road projects awarded by the Commission, it is now possible to predict proportions of roads experiencing schedule overruns.\",\"PeriodicalId\":11002,\"journal\":{\"name\":\"Day 1 Tue, March 23, 2021\",\"volume\":\"111 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-02-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Tue, March 23, 2021\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36263/nijest.2021.01.0269\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Tue, March 23, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36263/nijest.2021.01.0269","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

研究了尼日尔三角洲发展委员会(NDDC)在尼日利亚尼日尔三角洲地区从2000年成立到2015年完成的道路项目的超时情况。在被授予的3315条道路中,只有1081条道路在审查期内完工,占31.65%。随机选取162个已竣工公路项目进行定性研究,建立时间序列概念模型。在建立回归模型时,因变量和自变量均通过偏度系数、峰度值、Jarque-Bera检验、残差概率图、异方差检验和方差膨胀因子进行正态性检验。此外,由于了解了委员会批出的全部道路项目,现在可以预测出现工期超支的道路的比例。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
A Qualitative Study of Time Overrun of Completed Road Projects Awarded by the Niger Delta Development Commission in the Niger Delta Region of Nigeria
Time overrun of completed road projects awarded by the Niger Delta Development Commission (NDDC) in the Niger Delta Region of Nigeria from its inception in 2000 up to 2015 was studied. Out of 3315 roads awarded, only 1081 roads representing 31.65 percent were completed within the review period. The qualitative study was carried out on randomly selected completed 162 road projects for analysis, and a conceptual model of time series was developed. In developing the regression model, both dependent and independent variables were subjected to normality tests assessed by skewness coefficient, kurtosis value, Jarque-Bera test, residual probability plot, heteroscedasticity test and the variance inflation factor. Also, with knowledge of total road projects awarded by the Commission, it is now possible to predict proportions of roads experiencing schedule overruns.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Design an Adaptive Hybrid Approach for Genetic Algorithm to Detect Effective Malware Detection in Android Division Comparison of Stock Price Prediction Models using Pre-trained Neural Networks Efficient Two Stage Identification for Face mask detection using Multiclass Deep Learning Approach Blockchain Framework for Communication between Vehicle through IoT Devices and Sensors Machine Learning Algorithms Performance Analysis for VLSI IC Design
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1