基于shapley值的多事件干扰延迟索赔计算方法

Donghong Cui, L. Yao
{"title":"基于shapley值的多事件干扰延迟索赔计算方法","authors":"Donghong Cui, L. Yao","doi":"10.1109/ICIEEM.2009.5344560","DOIUrl":null,"url":null,"abstract":"As an important measure for parties of the contract to protect their own interests, project claim is the core of project contract management. For claims of time delay under multi-agent and multi-event interference, it is difficult to assess the responsibility. To solve this problem, this paper presents a new analytical method based on Shapley value, and brings forward a new parameter called Correction Factor to denote the affecting degree of every interference event. On the basis of this method, project delay responsibility is allotted to each single responsible activity, and then allotted to both owner and contractor in each single responsible activity. Finally, the responsibility is reallotted to the responsible parties through Correction Factor. This method takes into account the impact of the interference event, and makes the responsibility-sharing more equitable.","PeriodicalId":6326,"journal":{"name":"2009 16th International Conference on Industrial Engineering and Engineering Management","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2009-12-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Calculation method of delay claims with multi-event interference based on shapley value\",\"authors\":\"Donghong Cui, L. Yao\",\"doi\":\"10.1109/ICIEEM.2009.5344560\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"As an important measure for parties of the contract to protect their own interests, project claim is the core of project contract management. For claims of time delay under multi-agent and multi-event interference, it is difficult to assess the responsibility. To solve this problem, this paper presents a new analytical method based on Shapley value, and brings forward a new parameter called Correction Factor to denote the affecting degree of every interference event. On the basis of this method, project delay responsibility is allotted to each single responsible activity, and then allotted to both owner and contractor in each single responsible activity. Finally, the responsibility is reallotted to the responsible parties through Correction Factor. This method takes into account the impact of the interference event, and makes the responsibility-sharing more equitable.\",\"PeriodicalId\":6326,\"journal\":{\"name\":\"2009 16th International Conference on Industrial Engineering and Engineering Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2009-12-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2009 16th International Conference on Industrial Engineering and Engineering Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICIEEM.2009.5344560\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 16th International Conference on Industrial Engineering and Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICIEEM.2009.5344560","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

工程索赔作为合同当事人维护自身利益的重要手段,是工程合同管理的核心。对于多智能体和多事件干扰下的时间延迟索赔,其责任评估较为困难。为了解决这一问题,本文提出了一种新的基于Shapley值的分析方法,并提出了一个新的参数“校正因子”来表示每个干扰事件的影响程度。在此基础上,将项目延迟责任分配给每个单独的责任活动,然后在每个单独的责任活动中分配给业主和承包商。最后,通过修正因子将责任重新分配给责任方。该方法考虑了干扰事件的影响,使责任分担更加公平。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Calculation method of delay claims with multi-event interference based on shapley value
As an important measure for parties of the contract to protect their own interests, project claim is the core of project contract management. For claims of time delay under multi-agent and multi-event interference, it is difficult to assess the responsibility. To solve this problem, this paper presents a new analytical method based on Shapley value, and brings forward a new parameter called Correction Factor to denote the affecting degree of every interference event. On the basis of this method, project delay responsibility is allotted to each single responsible activity, and then allotted to both owner and contractor in each single responsible activity. Finally, the responsibility is reallotted to the responsible parties through Correction Factor. This method takes into account the impact of the interference event, and makes the responsibility-sharing more equitable.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Binary search tree visualization algorithm Dynamic alliance partner selection and its negotiation strategy based on agent and resources Research on reverse logistics-oriented multisources inventory control model The syncretism of capital structure theory: An explanation from adjustment speed of capital structure Research on the security model for e-business process management
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1