{"title":"Is This Cost Estimate Reliable? -- The Relationship between Homogeneity of Analogues and Estimation Reliability","authors":"Naoki Ohsugi, Akito Monden, Nahomi Kikuchi, Mike Barker, Masateru Tsunoda, Takeshi Kakimoto, Ken-ichi Matsumoto","doi":"10.1109/ESEM.2007.31","DOIUrl":null,"url":null,"abstract":"Analogy-based cost estimation provides a useful and intuitive means to support decision making in software project management. It derives a cost estimate required for completing a project from information about similar past projects, namely the analogues. While on average this method provides a relatively accurate cost estimate there remains a possibility of large estimation errors. In this paper, we empirically tested the hypothesis that \"using more homogeneous analogues produces a more reliable cost estimate\" using a software engineering data repository established by the software engineering center (SEC), Information-technology Promotion Agency, Japan. This testing showed that low and high homogeneity projects had a large variation in estimation reliability. For instance, the difference was 22.9% (p = 0.021) in terms of percentage to get accurate estimates (better than Median of Magnitude of Relative Error).","PeriodicalId":124420,"journal":{"name":"First International Symposium on Empirical Software Engineering and Measurement (ESEM 2007)","volume":"2 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-09-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"10","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"First International Symposium on Empirical Software Engineering and Measurement (ESEM 2007)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ESEM.2007.31","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 10
Abstract
Analogy-based cost estimation provides a useful and intuitive means to support decision making in software project management. It derives a cost estimate required for completing a project from information about similar past projects, namely the analogues. While on average this method provides a relatively accurate cost estimate there remains a possibility of large estimation errors. In this paper, we empirically tested the hypothesis that "using more homogeneous analogues produces a more reliable cost estimate" using a software engineering data repository established by the software engineering center (SEC), Information-technology Promotion Agency, Japan. This testing showed that low and high homogeneity projects had a large variation in estimation reliability. For instance, the difference was 22.9% (p = 0.021) in terms of percentage to get accurate estimates (better than Median of Magnitude of Relative Error).