Muhammad Yusuf Falah, Adib Muhammad Arrasyid, A. Ulfa, Rizal Zulfiqri Ahmad, Jimmy Trio Putra
{"title":"DAMPAK DISTRIBUTED ENERGY RESOURCES TERHADAP PROFIL TEGANGAN DAN RUGI DAYA PENYULANG BANTUL 05","authors":"Muhammad Yusuf Falah, Adib Muhammad Arrasyid, A. Ulfa, Rizal Zulfiqri Ahmad, Jimmy Trio Putra","doi":"10.21831/jee.v5i2.41090","DOIUrl":null,"url":null,"abstract":"ABSTRACT:To realize Indonesia's commitment to cut greenhouse effect, it is important to use environmentally friendly vehicles. On August 12, 2019, the Presidential Regulation on the velocity of Battery-Based Electric Motor Vehicle Program for land vehicle as a sign of the seriousness of the government applying this vehicle. This research is specific in terms of the provision of Public Electric Vehicle Charging Station (SPKLU) in Bantul refinery area, Yogyakarta after the installation of Photovoltaic (PV) plant as Distributed Energy Resources (DER). This study used a simulation of the Open Distribution System Simulator (OpenDSS) software distribution network in analyzing the comparison of voltage profiles and power losses before and after spklu installation. By optimizing the placement of SPKLU using Flower Pollination Algorithm (FPA) method using Matlab software that results in spklu placement on bus 58 by 300 kW, bus 37 by 301 kW, and bus 36 by 300 kW. The voltage profile changed from 0.9695 p.u to 0.9688 p.u and power losses from 53.3 kW to 56.1 kW.ABSTRAK:Untuk mewujudkan tanggungjawab Indonesia dalam mengurangi efek rumah kaca maka harus menggunakan angkutan ramah lingkungan. Pada tanggal 12 Agustus 2019 telah disahkan Perpres Percepatan Program Kendaraan Bermotor Listrik Berbasis Baterai sebagai transportasi jalan merupakan tanda seriusnya pemerintah mengaplikasikan kendaraan ini. Penelitian ini spesifik pada hal penyediaan Stasiun Pengisian Kendaraan Listrik Umum (SPKLU) pada area penyulang Bantul, Yogyakarta setelah pemasangan pembangkit Photovoltaic (PV) sebagai Distributed Energy Resources (DER). Penelitian ini menggunakan simulasi jaringan distribusi software Open Distribution System Simulator (OpenDSS) untuk mempelajari perbandingan profil tegangan dan rugi daya sebelum dan sesudah pengaplikasian SPKLU. Dengan optimasi penempatan SPKLU menggunakan metode Flower Pollination Algorithm (FPA) menggunakan software Matlab yang menghasilkan penempatan SPKLU pada bus 58 sebesar 300 kW, bus 37 sebesar 301 kW, dan bus 36 sebesar 300 kW. Profil tegangan berubah dari 0,9695 p.u menjadi 0,9688 p.u dan rugi-rugi daya dari 53,3 kW menjadi 56,1 kW.","PeriodicalId":294346,"journal":{"name":"Jurnal Edukasi Elektro","volume":"32 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-11-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Edukasi Elektro","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21831/jee.v5i2.41090","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
Abstract
ABSTRACT:To realize Indonesia's commitment to cut greenhouse effect, it is important to use environmentally friendly vehicles. On August 12, 2019, the Presidential Regulation on the velocity of Battery-Based Electric Motor Vehicle Program for land vehicle as a sign of the seriousness of the government applying this vehicle. This research is specific in terms of the provision of Public Electric Vehicle Charging Station (SPKLU) in Bantul refinery area, Yogyakarta after the installation of Photovoltaic (PV) plant as Distributed Energy Resources (DER). This study used a simulation of the Open Distribution System Simulator (OpenDSS) software distribution network in analyzing the comparison of voltage profiles and power losses before and after spklu installation. By optimizing the placement of SPKLU using Flower Pollination Algorithm (FPA) method using Matlab software that results in spklu placement on bus 58 by 300 kW, bus 37 by 301 kW, and bus 36 by 300 kW. The voltage profile changed from 0.9695 p.u to 0.9688 p.u and power losses from 53.3 kW to 56.1 kW.ABSTRAK:Untuk mewujudkan tanggungjawab Indonesia dalam mengurangi efek rumah kaca maka harus menggunakan angkutan ramah lingkungan. Pada tanggal 12 Agustus 2019 telah disahkan Perpres Percepatan Program Kendaraan Bermotor Listrik Berbasis Baterai sebagai transportasi jalan merupakan tanda seriusnya pemerintah mengaplikasikan kendaraan ini. Penelitian ini spesifik pada hal penyediaan Stasiun Pengisian Kendaraan Listrik Umum (SPKLU) pada area penyulang Bantul, Yogyakarta setelah pemasangan pembangkit Photovoltaic (PV) sebagai Distributed Energy Resources (DER). Penelitian ini menggunakan simulasi jaringan distribusi software Open Distribution System Simulator (OpenDSS) untuk mempelajari perbandingan profil tegangan dan rugi daya sebelum dan sesudah pengaplikasian SPKLU. Dengan optimasi penempatan SPKLU menggunakan metode Flower Pollination Algorithm (FPA) menggunakan software Matlab yang menghasilkan penempatan SPKLU pada bus 58 sebesar 300 kW, bus 37 sebesar 301 kW, dan bus 36 sebesar 300 kW. Profil tegangan berubah dari 0,9695 p.u menjadi 0,9688 p.u dan rugi-rugi daya dari 53,3 kW menjadi 56,1 kW.
摘要:要实现印尼减少温室效应的承诺,使用环保型汽车至关重要。2019年8月12日,总统发布了《关于陆地车辆电池电动汽车计划速度的规定》,这标志着政府对该车辆的认真应用。本研究是在日惹市Bantul炼油厂区安装光伏电站作为分布式能源(DER)后提供公共电动汽车充电站(SPKLU)的具体研究。本研究采用开放式配电系统模拟器(Open Distribution System Simulator, OpenDSS)软件对配电网进行仿真,对spklu安装前后的电压分布和功率损耗进行对比分析。利用Matlab软件利用花授粉算法(FPA)对SPKLU的布局进行优化,得到了SPKLU在58 × 300kw、37 × 301 kW和36 × 300kw母线上的布局。电压分布从0.9695 p.u变为0.9688 p.u,功率损耗从53.3 kW变为56.1 kW。8月12日,2019年8月12日,泰国,泰国,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度,印度。Penelitian ini spesifik pada hal penyediaan Stasiun Pengisian Kendaraan Listrik Umum (SPKLU) pada area penyulang Bantul,日惹setelah pemasangan pembangkit光伏(PV) sebagai分布式能源(DER)Open Distribution System Simulator (Open Distribution System Simulator, OpenDSS)是一种开放的分销系统仿真软件。登安optimasi penempatan SPKLU menggunakan方法花授粉算法(FPA) menggunakan软件Matlab杨menghasilkan penempatan SPKLU帕达总线58 sebesar 300 kW,总线37 sebesar 301 kW,总线36 sebesar 300 kW。profile tegangan berubah dari 0,9695 p.u menjadi 0,9688 p.u dan rugi-rugi daya dari 53,3 kW menjadi 56,1 kW。