Vito Project: Hull / Mooring Design & Platform Installation

Darin Johnson, C. Heyl, R. Kamal, Yile Li
{"title":"Vito Project: Hull / Mooring Design & Platform Installation","authors":"Darin Johnson, C. Heyl, R. Kamal, Yile Li","doi":"10.4043/32503-ms","DOIUrl":null,"url":null,"abstract":"\n In 2009, the Vito field was discovered in more than 4,000 ft of water approximately 150 miles offshore from New Orleans, Louisiana. The project produces from reservoirs nearly 30,000 feet below sea level. This paper provides an overview of the Hull & Mooring system, executing a minimum technical scope to produce a simplistic design. This paper is part of a Vito Project series at OTC 2023, and the other papers are listed in the references.\n The original Vito project execution strategy was to replicate the Shell mega-project of Appomattox. As the industry and market began to change in 2015, the project faced significant financial hurdles, and the project team decided to refresh the design concept to reduce cost and simplify. The team regrouped to propose a smaller semi-submersible Floating Production System (FPS) with a simplistic mooring design. The Topsides was designed to be lifted as a single module, with a payload of less than 10,000 st to enable competitive tendering process.\n The redesigned FPS concept was moored with 12 taut, chain – polyester – chain mooring line system utilizing an in-line mooring tensioner, removing the traditional mechanically complicated and space demanding \"on-vessel\" winch systems. Vito employed a passive hull system, with all ballasting occurring over the top without hull penetrations. There were no pump rooms within the hull as equipment is accessed from top of column, removing the need for regular hull access to maintain equipment. The hull compartmentation also followed a simple approach, containing only 12 ballast tanks to reduce fabrication cost. The hull design also included simplified ring stiffening for columns which eliminated the traditional orthogonally stiffened systems. Additionally, the structure utilized an upper column frame structure to support the topsides deck and served as a bracing for supporting columns at the top for squeeze-pry loads and bracing for supporting columns during dry tow. The simplification of the stiffening system and topsides deck support design reduced interfaces between hull and topsides and also opened up options for fabrication of topsides and hull.\n Key challenges included developing installation methods without traditional FPS mooring chain jacks and increasing installation options by not requiring a large installation derrick barge and enabling use of common anchor handler vessels. The project experienced fabrication delays due to COVID-19, which required creative solutions transporting the FPS from Singapore to the Gulf of Mexico. The design team enabled the use of various heavy transportation vessels (HTV), ultimately settling on a smaller HTV modified with four 25 ft outriggers.","PeriodicalId":196855,"journal":{"name":"Day 2 Tue, May 02, 2023","volume":"161 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-04-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, May 02, 2023","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/32503-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

Abstract

In 2009, the Vito field was discovered in more than 4,000 ft of water approximately 150 miles offshore from New Orleans, Louisiana. The project produces from reservoirs nearly 30,000 feet below sea level. This paper provides an overview of the Hull & Mooring system, executing a minimum technical scope to produce a simplistic design. This paper is part of a Vito Project series at OTC 2023, and the other papers are listed in the references. The original Vito project execution strategy was to replicate the Shell mega-project of Appomattox. As the industry and market began to change in 2015, the project faced significant financial hurdles, and the project team decided to refresh the design concept to reduce cost and simplify. The team regrouped to propose a smaller semi-submersible Floating Production System (FPS) with a simplistic mooring design. The Topsides was designed to be lifted as a single module, with a payload of less than 10,000 st to enable competitive tendering process. The redesigned FPS concept was moored with 12 taut, chain – polyester – chain mooring line system utilizing an in-line mooring tensioner, removing the traditional mechanically complicated and space demanding "on-vessel" winch systems. Vito employed a passive hull system, with all ballasting occurring over the top without hull penetrations. There were no pump rooms within the hull as equipment is accessed from top of column, removing the need for regular hull access to maintain equipment. The hull compartmentation also followed a simple approach, containing only 12 ballast tanks to reduce fabrication cost. The hull design also included simplified ring stiffening for columns which eliminated the traditional orthogonally stiffened systems. Additionally, the structure utilized an upper column frame structure to support the topsides deck and served as a bracing for supporting columns at the top for squeeze-pry loads and bracing for supporting columns during dry tow. The simplification of the stiffening system and topsides deck support design reduced interfaces between hull and topsides and also opened up options for fabrication of topsides and hull. Key challenges included developing installation methods without traditional FPS mooring chain jacks and increasing installation options by not requiring a large installation derrick barge and enabling use of common anchor handler vessels. The project experienced fabrication delays due to COVID-19, which required creative solutions transporting the FPS from Singapore to the Gulf of Mexico. The design team enabled the use of various heavy transportation vessels (HTV), ultimately settling on a smaller HTV modified with four 25 ft outriggers.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Vito项目:船体/系泊设计和平台安装
2009年,Vito油田在距离路易斯安那州新奥尔良约150英里的海面上被发现,水深超过4000英尺。该项目从海平面以下近3万英尺的水库中开采石油。本文提供了船体和系泊系统的概述,执行最小的技术范围,以产生一个简单的设计。本文是OTC 2023上Vito项目系列的一部分,其他论文在参考文献中列出。Vito最初的项目执行策略是复制壳牌的阿波马托克斯大型项目。随着2015年行业和市场的变化,该项目面临着巨大的资金障碍,项目团队决定更新设计理念,以降低成本和简化。团队重新组合,提出了一种更小的半潜式浮式生产系统(FPS),具有简单的系泊设计。顶部平台被设计为一个单独的模块,有效载荷小于10,000吨,以实现竞争性招标过程。重新设计的FPS概念船系泊时采用了12根紧绷的聚酯链系泊绳系统,该系统使用了一个在线系泊张力器,消除了传统的机械复杂且空间要求高的“船上”绞车系统。Vito采用了被动式船体系统,所有的压载都发生在顶部,没有船体穿透。由于设备可以从塔顶进入,因此船体内没有泵房,因此无需定期进入船体维护设备。船体隔舱也采用了简单的方法,仅包含12个压载舱以降低制造成本。船体设计还包括简化的圆柱环加强,消除了传统的正交加强系统。此外,该结构利用上部柱框架结构来支撑上层甲板,并作为顶部支撑柱的支撑,以承受挤压撬载荷,并在干拖时支撑支撑柱。加固系统和上层甲板支撑设计的简化减少了船体和上层甲板之间的界面,也为上层甲板和船体的制造提供了选择。主要挑战包括开发不需要传统FPS系泊千斤顶的安装方法,以及通过不需要大型安装井架驳船和使用通用锚处理船来增加安装选项。由于2019冠状病毒病,该项目经历了制造延迟,这需要创造性的解决方案将FPS从新加坡运送到墨西哥湾。设计团队允许使用各种重型运输船(HTV),最终确定了一个较小的HTV,修改了四个25英尺的支腿。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Estimation of Shear Wave Velocity Using Empirical, MLR, and GEP Techniques-Case Study: Kharg Island Offshore Oilfield Digital Twin of a Generic Jack-Up Platform Best Practices for Handling Completion Tubulars to Ensure Design Life Well Integrity in HPHT Wells Labrador Gas – History and Opportunity Junction Plate for High Pressure High Temperature System
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1