Kajian Teknis Produksi Alat Gali-Muat dan Angkut pada Penambangan Batu Gamping PT Akarna Marindo di Desa Cipatat Kecamatan Cipatat, Kabupaten Bandung Barat, Provinsi Jawa Barat

Arrmandha Alghifari, Iswandaru, Elfida Moralista
{"title":"Kajian Teknis Produksi Alat Gali-Muat dan Angkut pada Penambangan Batu Gamping PT Akarna Marindo di Desa Cipatat Kecamatan Cipatat, Kabupaten Bandung Barat, Provinsi Jawa Barat","authors":"Arrmandha Alghifari, Iswandaru, Elfida Moralista","doi":"10.29313/bcsme.v3i1.5404","DOIUrl":null,"url":null,"abstract":"Abstract. Limestone mining activities at PT Akarna Marindo include digging-loading and hauling activities, this activity is very important in mining activities because it involves achieving production targets. The problem in this study was not achieving the production target of 20,000 tons/month, because of this a technical study was carried out on loading and hauling equipment aimed at calculating actual production, knowing the factors that influence actual production, knowing match factors, and knowing efforts to increase production. The research was conducted in the mining area at location A, by observing the activities of digging, loading and transporting 1 Excavator PC-200 and 2 DT Hino FM 260 JD. The data collected is primary data including road geometry, number of digging-loading and hauling equipment, productive work time, cycle time of digging-loading and hauling equipment, inhibition time, in-situ density, loose density, swell factor and fill factor. Secondary data includes production targets, administrative maps, topography, geology, annual rainfall, specifications for digging and hauling equipment. Production of digging and loading equipment is 13.605,9 tons/month and transportation equipment is 13.521,1 tons/month, with an MF value of 0.83 (MF < 1). The production results did not reach the production target of 20,000 tons/month, the reasons for not achieving the production target were due to time constraints, not ideal road geometry, and less than optimal speed of the conveyance. Because of this, improvements were made to the road geometry, work efficiency and the cycle time of the transportation equipment, the results of the improvements were able to increase the production of the transportation equipment to 20.208,75 tons/month. \nAbstrak. Kegiatan penambangan batu gamping di PT Akarna Marindo meliputi aktivitas gali-muat dan angkut, aktivitas ini merupakan hal yang sangat penting dalam kegiatan penambangan karena menyangkut ketercapaian target produksi. Permasalahan dalam penelitian ini adalah tidak tercapainya target produksi sebesar 20.000 ton/bulan, karena itu dilakukan kajian secara teknis alat-gali muat dan angkut bertujuan untuk menghitung produksi aktual, mengetahui faktor-faktor yang memengaruhi produksi aktual, mengetahui match factor, dan mengetahui upaya untuk meningkatkan produksi. Penelitian dilakukan pada area penambangan lokasi A, dengan mengamati aktivitas penggalian, pemuatan dan pengangkutan 1 alat gali-muat Excavator PC-200 dan 2 alat angkut DT Hino FM 260 JD. Data yang dikumpulkan adalah data primer meliputi geometri jalan, jumlah alat gali-muat dan angkut, waktu kerja produktif, waktu edar alat gali-muat dan angkut, waktu hambatan, density insitu, density loose, swell factor dan fill factor. Data sekunder meliputi target produksi, peta administrasi, topografi, geologi, curah hujan tahunan, spesifikasi alat gali-muat dan angkut. Produksi alat gali-muat 13.605,9 ton/bulan dan alat angkut 13.521,1 ton/bulan, dengan nilai MF sebesar 0,83 (MF < 1). Hasil produksi tersebut tidak mencapai target produksi 20.000 ton/bulan, penyebab tidak tercapainya target produksi karena adanya waktu hambatan, geometri jalan tidak ideal, dan kurang optimalnya kecepatan alat angkut. Oleh karena itu dilakukan perbaikan geometri jalan, efisiensi kerja dan cycle time alat angkut, hasil perbaikan mampu meningkatkan produksi alat angkut menjadi 20.208,75 ton/bulan.","PeriodicalId":187584,"journal":{"name":"Bandung Conference Series: Mining Engineering","volume":"44 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-01-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bandung Conference Series: Mining Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29313/bcsme.v3i1.5404","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Abstract. Limestone mining activities at PT Akarna Marindo include digging-loading and hauling activities, this activity is very important in mining activities because it involves achieving production targets. The problem in this study was not achieving the production target of 20,000 tons/month, because of this a technical study was carried out on loading and hauling equipment aimed at calculating actual production, knowing the factors that influence actual production, knowing match factors, and knowing efforts to increase production. The research was conducted in the mining area at location A, by observing the activities of digging, loading and transporting 1 Excavator PC-200 and 2 DT Hino FM 260 JD. The data collected is primary data including road geometry, number of digging-loading and hauling equipment, productive work time, cycle time of digging-loading and hauling equipment, inhibition time, in-situ density, loose density, swell factor and fill factor. Secondary data includes production targets, administrative maps, topography, geology, annual rainfall, specifications for digging and hauling equipment. Production of digging and loading equipment is 13.605,9 tons/month and transportation equipment is 13.521,1 tons/month, with an MF value of 0.83 (MF < 1). The production results did not reach the production target of 20,000 tons/month, the reasons for not achieving the production target were due to time constraints, not ideal road geometry, and less than optimal speed of the conveyance. Because of this, improvements were made to the road geometry, work efficiency and the cycle time of the transportation equipment, the results of the improvements were able to increase the production of the transportation equipment to 20.208,75 tons/month. Abstrak. Kegiatan penambangan batu gamping di PT Akarna Marindo meliputi aktivitas gali-muat dan angkut, aktivitas ini merupakan hal yang sangat penting dalam kegiatan penambangan karena menyangkut ketercapaian target produksi. Permasalahan dalam penelitian ini adalah tidak tercapainya target produksi sebesar 20.000 ton/bulan, karena itu dilakukan kajian secara teknis alat-gali muat dan angkut bertujuan untuk menghitung produksi aktual, mengetahui faktor-faktor yang memengaruhi produksi aktual, mengetahui match factor, dan mengetahui upaya untuk meningkatkan produksi. Penelitian dilakukan pada area penambangan lokasi A, dengan mengamati aktivitas penggalian, pemuatan dan pengangkutan 1 alat gali-muat Excavator PC-200 dan 2 alat angkut DT Hino FM 260 JD. Data yang dikumpulkan adalah data primer meliputi geometri jalan, jumlah alat gali-muat dan angkut, waktu kerja produktif, waktu edar alat gali-muat dan angkut, waktu hambatan, density insitu, density loose, swell factor dan fill factor. Data sekunder meliputi target produksi, peta administrasi, topografi, geologi, curah hujan tahunan, spesifikasi alat gali-muat dan angkut. Produksi alat gali-muat 13.605,9 ton/bulan dan alat angkut 13.521,1 ton/bulan, dengan nilai MF sebesar 0,83 (MF < 1). Hasil produksi tersebut tidak mencapai target produksi 20.000 ton/bulan, penyebab tidak tercapainya target produksi karena adanya waktu hambatan, geometri jalan tidak ideal, dan kurang optimalnya kecepatan alat angkut. Oleh karena itu dilakukan perbaikan geometri jalan, efisiensi kerja dan cycle time alat angkut, hasil perbaikan mampu meningkatkan produksi alat angkut menjadi 20.208,75 ton/bulan.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
摘要。PT Akarna Marindo的石灰石开采活动包括挖掘-装载和运输活动,这一活动在采矿活动中非常重要,因为它涉及到生产目标的实现。本次研究的问题是没有达到2万吨/月的生产目标,因此对装载和运输设备进行了技术研究,旨在计算实际产量,了解影响实际产量的因素,了解匹配因素,了解增产力度。研究在A矿区进行,观察了1台PC-200挖掘机和2台DT Hino FM 260 JD的挖掘、装载和运输活动。采集的数据为原始数据,包括道路几何形状、挖装拖设备数量、生产作业时间、挖装拖设备周期时间、抑制时间、原位密度、松散密度、膨胀系数和填充系数。次要数据包括生产目标、行政地图、地形、地质、年降雨量、挖掘和运输设备的规格。掘装设备产量为13.605.9吨/月,运输设备产量为13.52.1吨/月,MF值为0.83 (MF < 1)。生产结果未达到2万吨/月的生产目标,未达到生产目标的原因是时间限制、道路几何形状不理想、运输速度未达到最佳。因此,改进了道路几何形状,工作效率和运输设备的周期时间,改进的结果能够将运输设备的产量增加到20.208,75吨/月。Abstrak。Kegiatan penambangan batu gamping di PT Akarna Marindo meliputi aktivitas gali-muat danangkut, aktivitas ini merupakan hal yang sangat penting dalam Kegiatan penambangan karena menyangkut ketercapa目标产品。Permasalahan dalam penelitian ini adalah tidak tercapainya目标产量为2万吨/bulan, karena itu dilakukan kajian secara teknis alat-gali mukat - alat-gali mukat - angkut bertujuan untuk menghitung producksi aktual, menggetahui factor - factor - yang mengengaruhi producksi aktual, menggetahui match factor, dan menggetahui upaya untuk mengkatkan producksi akil。Penelitian dilakukan pada area penambangan lokasi A, dengan mengamati aktivitas pengangkutan, pemuatan dan pengangkutan 1 alatgali - mut挖掘机PC-200丹2 alatangkut DT Hino FM 260 JD。数据yang dikumpulkan adalah数据primer meliputi geometri jalan, jumlah alat gali-muat dan angkut, waktu kerja producttif, waktu edar alat gali-muat dan angkut, waktu hambatan,密度原位,密度松散,膨胀因子和填充因子。数据检索:目标产品,peta administration,地形,地质,curah hujan ta湖南,物种,alat gali-muat and angkut。产量为13.605吨/bulan,产量为13.521吨/bulan,产量为13.521吨/bulan,产量为0.83吨/bulan(产量< 1). Hasil产量为2.50万吨/bulan,产量为2.000吨/bulan,产量为2.000吨/bulan,产量为2.32万吨/bulan,产量为2.32万吨/bulan,产量为2.32万吨/bulan,产量为2.32万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan,产量为2.31万吨/bulan。Oleh karena itu dilakukan perbaikan geometri jalan, efisiensi kerja dan循环时间alat angkut, hasil perbaikan mampu meningkatkan产品duksi alat angkut menjadi 20.208,75吨/bulan。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Kajian Kelayakan Ekonomi pada Kegiatan Hauling Tambang Tanah Liat PT Indocement Tunggal Prakarsa TBK Blok Pabuaran di Kecamatan Sukamakmur Kabupaten Bogor Provinsi Jawa Barat Analisis Investasi dan Kelayakan Ekonomi pada Penambangan Sirtu CV Billiant Ningrat di Kecamatan Leles Kabupaten Garut Provinsi Jawa Barat Manajemen Stockpile untuk Mencegah Terjadinya Self-Combustion di PLTU Banten 2 Labuan OMU Monitoring Korosi Discharge Conveyor F pada Tambang Batubara PT XYZ di Kabupaten Merangin Provinsi Jambi Pengaruh Bidang Diskontinu Terhadap Potensi Longsoran Baji pada Lereng Tambang Terbuka di PT Indocement Tunggal Prakarsa Desa Palimanan, Kecamatan Gempol, Kabupaten Cirebon, Provinsi Jawa Barat
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1