{"title":"Start-up challenge","authors":"S. Akhtar","doi":"10.1108/02580540210793310","DOIUrl":null,"url":null,"abstract":"Start-up during 2002 of the Gebze, Adapazari and Izmir combined cycle power plants in Turkey revealed over-pressure at the boiler feedwater pump discharge. The over-pressure was caused by grid over-frequency and cold water used at start-up and required an innovative solution to ensure that the plants could continue to operate reliably.","PeriodicalId":260015,"journal":{"name":"Power engineering international","volume":"133 3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Power engineering international","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/02580540210793310","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Start-up during 2002 of the Gebze, Adapazari and Izmir combined cycle power plants in Turkey revealed over-pressure at the boiler feedwater pump discharge. The over-pressure was caused by grid over-frequency and cold water used at start-up and required an innovative solution to ensure that the plants could continue to operate reliably.