{"title":"Research on Installation Technology of Super Large Radial Gate of Dam in Complex Environment","authors":"Zhou Ruoyu, Meichun Gou","doi":"10.11648/j.ajwse.20230901.12","DOIUrl":null,"url":null,"abstract":": Taking the installation construction of super large radial gates of Nam theun1 hydropower station in Laos as an example, due to the lag of civil construction period and the dam structure","PeriodicalId":423224,"journal":{"name":"American Journal of Water Science and Engineering","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-03-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"American Journal of Water Science and Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.11648/j.ajwse.20230901.12","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
: Taking the installation construction of super large radial gates of Nam theun1 hydropower station in Laos as an example, due to the lag of civil construction period and the dam structure