Cost Risk Allocation Theory and Practice

C. Smart
{"title":"Cost Risk Allocation Theory and Practice","authors":"C. Smart","doi":"10.1080/1941658X.2014.922907","DOIUrl":null,"url":null,"abstract":"Risk allocation is the assignment of risk reserves from a total project or portfolio level to individual constituent elements. For example, cost risk at the total project level is allocated to individual work breakdown structure elements. This is a non-trivial exercise in most instances, because of issues related to the aggregation of risks, such as the fact that percentiles do not add. For example, if a project is funded at a 70% confidence level then one cannot simply allocate that funding to work breakdown structure elements by assigning each its 70% confidence level estimate. This is because the resulting sum may (but not necessarily will) be larger than the total 70% confidence estimate for the entire project. One method for allocating risk that has commonly been used in practice and has been implemented in a cost estimating integration software package is to assign risk by assigning the element’s standard deviation as a proportion of the sum of the standard deviations for all work breakdown structure elements (Sandberg, 2007). Another popular method notes that risk is typically not symmetric, and looks at the relative contribution of the element’s variation above the mean or other reference estimate. Dr. Steve Book first presented this concept to a limited Government audience in 1992 and presented it to a wider audience several years later (Book, 1992, 2006). This technique, based on the concept of “need,” has been implemented in the NASA/Air Force Cost Model (Smart, 2005). These contributions represent the current state-of-the-practice in cost analysis. The notion of positive semi-variance as an alternative to the needs method was brought forth by Book (2006) and further propounded by Sandberg (2007). A new method proposed by Hermann (personal communication, 2010) discusses the concept of optimality in risk allocation and proposes a one-sided moment objective function for calculating the optimal allocation. An older method, developed in the 1990s by Lockheed Martin, assigns equal percentile allocations for all work breakdown structure elements (Goldberg and Weber, 1998). This method claims to be optimal, and Goldberg and Weber (1998) show that under a very specific assumption, that this is true. Aside from Hermann’s paper and the report by Goldberg and Weber on the Lockheed Martin method, cost risk allocation has typically not been associated with optimality. Neither the proportional standard deviation method nor the needs method guarantees the allocation scheme will be optimal or even necessarily desirable. Indeed, the twin topics of risk measurement and risk allocation have either been treated independently (Book, 2006), or they have been treated as one and the same (Sandberg, 2007). Regardless, the current situation is muddled, with no clear delineation between the two. In this article, the present author introduces to cost analysis the concept of gradient risk allocation, which has been recently used in the areas of finance and insurance (McNeil, Frey, & Embrechts, 2005). Gradient allocation clearly illustrates that the notions of risk measure and risk allocation are distinct but intrinsically linked. This method is shown to be an optimal method for allocation using three distinct arguments—axiomatic, game-theoretic, and economic (optimal is used in this context as desirable or good, not as the minimum or maximum of a specified objective function). It is also shown that the gradient risk allocation method is intrinsically tied to the method used to measure risk, a concept not heretofore considered in cost analysis. Gradient allocation is applied to five risk measures, resulting in five different allocation methods, each optimal for the risk measure from which they are derived. Considerations on when the proportional standard deviation and needs method are optimal are discussed, and a link between Hermann’s method and the proportional standard deviation method is demonstrated.","PeriodicalId":390877,"journal":{"name":"Journal of Cost Analysis and Parametrics","volume":"7 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2014-05-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Cost Analysis and Parametrics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1080/1941658X.2014.922907","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Risk allocation is the assignment of risk reserves from a total project or portfolio level to individual constituent elements. For example, cost risk at the total project level is allocated to individual work breakdown structure elements. This is a non-trivial exercise in most instances, because of issues related to the aggregation of risks, such as the fact that percentiles do not add. For example, if a project is funded at a 70% confidence level then one cannot simply allocate that funding to work breakdown structure elements by assigning each its 70% confidence level estimate. This is because the resulting sum may (but not necessarily will) be larger than the total 70% confidence estimate for the entire project. One method for allocating risk that has commonly been used in practice and has been implemented in a cost estimating integration software package is to assign risk by assigning the element’s standard deviation as a proportion of the sum of the standard deviations for all work breakdown structure elements (Sandberg, 2007). Another popular method notes that risk is typically not symmetric, and looks at the relative contribution of the element’s variation above the mean or other reference estimate. Dr. Steve Book first presented this concept to a limited Government audience in 1992 and presented it to a wider audience several years later (Book, 1992, 2006). This technique, based on the concept of “need,” has been implemented in the NASA/Air Force Cost Model (Smart, 2005). These contributions represent the current state-of-the-practice in cost analysis. The notion of positive semi-variance as an alternative to the needs method was brought forth by Book (2006) and further propounded by Sandberg (2007). A new method proposed by Hermann (personal communication, 2010) discusses the concept of optimality in risk allocation and proposes a one-sided moment objective function for calculating the optimal allocation. An older method, developed in the 1990s by Lockheed Martin, assigns equal percentile allocations for all work breakdown structure elements (Goldberg and Weber, 1998). This method claims to be optimal, and Goldberg and Weber (1998) show that under a very specific assumption, that this is true. Aside from Hermann’s paper and the report by Goldberg and Weber on the Lockheed Martin method, cost risk allocation has typically not been associated with optimality. Neither the proportional standard deviation method nor the needs method guarantees the allocation scheme will be optimal or even necessarily desirable. Indeed, the twin topics of risk measurement and risk allocation have either been treated independently (Book, 2006), or they have been treated as one and the same (Sandberg, 2007). Regardless, the current situation is muddled, with no clear delineation between the two. In this article, the present author introduces to cost analysis the concept of gradient risk allocation, which has been recently used in the areas of finance and insurance (McNeil, Frey, & Embrechts, 2005). Gradient allocation clearly illustrates that the notions of risk measure and risk allocation are distinct but intrinsically linked. This method is shown to be an optimal method for allocation using three distinct arguments—axiomatic, game-theoretic, and economic (optimal is used in this context as desirable or good, not as the minimum or maximum of a specified objective function). It is also shown that the gradient risk allocation method is intrinsically tied to the method used to measure risk, a concept not heretofore considered in cost analysis. Gradient allocation is applied to five risk measures, resulting in five different allocation methods, each optimal for the risk measure from which they are derived. Considerations on when the proportional standard deviation and needs method are optimal are discussed, and a link between Hermann’s method and the proportional standard deviation method is demonstrated.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
成本风险分担理论与实践
风险分配是将风险储备从整个项目或投资组合级别分配给单个组成元素。例如,整个项目级别的成本风险被分配到单个工作分解结构元素。在大多数情况下,这是一个重要的练习,因为与风险聚集有关的问题,例如百分位数不会增加的事实。例如,如果一个项目的资金是在70%的置信度水平上,那么一个人不能简单地通过分配每个70%置信度水平的估计来分配资金给工作分解结构元素。这是因为最终结果可能(但不一定会)大于整个项目的70%置信度估计。一种在实践中普遍使用并已在成本估算集成软件包中实现的风险分配方法是通过将元素的标准偏差分配为所有工作分解结构元素的标准偏差总和的比例来分配风险(Sandberg, 2007)。另一种流行的方法指出,风险通常是不对称的,并着眼于元素的变化高于平均值或其他参考估计的相对贡献。史蒂夫·布克博士于1992年首次向有限的政府受众提出了这一概念,并在几年后向更广泛的受众提出了这一概念(布克,1992,2006)。这种基于“需求”概念的技术已经在NASA/空军成本模型中实施(Smart, 2005)。这些贡献代表了当前成本分析的实践状况。Book(2006)提出了积极半方差的概念,作为需求方法的替代方案,并由Sandberg(2007)进一步提出。Hermann (personal communication, 2010)提出了一种新的方法,讨论了风险分配中的最优性概念,并提出了一个计算最优分配的单边时刻目标函数。洛克希德·马丁公司在20世纪90年代开发了一种较旧的方法,为所有工作分解结构元素分配相等的百分位数分配(Goldberg and Weber, 1998)。这种方法声称是最优的,Goldberg和Weber(1998)表明,在一个非常具体的假设下,这是正确的。除了Hermann的论文和Goldberg和Weber关于Lockheed Martin方法的报告外,成本风险分配通常与最优性无关。比例标准差法和需求法都不能保证分配方案是最优的,甚至不一定是理想的。事实上,风险度量和风险分配这两个主题要么被独立对待(Book, 2006),要么被视为一体(Sandberg, 2007)。无论如何,目前的情况是混乱的,两者之间没有明确的界限。在本文中,本文作者介绍了成本分析梯度风险分配的概念,该概念最近已在金融和保险领域使用(McNeil, Frey, & Embrechts, 2005)。梯度分配清楚地说明了风险度量和风险分配的概念是不同的,但又有内在的联系。这种方法被证明是一种分配的最佳方法,它使用了三个不同的论证——公理化的、博弈论的和经济的(在这种情况下,最优是指理想的或好的,而不是指特定目标函数的最小值或最大值)。还表明,梯度风险分配方法与用于度量风险的方法内在地联系在一起,这是一个迄今为止尚未在成本分析中考虑的概念。将梯度分配应用于五种风险度量,得到五种不同的分配方法,每种方法都是其衍生的风险度量的最优分配方法。讨论了比例标准差法和需求法在什么情况下最优的考虑,并论证了Hermann法与比例标准差法之间的联系。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Editorial Board EOV Multiproduct Cost-Volume-Profit Model: A Resource Reallocation Approach for Decision Making Dynamics of New Building Construction Costs: Implications for Forecasting Escalation Allowances Balancing Expert Opinion and Historical Data: The Case of Baseball Umpires Using Robust Statistical Methodology to Evaluate the Cost Performance of Project Delivery Systems: A Case Study of Horizontal Construction
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1