First Application of Intelligent Gas Lift System in ADNOC Offshore Field to Improve Profitability Through Enhanced Gas Lift

Zhihua Wang, J. Wills, J. Faustinelli, Walid Abdulhai, Stephen Faux
{"title":"First Application of Intelligent Gas Lift System in ADNOC Offshore Field to Improve Profitability Through Enhanced Gas Lift","authors":"Zhihua Wang, J. Wills, J. Faustinelli, Walid Abdulhai, Stephen Faux","doi":"10.2118/211587-ms","DOIUrl":null,"url":null,"abstract":"\n Gas lift is one of the most crucial components for achieving and maintaining the production targets in a giant offshore oil field development. All producer wells are completed with gas lift mandrels (GLMs) using both dummy and tubing pressure shearable valves to accelerate and enhance efficiency of the initial unloading and gas lift start up. The gas lift designs are optimized considering reservoir conditions and surface constraints over the well life cycle. However, once the GLMs are installed, the gas lift optimization would require intervention work, hence production interruptions. To maximize the gas lift performance and minimize the intervention work, a digital intelligent gas lift (DIAL) system was trialed.\n Once the system was selected, a comprehensive design review was conducted covering product qualification, material suitability, factory acceptance testing, and technical limits in both initial installation and well life cycle operation. Detailed pre-installation preparation such as system integration testing and installation procedures were prepared. Four DIAL units were installed successfully in a record extended reach drilling (ERD) well together with 4 conventional GLMs along with dummy valves, as contingency. The system was successfully tested during nitrogen unloading operations which not only demonstrated the functionality of the equipment, but also the increased efficiency of the use of the system.\n It is estimated that the use of DIAL in this pilot well will result in substantial net present value generation based on the elimination of well intervention related cost to service gas lift valves, avoidance of production deferral, and production gain resulting from optimized real time gas lift operations.\n Each DIAL unit has built-in pressure and temperature sensors and adjustable size orifices. This allows the operator to manage the evolving well and reservoir conditions by applying data driven decision making and surface control during well unloading and production to enable the optimum gas lift injection rate and depth to maximize production. This is all able to be accomplished without the need of wireline intervention for valve change out. This process is repeated until gas reached the deepest valve. Additional benefits of using DIAL system in gas lift operations, as compared to conventional systems, will be described in the paper.\n The first DIAL system was installed in one of the top 10 globally longest ERD wells containing the largest DIAL system ever mounted. The paper will describe the brief history of artificial lift strategy for the field and current practices, drivers for trialing DIAL, the equipment qualification process, installation overview, and finally ultimate benefits seen in the initial unloading and gas lift operations.","PeriodicalId":258316,"journal":{"name":"Day 3 Wed, November 02, 2022","volume":"43 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-10-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, November 02, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/211587-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Gas lift is one of the most crucial components for achieving and maintaining the production targets in a giant offshore oil field development. All producer wells are completed with gas lift mandrels (GLMs) using both dummy and tubing pressure shearable valves to accelerate and enhance efficiency of the initial unloading and gas lift start up. The gas lift designs are optimized considering reservoir conditions and surface constraints over the well life cycle. However, once the GLMs are installed, the gas lift optimization would require intervention work, hence production interruptions. To maximize the gas lift performance and minimize the intervention work, a digital intelligent gas lift (DIAL) system was trialed. Once the system was selected, a comprehensive design review was conducted covering product qualification, material suitability, factory acceptance testing, and technical limits in both initial installation and well life cycle operation. Detailed pre-installation preparation such as system integration testing and installation procedures were prepared. Four DIAL units were installed successfully in a record extended reach drilling (ERD) well together with 4 conventional GLMs along with dummy valves, as contingency. The system was successfully tested during nitrogen unloading operations which not only demonstrated the functionality of the equipment, but also the increased efficiency of the use of the system. It is estimated that the use of DIAL in this pilot well will result in substantial net present value generation based on the elimination of well intervention related cost to service gas lift valves, avoidance of production deferral, and production gain resulting from optimized real time gas lift operations. Each DIAL unit has built-in pressure and temperature sensors and adjustable size orifices. This allows the operator to manage the evolving well and reservoir conditions by applying data driven decision making and surface control during well unloading and production to enable the optimum gas lift injection rate and depth to maximize production. This is all able to be accomplished without the need of wireline intervention for valve change out. This process is repeated until gas reached the deepest valve. Additional benefits of using DIAL system in gas lift operations, as compared to conventional systems, will be described in the paper. The first DIAL system was installed in one of the top 10 globally longest ERD wells containing the largest DIAL system ever mounted. The paper will describe the brief history of artificial lift strategy for the field and current practices, drivers for trialing DIAL, the equipment qualification process, installation overview, and finally ultimate benefits seen in the initial unloading and gas lift operations.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
ADNOC海上油田首次应用智能气举系统,通过强化气举提高盈利能力
在大型海上油田开发中,气举是实现和保持生产目标的最关键的组成部分之一。所有生产井都使用气举心轴(glm)完成,使用假人和油管压力剪切阀,以加速和提高初始卸载和气举启动的效率。考虑到油藏条件和井生命周期内的地面限制因素,气举设计进行了优化。然而,一旦安装了glm,气举优化将需要进行干预工作,因此生产中断。为了最大限度地提高气举性能并减少修井作业,试验了一种数字智能气举(DIAL)系统。一旦系统被选中,就会进行全面的设计审查,包括产品资格、材料适用性、工厂验收测试以及初始安装和井生命周期操作中的技术限制。详细的安装前准备,如系统集成测试和安装程序准备。作为应急措施,该公司在一口大位移钻井(ERD)井中成功安装了4台DIAL装置,以及4台常规glm和假阀。该系统在氮气卸载作业中成功进行了测试,不仅证明了设备的功能,而且提高了系统的使用效率。据估计,在这口试验井中使用DIAL将产生可观的净现值,因为它消除了与气举阀维修相关的油井干预成本,避免了生产延迟,并通过优化的实时气举操作获得了生产收益。每个DIAL单元都内置压力和温度传感器以及可调节尺寸的孔。这使得作业者能够在卸井和生产过程中通过数据驱动的决策和地面控制来管理不断变化的井和油藏条件,从而实现最佳气举注入速度和深度,从而最大限度地提高产量。这一切都可以在更换阀门时无需电缆干预即可完成。这个过程不断重复,直到气体到达最深的阀门。与传统系统相比,在气举作业中使用DIAL系统的其他好处将在本文中描述。第一口DIAL系统安装在全球最长的10口ERD井之一,其中包含有史以来安装的最大DIAL系统。本文将介绍人工举升策略的简要历史和当前实践,DIAL试验的驱动因素,设备认证过程,安装概述,以及在初始卸载和气举操作中看到的最终效益。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Gas Kick Well Control Situation in High-Temperature Well Managed with Oil-Based Mud and Managed Pressure Drilling Technology Use of Virtual Metering to Maximize Water Injection Efficiency in an Offshore Field Abu Dhabi Effective Interbed Multiple Attenuation with Exploration-Scale Seismic Data Use of Machine Learning Approach on the Results of a 3D Grid Model to Identify Impacting Uncertainties and Derive Low/High Production Profiles, FRF Team A Polymer Flood Pilot with Autonomous Outflow Control Device Technology and Resilient Cost Management from South Sultanate of Oman
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1