Jing Zhong Tee, I. Lim, Keliang Zhou, O. Anaya‐Lara
{"title":"Transient Stability Analysis of Offshore Wind With O&G Platforms and an Energy Storage System","authors":"Jing Zhong Tee, I. Lim, Keliang Zhou, O. Anaya‐Lara","doi":"10.1109/PESGM41954.2020.9281706","DOIUrl":null,"url":null,"abstract":"The integration of offshore floating wind turbine generation (WTG) with offshore O&G platforms in the off-grid configuration which is a business model that is in the process of developing in the North Sea. As such, an integrated system consisting of an offshore floating WTG and O&G production platforms with onboard battery energy storage system (BESS) is proposed in this paper. In simulation, there are 4 different scenarios and results show that conventional system has high transient stability which do not meet the IEC standards for O&G platforms. The simulation has shown proposed system 2 which has incorporated with BESS 1 and BESS 2, has a reduction in transient deviation that can meets the IEC standards. In addition, capital expenditure (CapEx) and operational expenditure (OpEx) of proposed system 2 is presented in this paper.","PeriodicalId":106476,"journal":{"name":"2020 IEEE Power & Energy Society General Meeting (PESGM)","volume":"107 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-08-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2020 IEEE Power & Energy Society General Meeting (PESGM)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PESGM41954.2020.9281706","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5
Abstract
The integration of offshore floating wind turbine generation (WTG) with offshore O&G platforms in the off-grid configuration which is a business model that is in the process of developing in the North Sea. As such, an integrated system consisting of an offshore floating WTG and O&G production platforms with onboard battery energy storage system (BESS) is proposed in this paper. In simulation, there are 4 different scenarios and results show that conventional system has high transient stability which do not meet the IEC standards for O&G platforms. The simulation has shown proposed system 2 which has incorporated with BESS 1 and BESS 2, has a reduction in transient deviation that can meets the IEC standards. In addition, capital expenditure (CapEx) and operational expenditure (OpEx) of proposed system 2 is presented in this paper.