Pengaruh Geometri Jalan Tambang Terhadap Produksi Alat Angkut Tambang Batubara PT Hillconjaya Sakti Jobsite Sebuku Tanjung Coal, Kecamatan Pulau Laut Tengah, Kabupaten Kotabaru, Provinsi Kalimantan Selatan
{"title":"Pengaruh Geometri Jalan Tambang Terhadap Produksi Alat Angkut Tambang Batubara PT Hillconjaya Sakti Jobsite Sebuku Tanjung Coal, Kecamatan Pulau Laut Tengah, Kabupaten Kotabaru, Provinsi Kalimantan Selatan","authors":"Ahmad Heriansyah, Iswandaru, Noor Fauzi Isniarno","doi":"10.29313/bcsme.v3i1.6076","DOIUrl":null,"url":null,"abstract":"Abstract. PT Hillconjaya Sakti is a mining contractor company whose job is to strip coal and overburden with an overburden production target of 291.937 BCM/month on one of the PC 2000 excavator loaders with actual production of 266.043 BCM/month. The problem in this study is the design of the overburden stripping haul road which is not ideal causing less than optimal productivity. So it is necessary to evaluate the geometry of the road which aims to determine the ideal haul road design, compare the target production of the conveyance with production after repair and find out the cycle time of the conveyance in overburden hauling activities .The research was conducted in the overburden area from front loading to disposal at South T3 Pit with HD Sanyi SRT 95C conveyor with a capacity of 42 m2. The data collected is crossslope, superelevation and maximum speed of the conveyance under certain road grade conditions and also the T-junctions formed on the haul road.. In the research results there are many road segments that have not reached the ideal criteria in road geometry, especially in the front loading area. The results of calculating the ideal geometry are 21,33 m for one lane, 25,55 m for bends, 1,02 m super elevation and 42,6 cm crossslope. The results of road repairs will cause a decrease in the circulation time or cycle time of the transportation equipment, there is a change in the cycle time of the transportation equipment, namely 13,97 minutes, 14,3 minutes, 14,02 minutes, 14,05, 14,2 minutes to 10,48 minutes so there was an increase in the production of transportation equipment to 336.982 BCM/month. \nAbstrak. PT Hillconjaya sakti merupakan perusahaan kontraktor penambangan yang bertugas dalam melakukan pengupasan batubara dan overburden dengan target produksi overburden sebesar 291.937 BCM/bulan pada salah satu alat muat excavator PC 2000 dengan produksi aktual 266.043 BCM/bulan. Permasalahan dalam penelitian ini adalah perancangan pada jalan angkut pengupasan overburden yang tidak ideal menyebabkan produktivitas kurang optimal. Maka perlu dilakukan evaluasi geometri jalan yang bertujuan untuk melakukan penentuan rancangan jalan angkut ideal, melakukan perbandingan target produksi alat angkut dengan produksi setelah perbaikan dan Mengetahui cycle time dari alat angkut pada kegiatan pengangkutan overburden.. Penelitian dilakukan pada area overburden dari front loading ke disposal di Pit T3 Selatan dengan alat angkut HD Sanyi SRT 95C dengan kapasitas 42 m2. Data yang dikumpulkan adalah data crossslope, superelevasi serta kecepatan maksimal alat angkut dalam kondisi grade jalan tertentu dan juga pertigaan yang terbentuk pada jalan angkut.. Pada hasil penelitian terdapat banyak segmen jalan yang belum mencapai dari kriteria ideal pada geometri jalan khusus nya pada daerah front loading. Hasil dari perhitungan geometri ideal yaitu 21,33 m untuk satu jalur,jalur tikungan 25,55 m, superelevasi 1,02 m dan crossslope 42,6 cm. Hasil perbaikan jalan akan menyebabkan penurunan waktu edar atau cycle time alat angkut, terjadi perubahan cycle time alat angkut yaitu 13,97 menit, 14,3 menit, 14,02 menit, 14,05, 14,2 menit menjadi 10,48 menit sehingga terjadi peningkatan produksi alat angkut menjadi 336.982 BCM/Bulan.","PeriodicalId":187584,"journal":{"name":"Bandung Conference Series: Mining Engineering","volume":"47 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-01-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bandung Conference Series: Mining Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29313/bcsme.v3i1.6076","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Abstract. PT Hillconjaya Sakti is a mining contractor company whose job is to strip coal and overburden with an overburden production target of 291.937 BCM/month on one of the PC 2000 excavator loaders with actual production of 266.043 BCM/month. The problem in this study is the design of the overburden stripping haul road which is not ideal causing less than optimal productivity. So it is necessary to evaluate the geometry of the road which aims to determine the ideal haul road design, compare the target production of the conveyance with production after repair and find out the cycle time of the conveyance in overburden hauling activities .The research was conducted in the overburden area from front loading to disposal at South T3 Pit with HD Sanyi SRT 95C conveyor with a capacity of 42 m2. The data collected is crossslope, superelevation and maximum speed of the conveyance under certain road grade conditions and also the T-junctions formed on the haul road.. In the research results there are many road segments that have not reached the ideal criteria in road geometry, especially in the front loading area. The results of calculating the ideal geometry are 21,33 m for one lane, 25,55 m for bends, 1,02 m super elevation and 42,6 cm crossslope. The results of road repairs will cause a decrease in the circulation time or cycle time of the transportation equipment, there is a change in the cycle time of the transportation equipment, namely 13,97 minutes, 14,3 minutes, 14,02 minutes, 14,05, 14,2 minutes to 10,48 minutes so there was an increase in the production of transportation equipment to 336.982 BCM/month.
Abstrak. PT Hillconjaya sakti merupakan perusahaan kontraktor penambangan yang bertugas dalam melakukan pengupasan batubara dan overburden dengan target produksi overburden sebesar 291.937 BCM/bulan pada salah satu alat muat excavator PC 2000 dengan produksi aktual 266.043 BCM/bulan. Permasalahan dalam penelitian ini adalah perancangan pada jalan angkut pengupasan overburden yang tidak ideal menyebabkan produktivitas kurang optimal. Maka perlu dilakukan evaluasi geometri jalan yang bertujuan untuk melakukan penentuan rancangan jalan angkut ideal, melakukan perbandingan target produksi alat angkut dengan produksi setelah perbaikan dan Mengetahui cycle time dari alat angkut pada kegiatan pengangkutan overburden.. Penelitian dilakukan pada area overburden dari front loading ke disposal di Pit T3 Selatan dengan alat angkut HD Sanyi SRT 95C dengan kapasitas 42 m2. Data yang dikumpulkan adalah data crossslope, superelevasi serta kecepatan maksimal alat angkut dalam kondisi grade jalan tertentu dan juga pertigaan yang terbentuk pada jalan angkut.. Pada hasil penelitian terdapat banyak segmen jalan yang belum mencapai dari kriteria ideal pada geometri jalan khusus nya pada daerah front loading. Hasil dari perhitungan geometri ideal yaitu 21,33 m untuk satu jalur,jalur tikungan 25,55 m, superelevasi 1,02 m dan crossslope 42,6 cm. Hasil perbaikan jalan akan menyebabkan penurunan waktu edar atau cycle time alat angkut, terjadi perubahan cycle time alat angkut yaitu 13,97 menit, 14,3 menit, 14,02 menit, 14,05, 14,2 menit menjadi 10,48 menit sehingga terjadi peningkatan produksi alat angkut menjadi 336.982 BCM/Bulan.
煤矿道路几何形状对煤矿运输设备生产的影响 PT Hillconjaya Sakti 工作地点 Sebuku Tanjung 煤矿,南加里曼丹省 Kotabaru 县 Central Laut 岛区
摘要。PT hillconaya Sakti是一家采矿承包商公司,其工作是剥离煤炭和覆盖层,覆盖层产量目标为291.937 BCM/月,PC 2000挖掘机装载机的实际产量为266.043 BCM/月。本文研究的问题是覆盖层剥脱运输道路设计不理想,导致生产效率达不到最优。因此,有必要对道路的几何形状进行评价,以确定理想的运输道路设计,并将运输工具的目标产量与修复后的产量进行比较,找出运输工具在覆盖层运输活动中的周期时间。采用容量为42 m2的HD三易SRT 95C输送机对南T3坑覆盖层从前装到处置进行了研究。所收集的数据是在一定道路坡度条件下运输工具的横断面、超标高和最大速度,以及运输道路上形成的t形路口。在研究结果中,有许多路段在道路几何形状上没有达到理想的标准,特别是在前加载区域。计算结果表明,理想的几何形状为单车道21,33 m,弯道25,55 m,超高程1,02 m,横坡42,6 cm。道路维修的结果将导致运输设备的循环时间或周期时间的减少,运输设备的周期时间发生变化,即13.97分钟、14.3分钟、14.02分钟、14.05、14.2分钟到10.48分钟,因此运输设备的产量增加到336.982 BCM/月。Abstrak。PT hillconaya sakti merupakan perusahaan kontraktor penambangan yang bertugas dalam melakukan企鹅batubara dan覆盖层登干目标产品覆盖层sebesar 291.937 BCM/bulan pada salah satu alat muat挖掘机PC 2000登干产品实际266.043 BCM/bulan。企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅覆盖,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅,企鹅Maka perlu dilakukan评估几何,jalan yang bertujuan untuk melakukan penentuan ranangan jangkut理想,melakukan perbandan目标产品,alat angkut dengan产品,setelah perbaikan dan Mengetahui循环时间,alat angkut paada kegiatan pengangkutan覆盖层。Penelitian dilakukan padas地区覆盖层dari前加载,如处置di Pit T3 Selatan dengan alat angkut HD Sanyi SRT 95C dengan kapasitas 42 m2。数据yang dikumpulkan adalah数据坡度,superelevasi serta keepatan maksimal alat angkut dalam kondisi等级jalan tertentu dan juga pertigaan yang terbentuk pada jalan angkut..Pada hasil penelitian terdapat banyak节,jalan yang belum mencapai dari标准,理想的Pada几何,jalan khusus nya Pada daerah前加载。哈西尔达里perhitungan的理想几何尺寸为21,33 m,高度为25,55 m,高度为1,02 m,坡度为42,6 cm。Hasil perbaikan jalan akan menyebabkan penurunan waktu edar atau周期时间alat angkut, terjadi perubahan周期时间alat angkut yitu 13,97 menit, 14,3 menit, 14,02 menit, 14,05, 14,2 menit menjadi 10,48 menit seingga terjadi peningkatan producksi alat angkut menjadi 336.982 BCM/Bulan。