{"title":"Performance improvements in horizontally integrated production networks through real-time reschedulingin the event of disruptions","authors":"Peter Burggraf, Johannes Wagne, Oliver Bischoff","doi":"10.24425/mper.2019.129596","DOIUrl":null,"url":null,"abstract":"Received: 23 November 2018 Abstract Accepted: 13 August 2019 Rescheduling is a frequently used reactive strategy in order to limit the effects of disruptions on throughput times in multi-stage production processes. However, organizational deficits often cause delays in the information on disruptions, so rescheduling cannot limit disruption effects on throughput times optimally. Our approach strives for an investigation of possible performance improvements in multi-stage production processes enabled by realtime rescheduling in the event of disruptions. We developed a methodology whereby we could measure these possible performance improvements. For this purpose, we created and implemented a simulation model of a multi-stage production process. We defined system parameters and varied factors according to our experiment design, such as information delay, lot sizes and disruption durations. The simulation results were plotted and evaluated using DoE methodology. Dependent on the factor settings, we were able to prove large improvements by real-time rescheduling regarding the absorption of disruption effects in our experiments.","PeriodicalId":45454,"journal":{"name":"Management and Production Engineering Review","volume":"1995 9","pages":"0"},"PeriodicalIF":0.9000,"publicationDate":"2023-11-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Management and Production Engineering Review","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24425/mper.2019.129596","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 1
Abstract
Received: 23 November 2018 Abstract Accepted: 13 August 2019 Rescheduling is a frequently used reactive strategy in order to limit the effects of disruptions on throughput times in multi-stage production processes. However, organizational deficits often cause delays in the information on disruptions, so rescheduling cannot limit disruption effects on throughput times optimally. Our approach strives for an investigation of possible performance improvements in multi-stage production processes enabled by realtime rescheduling in the event of disruptions. We developed a methodology whereby we could measure these possible performance improvements. For this purpose, we created and implemented a simulation model of a multi-stage production process. We defined system parameters and varied factors according to our experiment design, such as information delay, lot sizes and disruption durations. The simulation results were plotted and evaluated using DoE methodology. Dependent on the factor settings, we were able to prove large improvements by real-time rescheduling regarding the absorption of disruption effects in our experiments.
期刊介绍:
Management and Production Engineering Review (MPER) is a peer-refereed, international, multidisciplinary journal covering a broad spectrum of topics in production engineering and management. Production engineering is a currently developing stream of science encompassing planning, design, implementation and management of production and logistic systems. Orientation towards human resources factor differentiates production engineering from other technical disciplines. The journal aims to advance the theoretical and applied knowledge of this rapidly evolving field, with a special focus on production management, organisation of production processes, management of production knowledge, computer integrated management of production flow, enterprise effectiveness, maintainability and sustainable manufacturing, productivity and organisation, forecasting, modelling and simulation, decision making systems, project management, innovation management and technology transfer, quality engineering and safety at work, supply chain optimization and logistics. Management and Production Engineering Review is published under the auspices of the Polish Academy of Sciences Committee on Production Engineering and Polish Association for Production Management.