Multi-objective planning for time-cost trade-offs in multi-project parallel environment

IF 3.9 2区 工程技术 Q1 ENGINEERING, CIVIL Engineering, Construction and Architectural Management Pub Date : 2024-03-26 DOI:10.1108/ecam-08-2023-0867
Jing An, Suicheng Li, Xiao Ping Wu
{"title":"Multi-objective planning for time-cost trade-offs in multi-project parallel environment","authors":"Jing An, Suicheng Li, Xiao Ping Wu","doi":"10.1108/ecam-08-2023-0867","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study focuses on resource-constrained project scheduling in multi-project environments. The research simplifies the problem by adopting a single-project perspective using gain coefficients.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>It employs uncertainty theory and multi-objective programming to construct a model. The optimal solution is identified using Matlab, while LINGO determines satisfactory alternatives. By combining these methods and considering actual construction project situations, a compromise solution closely approximating the optimal one is derived.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>The study provides fresh insights into modeling and resolving resource-constrained project scheduling issues, supported by real-world examples that effectively illustrate its practical significance.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>The research highlights three main contributions: effective resource utilization, project prioritization and conflict management, and addressing uncertainty. It offers decision support for project managers to balance resource allocation, resolve conflicts, and adapt to changing project demands.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":"127 1","pages":""},"PeriodicalIF":3.9000,"publicationDate":"2024-03-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-08-2023-0867","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0

Abstract

Purpose

Project managers bear the responsibility of selecting and developing resource scheduling methods that align with project requirements and organizational circumstances. This study focuses on resource-constrained project scheduling in multi-project environments. The research simplifies the problem by adopting a single-project perspective using gain coefficients.

Design/methodology/approach

It employs uncertainty theory and multi-objective programming to construct a model. The optimal solution is identified using Matlab, while LINGO determines satisfactory alternatives. By combining these methods and considering actual construction project situations, a compromise solution closely approximating the optimal one is derived.

Findings

The study provides fresh insights into modeling and resolving resource-constrained project scheduling issues, supported by real-world examples that effectively illustrate its practical significance.

Originality/value

The research highlights three main contributions: effective resource utilization, project prioritization and conflict management, and addressing uncertainty. It offers decision support for project managers to balance resource allocation, resolve conflicts, and adapt to changing project demands.

查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
多项目并行环境中时间成本权衡的多目标规划
目的项目经理有责任选择和制定符合项目要求和组织环境的资源调度方法。本研究侧重于多项目环境中的资源受限项目调度。设计/方法/途径它采用不确定性理论和多目标程序设计来构建模型。利用 Matlab 确定最优解,同时利用 LINGO 确定令人满意的替代方案。研究结果该研究为资源受限的项目调度问题的建模和解决提供了新的见解,并辅以实际案例,有效地说明了其实际意义。它为项目经理平衡资源分配、解决冲突和适应不断变化的项目需求提供了决策支持。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
Engineering, Construction and Architectural Management
Engineering, Construction and Architectural Management Business, Management and Accounting-General Business,Management and Accounting
CiteScore
8.10
自引率
19.50%
发文量
226
期刊介绍: ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process. ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.
期刊最新文献
Production-oriented approach for optimal mass-customisation of floor panel layouts in cross-laminated timber (CLT) buildings A decision-support system for choosing between traditional and alternative project delivery methods for bundled projects Traversing the complexity of digital construction and beyond through soft skills: experiences of Malaysian architects Blockchain-enhanced computer vision approach for remote safety inspection in construction A novel approach for integrating BIM and green building rating systems in the construction projects design phase
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1