Examining the financial uncertainty of an alliance project from the perspective of the contracting parties

Pertti Lahdenperä
{"title":"Examining the financial uncertainty of an alliance project from the perspective of the contracting parties","authors":"Pertti Lahdenperä","doi":"10.1088/1755-1315/1389/1/012019","DOIUrl":null,"url":null,"abstract":"A project alliance is a project delivery system in which the owner and service providers share the risks associated with the project. The aim of this paper is to increase understanding of the functioning of the payment bases of alliance projects, especially from the perspective of diverse uncertainty. The work is based on the plans and contracts of one of the implemented alliance projects and on modelling the project’s payment system. The developed model was simulated taking into consideration the multiple uncertainties associated with the project. The compensation paid by the owner to the service providers and the service providers’ consortium fee were examined in particular. Alongside the original model based on the project’s contract, some alternative instances were also defined. The focus was on the effect of the cost escalation and on the transfer of the corresponding risk to the alliance, as according to the contract the inflation risk of the project lay with the owner. In addition, the model was examined in situations where uncertainty increases significantly, or risk events tend to co-occur. At their most extreme, the risks were assumed to be so high that the service providers’ loss limitation clause could have steered the determination of compensation. The contribution of the work is in illustrating the effect of different contractual solutions and broadening our understanding of the functionality and sensitivity of the alliance payment system.","PeriodicalId":14556,"journal":{"name":"IOP Conference Series: Earth and Environmental Science","volume":"42 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"IOP Conference Series: Earth and Environmental Science","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1088/1755-1315/1389/1/012019","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A project alliance is a project delivery system in which the owner and service providers share the risks associated with the project. The aim of this paper is to increase understanding of the functioning of the payment bases of alliance projects, especially from the perspective of diverse uncertainty. The work is based on the plans and contracts of one of the implemented alliance projects and on modelling the project’s payment system. The developed model was simulated taking into consideration the multiple uncertainties associated with the project. The compensation paid by the owner to the service providers and the service providers’ consortium fee were examined in particular. Alongside the original model based on the project’s contract, some alternative instances were also defined. The focus was on the effect of the cost escalation and on the transfer of the corresponding risk to the alliance, as according to the contract the inflation risk of the project lay with the owner. In addition, the model was examined in situations where uncertainty increases significantly, or risk events tend to co-occur. At their most extreme, the risks were assumed to be so high that the service providers’ loss limitation clause could have steered the determination of compensation. The contribution of the work is in illustrating the effect of different contractual solutions and broadening our understanding of the functionality and sensitivity of the alliance payment system.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
从签约方的角度研究联盟项目的财务不确定性
项目联盟是一种项目交付系统,其中业主和服务供应商分担与项目相关的风险。本文旨在加深对联盟项目支付基础功能的理解,特别是从各种不确定性的角度。这项工作以一个已实施的联盟项目的计划和合同为基础,并对项目的支付系统进行建模。考虑到与项目相关的多种不确定性,对所开发的模型进行了模拟。对业主支付给服务供应商的补偿金和服务供应商的联盟酬金进行了特别研究。除了基于项目合同的原始模型外,还定义了一些替代实例。重点是成本上升的影响以及相应风险向联盟的转移,因为根据合同,项目的通货膨胀风险由业主承担。此外,在不确定性显著增加或风险事件往往同时发生的情况下,也对模型进行了研究。在最极端的情况下,假设风险非常高,以至于服务供应商的损失限制条款可以指导赔偿的确定。这项工作的贡献在于说明了不同合同解决方案的效果,并拓宽了我们对联盟支付系统的功能和敏感性的认识。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
CiteScore
1.00
自引率
0.00%
发文量
0
期刊最新文献
Peer Review Statement Response Surface Methodological Approach for the Adsorptive Removal of Geosmin and 2-Methylisoborneol on Sodium Hydroxide-Treated Powdered Activated Carbon Torrefaction performance of Macadamia husk under a flue gas atmosphere for solid biofuel applications Assessing the Techno-Economics of Solar-Assisted Absorption Air Conditioning in a University Building in Jordan Wyoming's produced water: Analysis and green hydrogen potential
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1