Spray dust control measures of tunnel blasting dust based on CFD dust-droplet coupling model and orthogonal test

IF 6.7 1区 工程技术 Q1 CONSTRUCTION & BUILDING TECHNOLOGY Tunnelling and Underground Space Technology Pub Date : 2024-11-22 DOI:10.1016/j.tust.2024.106233
Zheng Chen , Shulei Zhao , Chen Dong , Shuaishuai Wang , Yabin Guo , Xuan Gao , Bing Sun , Wengan Chen , Chun Guo
{"title":"Spray dust control measures of tunnel blasting dust based on CFD dust-droplet coupling model and orthogonal test","authors":"Zheng Chen ,&nbsp;Shulei Zhao ,&nbsp;Chen Dong ,&nbsp;Shuaishuai Wang ,&nbsp;Yabin Guo ,&nbsp;Xuan Gao ,&nbsp;Bing Sun ,&nbsp;Wengan Chen ,&nbsp;Chun Guo","doi":"10.1016/j.tust.2024.106233","DOIUrl":null,"url":null,"abstract":"<div><div>In extra-long tunnels, the dust generated by blasting excavation is difficult to discharge through ventilation, which can easily lead to secondary dust generation, severely affecting the health of construction personnel inside the tunnel and potentially increasing the construction interval. To shorten the dust removal time and enhance efficiency during tunnel blasting, this study utilized a single-hole single-track railway tunnel to conduct on-site measurements and numerical simulations of blasting dust. The effectiveness of the dust mist coupling model was validated through indoor model experiments, showing a maximum deviation of 16.94 % between the average concentration at numerical simulation monitoring points and that from model test measurements. Additionally, the model’s stability was assessed using three grid sizes: coarse, medium, and fine, with the maximum relative change in dust removal rate reaching 14.75 %. In combination with the original forced ventilation system, a three-section spray dedusting method was designed. The first nozzle was positioned at the center of the forced air duct outlet, with a nozzle diameter of SH2.4 mm. The second section, located 50 m from the tunnel face, contained two nozzles placed at the top and bottom of the section. The third section, situated approximately 100 m from the tunnel face, featured two X-core circular nozzles with a diameter of 2 mm, operating at a spray pressure of 8 MPa. Nine groups of orthogonal experiments were designed using CFD, identifying the spray angle, compressed air duct volume, and spray ring spacing as the most influential factors in dust removal time. Through the addition of Experiment 10 to the orthogonal set and subsequent comparisons, the optimal spray parameters were determined to be a spray angle of 15°, a compressed air duct air volume of 26 m<sup>3</sup>/s, and a spray ring spacing of 50 m. Based on the analysis of numerical results, it can be concluded that the spray dust reduction measures effectively reduced the dust concentration within 200 m of the tunnel face to a safe level 900 s after blasting.</div></div>","PeriodicalId":49414,"journal":{"name":"Tunnelling and Underground Space Technology","volume":"156 ","pages":"Article 106233"},"PeriodicalIF":6.7000,"publicationDate":"2024-11-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Tunnelling and Underground Space Technology","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0886779824006515","RegionNum":1,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

Abstract

In extra-long tunnels, the dust generated by blasting excavation is difficult to discharge through ventilation, which can easily lead to secondary dust generation, severely affecting the health of construction personnel inside the tunnel and potentially increasing the construction interval. To shorten the dust removal time and enhance efficiency during tunnel blasting, this study utilized a single-hole single-track railway tunnel to conduct on-site measurements and numerical simulations of blasting dust. The effectiveness of the dust mist coupling model was validated through indoor model experiments, showing a maximum deviation of 16.94 % between the average concentration at numerical simulation monitoring points and that from model test measurements. Additionally, the model’s stability was assessed using three grid sizes: coarse, medium, and fine, with the maximum relative change in dust removal rate reaching 14.75 %. In combination with the original forced ventilation system, a three-section spray dedusting method was designed. The first nozzle was positioned at the center of the forced air duct outlet, with a nozzle diameter of SH2.4 mm. The second section, located 50 m from the tunnel face, contained two nozzles placed at the top and bottom of the section. The third section, situated approximately 100 m from the tunnel face, featured two X-core circular nozzles with a diameter of 2 mm, operating at a spray pressure of 8 MPa. Nine groups of orthogonal experiments were designed using CFD, identifying the spray angle, compressed air duct volume, and spray ring spacing as the most influential factors in dust removal time. Through the addition of Experiment 10 to the orthogonal set and subsequent comparisons, the optimal spray parameters were determined to be a spray angle of 15°, a compressed air duct air volume of 26 m3/s, and a spray ring spacing of 50 m. Based on the analysis of numerical results, it can be concluded that the spray dust reduction measures effectively reduced the dust concentration within 200 m of the tunnel face to a safe level 900 s after blasting.

Abstract Image

查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
基于 CFD 尘滴耦合模型和正交试验的隧道爆破粉尘喷雾防尘措施
在超长隧道中,爆破开挖产生的粉尘难以通过通风排出,容易导致二次扬尘产生,严重影响隧道内施工人员的健康,并有可能增加施工间隔。为缩短隧道爆破时的除尘时间,提高效率,本研究利用单洞单轨铁路隧道对爆破扬尘进行了现场测量和数值模拟。通过室内模型试验验证了尘雾耦合模型的有效性,结果表明数值模拟监测点的平均浓度与模型试验测量值的最大偏差为 16.94%。此外,使用粗、中、细三种网格尺寸对模型的稳定性进行了评估,除尘率的最大相对变化达到 14.75%。结合原有的强制通风系统,设计了一种三段式喷雾除尘方法。第一个喷嘴位于强制通风管道出口的中心位置,喷嘴直径为 SH2.4mm。第二节距隧道面 50 米,包含两个喷嘴,分别位于该节的顶部和底部。第三段距离隧道面约 100 米,设有两个直径为 2 毫米的 X 型核心圆形喷嘴,喷射压力为 8 兆帕。利用 CFD 设计了九组正交实验,确定喷雾角度、压缩空气管道容积和喷雾环间距是除尘时间的最大影响因素。根据数值结果分析,可以得出结论:喷射降尘措施有效地将隧道工作面 200 米范围内的粉尘浓度降低到爆破后 900 秒的安全水平。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
Tunnelling and Underground Space Technology
Tunnelling and Underground Space Technology 工程技术-工程:土木
CiteScore
11.90
自引率
18.80%
发文量
454
审稿时长
10.8 months
期刊介绍: Tunnelling and Underground Space Technology is an international journal which publishes authoritative articles encompassing the development of innovative uses of underground space and the results of high quality research into improved, more cost-effective techniques for the planning, geo-investigation, design, construction, operation and maintenance of underground and earth-sheltered structures. The journal provides an effective vehicle for the improved worldwide exchange of information on developments in underground technology - and the experience gained from its use - and is strongly committed to publishing papers on the interdisciplinary aspects of creating, planning, and regulating underground space.
期刊最新文献
A novel hybrid SPH-DEM approach for simulating rockburst behavior in tunnel excavation Damage distribution characteristics and space optimizations of the large-diameter deep multi-holes blasting in thick ore bodies A novel global re-localization method for underground mining vehicles in haulage roadways: A case study of solid-state LiDAR-equipped load-haul-dump vehicles Mechanical properties and damage characteristics of granite surrounding rock in deep tunnel under thermal-hydro-mechanical coupling condition Raise boring machines – A comprehensive review of performance prediction and operational challenges
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1