Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method (CPM)

Ahmad Nalhadi, Nana Suntana
{"title":"Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method (CPM)","authors":"Ahmad Nalhadi, Nana Suntana","doi":"10.30656/jsmi.v1i1.167","DOIUrl":null,"url":null,"abstract":"CV. ABP a construction company worked in infrastructure building development for private and goverment. Now CV. ABP is handling infrastructure development project of the acropolitan area (Right Payment) Sukaci - Baros Village. This project has been late for 19 days from the dead line 126 days. Therefore the cost is getting higher. It happened because bad management is the problem source. Restoring the project time need to be focused on the cost and the due date based on the schedule. Scheduling evaluation using Critical Path Method (CPM) and Crashing to find optimal results using Critical Path Method (CPM) can be found the critical paths activity, there are ground digging , bopflang installation, stone installation, agregrate B agrgregation , aggregate A flatting, rigit bavement work, and refining, when the time suppression obtained optimal time results from 126 days to 92 days. It taken an alternative to the addition of working hours with duration 92 day after the crashing. Using two alternatives, additional working hours and the addition of workforce, obtaining the difference of extra hours of work cost Rp 80.128.125 and labourcost increase Rp 55.260 from the regular cost.","PeriodicalId":53057,"journal":{"name":"Jurnal Sistem dan Manajemen Industri","volume":"1 1","pages":"35-42"},"PeriodicalIF":0.0000,"publicationDate":"2017-08-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Sistem dan Manajemen Industri","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30656/jsmi.v1i1.167","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 4

Abstract

CV. ABP a construction company worked in infrastructure building development for private and goverment. Now CV. ABP is handling infrastructure development project of the acropolitan area (Right Payment) Sukaci - Baros Village. This project has been late for 19 days from the dead line 126 days. Therefore the cost is getting higher. It happened because bad management is the problem source. Restoring the project time need to be focused on the cost and the due date based on the schedule. Scheduling evaluation using Critical Path Method (CPM) and Crashing to find optimal results using Critical Path Method (CPM) can be found the critical paths activity, there are ground digging , bopflang installation, stone installation, agregrate B agrgregation , aggregate A flatting, rigit bavement work, and refining, when the time suppression obtained optimal time results from 126 days to 92 days. It taken an alternative to the addition of working hours with duration 92 day after the crashing. Using two alternatives, additional working hours and the addition of workforce, obtaining the difference of extra hours of work cost Rp 80.128.125 and labourcost increase Rp 55.260 from the regular cost.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
用Critical Path Method方法分析Sukaci-Baros村基础设施(CPM)
简历。ABP是一家为私人和政府从事基础设施建设开发的建筑公司。现在的简历。ABP正在处理卫城地区的基础设施发展项目(Right Payment) Sukaci - Baros村。这个项目已经从截止日期126天延迟了19天。因此成本越来越高。这是因为管理不善是问题的根源。恢复项目时间需要关注基于时间表的成本和到期日期。采用关键路径法(Critical Path Method, CPM)进行调度评价,采用关键路径法(Critical Path Method, CPM)寻找最优结果,可以发现关键路径活动,有挖地、装布、装石、集料B集料、集料A铺平、铺装、精炼,其中时间抑制获得的最优时间为126 ~ 92天。在事故发生后的92天内,采取了增加工作时间的替代方案。使用额外工作时间和增加劳动力两种替代方案,获得额外工作时间成本Rp 80.128.125和劳动力成本从正常成本增加Rp 55.260的差异。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
10
审稿时长
12 weeks
期刊最新文献
Implementation system monitoring and control temperature and pH in urban silver catfish hatchery to enhance efficiency and responsiveness based on IoT Optimizing business location for small and medium enter¬prises considering travel time uncertainty, natural disasters, and density population: a study case in Jakarta Economic production quantity model with defective items, imperfect rework process, and lost sales Supply chain performance measurement incorporating green factors using the supply chain operations reference on a fertilizer company Intelligent optimisation for multi-objectives flexible manufacturing cells formation
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1