First in Place Replacement of a TLP Top Tendon Connector Flex Bearing

J. Otten, Vinu M Kuriakose, Shakib Amini
{"title":"First in Place Replacement of a TLP Top Tendon Connector Flex Bearing","authors":"J. Otten, Vinu M Kuriakose, Shakib Amini","doi":"10.1115/omae2019-96232","DOIUrl":null,"url":null,"abstract":"\n Tension Leg Platform (TLP) tendons typically are installed for the life of the platform and incorporate elastomeric flex bearings. The Allegheny TLP, owned and operated by ENI Petroleum, was installed in Gulf of Mexico Green Canyon Block 254A, in 1999. It was designed for a service life of 20 years and currently ENI wants to extend the operating life of the platform. A baseline inspection showed significant degradation of the top tendon connector (TTC) flex bearing and it was concluded that the flex bearings needed to be replaced if the platform was to continue to operate safely.\n SBM and BHGE came up with a solution for replacing the TTC including the flex bearing, which was accepted by ENI. This involved ballasting the TLP to reduce the tendon pretensions, installing a temporary buoyancy module, and using a hydraulic tool, first of its kind in the world, to take the load off of the old TTC and gradually release the tendon to free stand. The tool was then retrieved with the old TTC, onboard the installation vessel. A second identical tool with the new TTC was then lowered on to the porch and the tendon stretched to the lock-off position by the tool and locked in position with the new TTC. This was done on all six (6) tendons and the platform was de-ballasted to the original tendon pre-tensions. Development of the tendon de-tensioning tool required new designs, extensive shop testing, and planning.\n The final offshore campaign took place during July 2018 and was completed in three (3) weeks. This represented a successful conclusion to a three (3) year effort. This paper highlights lessons learned in completing a complex first time ever project and makes recommendations for the design of future TLP’s.","PeriodicalId":23567,"journal":{"name":"Volume 1: Offshore Technology; Offshore Geotechnics","volume":"50 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-11-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Volume 1: Offshore Technology; Offshore Geotechnics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/omae2019-96232","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Tension Leg Platform (TLP) tendons typically are installed for the life of the platform and incorporate elastomeric flex bearings. The Allegheny TLP, owned and operated by ENI Petroleum, was installed in Gulf of Mexico Green Canyon Block 254A, in 1999. It was designed for a service life of 20 years and currently ENI wants to extend the operating life of the platform. A baseline inspection showed significant degradation of the top tendon connector (TTC) flex bearing and it was concluded that the flex bearings needed to be replaced if the platform was to continue to operate safely. SBM and BHGE came up with a solution for replacing the TTC including the flex bearing, which was accepted by ENI. This involved ballasting the TLP to reduce the tendon pretensions, installing a temporary buoyancy module, and using a hydraulic tool, first of its kind in the world, to take the load off of the old TTC and gradually release the tendon to free stand. The tool was then retrieved with the old TTC, onboard the installation vessel. A second identical tool with the new TTC was then lowered on to the porch and the tendon stretched to the lock-off position by the tool and locked in position with the new TTC. This was done on all six (6) tendons and the platform was de-ballasted to the original tendon pre-tensions. Development of the tendon de-tensioning tool required new designs, extensive shop testing, and planning. The final offshore campaign took place during July 2018 and was completed in three (3) weeks. This represented a successful conclusion to a three (3) year effort. This paper highlights lessons learned in completing a complex first time ever project and makes recommendations for the design of future TLP’s.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
TLP顶部肌腱接头伸缩轴承的首次原位更换
张力腿平台(TLP)肌腱通常安装在平台的使用寿命内,并包含弹性伸缩轴承。Allegheny TLP由ENI石油公司拥有并运营,于1999年安装在墨西哥湾Green Canyon区块254A。它的设计使用寿命为20年,目前ENI希望延长平台的使用寿命。基线检查显示,顶部肌腱连接器(TTC)弯曲轴承明显退化,如果平台要继续安全运行,则需要更换弯曲轴承。SBM和BHGE提出了替换TTC的解决方案,包括伸缩轴承,该方案被ENI接受。这包括压载张力腿平台以减少肌腱张力,安装临时浮力模块,并使用世界上第一个液压工具来减轻旧TTC的负荷,并逐渐释放肌腱,使其自由站立。然后,该工具与旧TTC一起被回收到安装船上。然后将第二个与新TTC相同的工具放置在门廊上,将肌腱拉伸到锁定位置,并与新TTC锁定在一起。在所有6根肌腱上进行了这一操作,并将平台卸压至原始肌腱预张力。肌腱去张力工具的开发需要新的设计、大量的车间测试和规划。最后一次海上作业于2018年7月进行,并在三(3)周内完成。这标志着三年努力的成功结束。本文重点介绍了首次完成复杂项目的经验教训,并对未来张力腿平台的设计提出了建议。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Influence of Different Pile Installation Methods on Dense Sand Estimating Second Order Wave Drift Forces and Moments for Calculating DP Capability Plots A Conjoint Analysis of the Stability and Time-Domain Analysis on Floating Platform During Mooring Line Breaking Wave Propagation in CFD-Based Numerical Wave Tank CFD Analysis on Hydrodynamic Characteristics for Optimizing Torpedo Anchors
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1