Buzios Presalt Wells: Delivering Intelligent Completion In Ultra-Deepwater Carbonate Reservoirs

E. Schnitzler, L. F. Gonçalez, Roger Savoldi Roman, M. Marques, Fábio Rosas Gutterres, Manoel Feliciano Silva, Carlos Alexandre Belo Castilho
{"title":"Buzios Presalt Wells: Delivering Intelligent Completion In Ultra-Deepwater Carbonate Reservoirs","authors":"E. Schnitzler, L. F. Gonçalez, Roger Savoldi Roman, M. Marques, Fábio Rosas Gutterres, Manoel Feliciano Silva, Carlos Alexandre Belo Castilho","doi":"10.4043/31116-ms","DOIUrl":null,"url":null,"abstract":"\n This paper describes the challenges faced on the deployment of intelligent well completion (IWC) systems in some of the wells built in Buzios field, mostly related to heavy fluid losses that occurred during the well construction. It also presents the solutions used to overcome them. This kind of event affects not only drilling and casing cementing operations, but may also prevent a safe and efficient installation of the completion system as initially designed.\n The IWC design typically used in Brazilian pre-salt areas comprises cased hole wells. Perforation operations must be performed before installing the integral completion system, as it does not include a separation between upper and lower completion. Therefore, the reservoir remains communicated to the wellbore during the whole completion installation process, frequently requiring prior fluid loss control as to allow safe deployment. Rock characteristics found in this field make it difficult to effectively control losses in some of the wells, requiring the use of different well construction practices that led to the development of some new well designs.\n The well engineering team developed a new well concept, where a separated lower completion system is installed in open hole, delivering temporary reservoir isolation. This new well architecture not only delivers reduced drilling and completion duration and costs, but also provides the IWC features in wells with major fluid losses. This is possible by the use of multiple managed pressure drilling (MPD) techniques when required, which were considered since the initial design phase. Safe and effective construction of some wells in pre-salt fields was considered not feasible before the adoption of MPD solutions, both for drilling and completions.\n Other important aspects considered on the new well design are the large thickness and high productivity of Buzios field reservoirs, as well as the need of some flexibility to deal with uncertainties. Finally, the new completion project was also designed to improve performance and safety on future challenging heavy workover interventions. The well construction area has gradually obtained improved performance in Buzios field with the adoption of the new practices and well design presented in this paper.\n The new solutions developed for Buzios field have set a new drilling and completion philosophy for pre-salt wells, setting the grounds for future projects. The improved performance is essential to keep these deepwater projects competitive, especially in challenging oil price scenarios. One of the groundbreaking solutions used is the possibility of installing the lower completion using managed pressure drilling techniques.","PeriodicalId":11072,"journal":{"name":"Day 1 Mon, August 16, 2021","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Mon, August 16, 2021","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/31116-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This paper describes the challenges faced on the deployment of intelligent well completion (IWC) systems in some of the wells built in Buzios field, mostly related to heavy fluid losses that occurred during the well construction. It also presents the solutions used to overcome them. This kind of event affects not only drilling and casing cementing operations, but may also prevent a safe and efficient installation of the completion system as initially designed. The IWC design typically used in Brazilian pre-salt areas comprises cased hole wells. Perforation operations must be performed before installing the integral completion system, as it does not include a separation between upper and lower completion. Therefore, the reservoir remains communicated to the wellbore during the whole completion installation process, frequently requiring prior fluid loss control as to allow safe deployment. Rock characteristics found in this field make it difficult to effectively control losses in some of the wells, requiring the use of different well construction practices that led to the development of some new well designs. The well engineering team developed a new well concept, where a separated lower completion system is installed in open hole, delivering temporary reservoir isolation. This new well architecture not only delivers reduced drilling and completion duration and costs, but also provides the IWC features in wells with major fluid losses. This is possible by the use of multiple managed pressure drilling (MPD) techniques when required, which were considered since the initial design phase. Safe and effective construction of some wells in pre-salt fields was considered not feasible before the adoption of MPD solutions, both for drilling and completions. Other important aspects considered on the new well design are the large thickness and high productivity of Buzios field reservoirs, as well as the need of some flexibility to deal with uncertainties. Finally, the new completion project was also designed to improve performance and safety on future challenging heavy workover interventions. The well construction area has gradually obtained improved performance in Buzios field with the adoption of the new practices and well design presented in this paper. The new solutions developed for Buzios field have set a new drilling and completion philosophy for pre-salt wells, setting the grounds for future projects. The improved performance is essential to keep these deepwater projects competitive, especially in challenging oil price scenarios. One of the groundbreaking solutions used is the possibility of installing the lower completion using managed pressure drilling techniques.
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Buzios盐下井:超深水碳酸盐岩储层智能完井技术
本文介绍了在Buzios油田的一些井中部署智能完井(IWC)系统所面临的挑战,主要与井建设过程中发生的严重流体漏失有关。它还提出了克服这些问题的解决方案。此类事件不仅会影响钻井和套管固井作业,还可能阻碍完井系统按照最初的设计安全高效地安装。IWC设计通常用于巴西盐下地区,包括套管井。射孔作业必须在安装完整完井系统之前进行,因为它不包括上部和下部完井之间的分离。因此,在整个完井安装过程中,储层与井筒保持连通,通常需要事先控制漏液,以确保安全部署。该油田的岩石特性使得一些井难以有效控制漏失,因此需要采用不同的施工方法,从而开发出一些新的井设计。井工程团队开发了一种新的井概念,在裸眼井中安装了一个分离的下部完井系统,实现了暂时的油藏隔离。这种新型井结构不仅缩短了钻井和完井时间,降低了成本,而且在流体漏失较大的井中也具有IWC的特点。这可以通过在需要时使用多重控压钻井(MPD)技术来实现,这些技术从最初的设计阶段就开始考虑了。在采用MPD解决方案进行钻井和完井之前,人们认为盐下油田的一些井的安全有效施工是不可行的。新井设计考虑的其他重要方面是Buzios油田储层的大厚度和高产能,以及需要一定的灵活性来应对不确定性。最后,新的完井项目还旨在提高未来具有挑战性的大型修井作业的性能和安全性。采用本文提出的新做法和井设计,Buzios油田的建井区域的性能逐渐得到改善。为Buzios油田开发的新解决方案为盐下井的钻井和完井奠定了新的理念,为未来的项目奠定了基础。提高性能对于保持深水项目的竞争力至关重要,尤其是在油价低迷的情况下。使用的突破性解决方案之一是使用控压钻井技术安装下部完井。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Drilling Fluids Project Engineering Guidance and Most Common Fluids Related Challenges for Deepwater and HPHT Offshore Wells Empirical Design of Optimum Frequency of Well Testing for Deepwater Operation Sustaining Oil and Gas Fields by Using Multiphase Gas Compression to Increase Production and Reserves, and Lower Operating Costs and Environmental Emissions Footprint Structural Digital Twin of FPSO for Monitoring the Hull and Topsides Based on Inspection Data and Load Measurement Application of LWD Multipole Sonic for Quantitative Cement Evaluation – Well Integrity in the Norwegian Continental Shelf
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1