{"title":"具有共同到期日的单机多订单作业调度问题的遗传算法","authors":"Jens Rocholl, L. Mönch","doi":"10.1109/COASE.2017.8256240","DOIUrl":null,"url":null,"abstract":"In this paper, we discuss a multiple orders per job (MOJ) scheduling problem. Front opening unified pods (FOUPs) transfer wafers in 300-mm wafer fabs. Several orders can be grouped in one FOUP which can be considered as a job. A lot processing environment is assumed. All the orders have an unrestrictively late common due date. The earliness and tardiness of the orders is minimized. Since the problem is NP-hard, we propose two hybridized genetic algorithms. Computational experiments on randomly generated problem instances are carried out that demonstrate that the genetic algorithms perform well.","PeriodicalId":445441,"journal":{"name":"2017 13th IEEE Conference on Automation Science and Engineering (CASE)","volume":"6 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2017-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Genetic algorithms for a single-machine multiple orders per job scheduling problem with a common due date\",\"authors\":\"Jens Rocholl, L. Mönch\",\"doi\":\"10.1109/COASE.2017.8256240\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this paper, we discuss a multiple orders per job (MOJ) scheduling problem. Front opening unified pods (FOUPs) transfer wafers in 300-mm wafer fabs. Several orders can be grouped in one FOUP which can be considered as a job. A lot processing environment is assumed. All the orders have an unrestrictively late common due date. The earliness and tardiness of the orders is minimized. Since the problem is NP-hard, we propose two hybridized genetic algorithms. Computational experiments on randomly generated problem instances are carried out that demonstrate that the genetic algorithms perform well.\",\"PeriodicalId\":445441,\"journal\":{\"name\":\"2017 13th IEEE Conference on Automation Science and Engineering (CASE)\",\"volume\":\"6 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2017 13th IEEE Conference on Automation Science and Engineering (CASE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/COASE.2017.8256240\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2017 13th IEEE Conference on Automation Science and Engineering (CASE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/COASE.2017.8256240","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Genetic algorithms for a single-machine multiple orders per job scheduling problem with a common due date
In this paper, we discuss a multiple orders per job (MOJ) scheduling problem. Front opening unified pods (FOUPs) transfer wafers in 300-mm wafer fabs. Several orders can be grouped in one FOUP which can be considered as a job. A lot processing environment is assumed. All the orders have an unrestrictively late common due date. The earliness and tardiness of the orders is minimized. Since the problem is NP-hard, we propose two hybridized genetic algorithms. Computational experiments on randomly generated problem instances are carried out that demonstrate that the genetic algorithms perform well.