在阿曼苏丹国一个价值数十亿美元的含硫油田开发项目中,采用协作方法进行生产前交叉流风险评估和缓解:案例研究

M. Cobanoglu, Abdullah Nabhani
{"title":"在阿曼苏丹国一个价值数十亿美元的含硫油田开发项目中,采用协作方法进行生产前交叉流风险评估和缓解:案例研究","authors":"M. Cobanoglu, Abdullah Nabhani","doi":"10.2118/196707-ms","DOIUrl":null,"url":null,"abstract":"\n The Yibal Khuff/Sudair reservoirs were discovered in 1977. The field contains both Non-Associated Gas in the Sudair & Lower Khuff reservoirs and Associated Gas with oil rims in the Upper Khuff reservoirs. The Upper and Lower Khuff hydrocarbons contain 2–3% H2S and 4–6% CO2, whereas the Sudair gas contain 1–1.5% CO2 and less than 50 ppm H2S. The Field Development Plan (FDP), a multibillion dollar sour development project, was completed in 2011 proposing a total of 47 wells, 34 dedicated horizontal/vertical wells for oil rim production and 13 commingled vertical/deviated gas wells, and the construction of new sour surface facilities with a gas production capacity of 6 MMm3/day.\n FDP execution started in 2016 while the details of field start-up, scheduled a few years later, were still being planned. As part of this planning, it was noticed that a number of pre-drilled wells required perforation and clean-up before facility startup. Due to the time necessary to prepare all the pre-drilled wells, pre-production wellbore cross-flow was expected to occur in wells located in the West block of the field. A dedicated subsurface team was assigned in 2017 to evaluate and mitigate the potential risks associated with this expected cross-flow through the wellbore resulting from the pressure difference between the Lower Khuff and Upper Khuff layers.\n This paper covers the integrated approach that the team followed to address the expected cross-flow issue, including: Basis for pre-production cross- flowThe quantification of the cross-flow using analytical and numerical simulation methodsThe assessment of the impact of cross-flow on process safety and the environment (i.e. drilling risks with potential blow out of sour gas) and social responsibility (i.e. production capacity and ultimate recovery losses resulting in lower benefits to the community)The identification and assessment of solutions to stop/reduce the cross-flowThe implementation of a robust and feasible mitigation plan\n The conducted study demonstrated that the impact of cross-flow at well level would be severe. The cross-flow rate could reach up to 25-137 Km3/day/well, while the field level cross-flow rate could reach up to 400 Km3/day. The oil rate capacity reduction in the West Block wells could reach 20-30% at start-up, resulting in a total only 1% oil ultimate recovery loss at field level since the West block contribution is small to total production and West block wells are constrained. The study also showed that the casing design is adequate and drilling risks are manageable even in case of cross-flow. Out of several solutions identified to stop/reduce cross-flow, phasing perforation was considered the most robust and feasible option.\n This paper presents the novel approach of a collaborative study that resulted in improved safety and reduced environmental risks and potential ultimate recovery losses. It also presents the methodologies used to allow the Assessment and Mitigation of Pre-Production Cross-flow and evaluation of the best option to mitigate the cross-flow in order to minimize the impact of cross-flow at minimum cost, well interventions and impact on well deliverable.","PeriodicalId":354509,"journal":{"name":"Day 3 Thu, September 19, 2019","volume":"43 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-09-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A Collaborative Approach to Risk Assessment and Mitigation of Pre-Production Cross-Flow for a Multi-Billion Dollar Sour Field Development Project in the Sultanate of Oman: A Case Study\",\"authors\":\"M. Cobanoglu, Abdullah Nabhani\",\"doi\":\"10.2118/196707-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The Yibal Khuff/Sudair reservoirs were discovered in 1977. The field contains both Non-Associated Gas in the Sudair & Lower Khuff reservoirs and Associated Gas with oil rims in the Upper Khuff reservoirs. The Upper and Lower Khuff hydrocarbons contain 2–3% H2S and 4–6% CO2, whereas the Sudair gas contain 1–1.5% CO2 and less than 50 ppm H2S. The Field Development Plan (FDP), a multibillion dollar sour development project, was completed in 2011 proposing a total of 47 wells, 34 dedicated horizontal/vertical wells for oil rim production and 13 commingled vertical/deviated gas wells, and the construction of new sour surface facilities with a gas production capacity of 6 MMm3/day.\\n FDP execution started in 2016 while the details of field start-up, scheduled a few years later, were still being planned. As part of this planning, it was noticed that a number of pre-drilled wells required perforation and clean-up before facility startup. Due to the time necessary to prepare all the pre-drilled wells, pre-production wellbore cross-flow was expected to occur in wells located in the West block of the field. A dedicated subsurface team was assigned in 2017 to evaluate and mitigate the potential risks associated with this expected cross-flow through the wellbore resulting from the pressure difference between the Lower Khuff and Upper Khuff layers.\\n This paper covers the integrated approach that the team followed to address the expected cross-flow issue, including: Basis for pre-production cross- flowThe quantification of the cross-flow using analytical and numerical simulation methodsThe assessment of the impact of cross-flow on process safety and the environment (i.e. drilling risks with potential blow out of sour gas) and social responsibility (i.e. production capacity and ultimate recovery losses resulting in lower benefits to the community)The identification and assessment of solutions to stop/reduce the cross-flowThe implementation of a robust and feasible mitigation plan\\n The conducted study demonstrated that the impact of cross-flow at well level would be severe. The cross-flow rate could reach up to 25-137 Km3/day/well, while the field level cross-flow rate could reach up to 400 Km3/day. The oil rate capacity reduction in the West Block wells could reach 20-30% at start-up, resulting in a total only 1% oil ultimate recovery loss at field level since the West block contribution is small to total production and West block wells are constrained. The study also showed that the casing design is adequate and drilling risks are manageable even in case of cross-flow. Out of several solutions identified to stop/reduce cross-flow, phasing perforation was considered the most robust and feasible option.\\n This paper presents the novel approach of a collaborative study that resulted in improved safety and reduced environmental risks and potential ultimate recovery losses. It also presents the methodologies used to allow the Assessment and Mitigation of Pre-Production Cross-flow and evaluation of the best option to mitigate the cross-flow in order to minimize the impact of cross-flow at minimum cost, well interventions and impact on well deliverable.\",\"PeriodicalId\":354509,\"journal\":{\"name\":\"Day 3 Thu, September 19, 2019\",\"volume\":\"43 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-09-17\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Thu, September 19, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/196707-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Thu, September 19, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/196707-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

Yibal Khuff/Sudair水库于1977年被发现。该油田包含Sudair和下Khuff储层中的非伴生气和上Khuff储层中含油环的伴生气。Upper和Lower Khuff天然气中含有2-3%的H2S和4-6%的CO2,而Sudair天然气中含有1-1.5%的CO2和低于50 ppm的H2S。油田开发计划(FDP)是一个价值数十亿美元的酸开发项目,于2011年完成,共47口井,34口专用水平/直井用于油环生产,13口混合垂直/斜井,并建设新的酸地面设施,产气量为6mm3 /天。FDP于2016年开始执行,而几年后的现场启动细节仍在计划中。作为该计划的一部分,人们注意到,在设施启动之前,许多预钻井需要射孔和清理。由于准备所有预钻井需要时间,预计将在油田西部区块的井中进行预生产井眼过流。2017年,该公司成立了一个专门的地下团队,以评估和减轻由于Lower Khuff层和Upper Khuff层之间的压力差而导致的井筒交叉流的潜在风险。本文涵盖了团队所遵循的解决预期的交叉流问题的集成方法,包括:生产前交叉流的基础使用分析和数值模拟方法对交叉流进行量化评估交叉流对过程安全和环境的影响(即潜在的吹出含酸气体的钻井风险)和社会责任(即生产能力和最终回收损失导致社区效益降低)识别和评估停止/减少交叉流的解决方案实施稳健和可行的缓解方案所进行的研究表明,井面上的横流影响将是严重的。井侧流量可达25 ~ 137 Km3/天,而现场侧流量可达400 Km3/天。由于西部区块对总产量的贡献很小,并且西部区块的井受到限制,因此在启动时,西部区块油井的产油能力下降可能达到20-30%,导致油田最终采收率总计仅为1%。研究还表明,套管设计是合理的,即使在交叉流的情况下,钻井风险也是可控的。在已确定的几种停止/减少交叉流的解决方案中,相位射孔被认为是最稳健和可行的选择。本文提出了一种新的合作研究方法,该方法提高了安全性,降低了环境风险和潜在的最终采收率损失。本文还介绍了用于评估和缓解生产前交叉流的方法,以及评估缓解交叉流的最佳方案,以便以最小的成本、油井干预和对油井产量的影响最小化。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
A Collaborative Approach to Risk Assessment and Mitigation of Pre-Production Cross-Flow for a Multi-Billion Dollar Sour Field Development Project in the Sultanate of Oman: A Case Study
The Yibal Khuff/Sudair reservoirs were discovered in 1977. The field contains both Non-Associated Gas in the Sudair & Lower Khuff reservoirs and Associated Gas with oil rims in the Upper Khuff reservoirs. The Upper and Lower Khuff hydrocarbons contain 2–3% H2S and 4–6% CO2, whereas the Sudair gas contain 1–1.5% CO2 and less than 50 ppm H2S. The Field Development Plan (FDP), a multibillion dollar sour development project, was completed in 2011 proposing a total of 47 wells, 34 dedicated horizontal/vertical wells for oil rim production and 13 commingled vertical/deviated gas wells, and the construction of new sour surface facilities with a gas production capacity of 6 MMm3/day. FDP execution started in 2016 while the details of field start-up, scheduled a few years later, were still being planned. As part of this planning, it was noticed that a number of pre-drilled wells required perforation and clean-up before facility startup. Due to the time necessary to prepare all the pre-drilled wells, pre-production wellbore cross-flow was expected to occur in wells located in the West block of the field. A dedicated subsurface team was assigned in 2017 to evaluate and mitigate the potential risks associated with this expected cross-flow through the wellbore resulting from the pressure difference between the Lower Khuff and Upper Khuff layers. This paper covers the integrated approach that the team followed to address the expected cross-flow issue, including: Basis for pre-production cross- flowThe quantification of the cross-flow using analytical and numerical simulation methodsThe assessment of the impact of cross-flow on process safety and the environment (i.e. drilling risks with potential blow out of sour gas) and social responsibility (i.e. production capacity and ultimate recovery losses resulting in lower benefits to the community)The identification and assessment of solutions to stop/reduce the cross-flowThe implementation of a robust and feasible mitigation plan The conducted study demonstrated that the impact of cross-flow at well level would be severe. The cross-flow rate could reach up to 25-137 Km3/day/well, while the field level cross-flow rate could reach up to 400 Km3/day. The oil rate capacity reduction in the West Block wells could reach 20-30% at start-up, resulting in a total only 1% oil ultimate recovery loss at field level since the West block contribution is small to total production and West block wells are constrained. The study also showed that the casing design is adequate and drilling risks are manageable even in case of cross-flow. Out of several solutions identified to stop/reduce cross-flow, phasing perforation was considered the most robust and feasible option. This paper presents the novel approach of a collaborative study that resulted in improved safety and reduced environmental risks and potential ultimate recovery losses. It also presents the methodologies used to allow the Assessment and Mitigation of Pre-Production Cross-flow and evaluation of the best option to mitigate the cross-flow in order to minimize the impact of cross-flow at minimum cost, well interventions and impact on well deliverable.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Middle East Karst Carbonate: An Integrated Workflow For Prediction Of Karst Enhancement Distribution Potential Applicability of Miscible N2 Flooding in High-Temperature Abu Dhabi Reservoir Modelling Dispersed Chemical Droplets Injection in the Gas Stream for EOR Applications A Collaborative Approach to Risk Assessment and Mitigation of Pre-Production Cross-Flow for a Multi-Billion Dollar Sour Field Development Project in the Sultanate of Oman: A Case Study Multidisciplinary Approach for Unconventional Reservoirs Characterisation by Integrating Wireline Openhole Logging Techniques – Electric and Sonic to Formation Testing
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1