竞争环境下的综合发电和输电规划

I. Elamin, Mohammed T. Al-Saba
{"title":"竞争环境下的综合发电和输电规划","authors":"I. Elamin, Mohammed T. Al-Saba","doi":"10.1109/POWERENG.2009.4915202","DOIUrl":null,"url":null,"abstract":"In a deregulated power system, generation companies would like to maximize their profits and share of the electricity market. This can only be achieved if transmission access and network availability is satisfactory. New mathematical models for generation and transmission planning are thus needed. The problem is divided into two sub-problems of generation and transmission. The two sub-problems will then be combined to provide a composite solution. The generation sub-problem considers investment costs, fuel cost, operation and maintenance costs, generation limits, and limits on unserved energy. The transmission sub-problem takes into consideration power flow, cost of adding lines, number of circuits in a route. The transmission sub-problem is formulated as a mixed integer optimization problem. The developed algorithms were solved using Branch and Bound method. The transmission sub-problem was solved through DC power flow based on a successive backward method. This was tested on two systems including an artificial an IPP seeking an appropriate location. The results provide a location for the IPP with sufficient transmission access and at the same time minimized the overall costs.","PeriodicalId":246039,"journal":{"name":"2009 International Conference on Power Engineering, Energy and Electrical Drives","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-03-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Composite generation and transmission planning in a competitive environment\",\"authors\":\"I. Elamin, Mohammed T. Al-Saba\",\"doi\":\"10.1109/POWERENG.2009.4915202\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In a deregulated power system, generation companies would like to maximize their profits and share of the electricity market. This can only be achieved if transmission access and network availability is satisfactory. New mathematical models for generation and transmission planning are thus needed. The problem is divided into two sub-problems of generation and transmission. The two sub-problems will then be combined to provide a composite solution. The generation sub-problem considers investment costs, fuel cost, operation and maintenance costs, generation limits, and limits on unserved energy. The transmission sub-problem takes into consideration power flow, cost of adding lines, number of circuits in a route. The transmission sub-problem is formulated as a mixed integer optimization problem. The developed algorithms were solved using Branch and Bound method. The transmission sub-problem was solved through DC power flow based on a successive backward method. This was tested on two systems including an artificial an IPP seeking an appropriate location. The results provide a location for the IPP with sufficient transmission access and at the same time minimized the overall costs.\",\"PeriodicalId\":246039,\"journal\":{\"name\":\"2009 International Conference on Power Engineering, Energy and Electrical Drives\",\"volume\":\"16 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2009-03-18\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2009 International Conference on Power Engineering, Energy and Electrical Drives\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/POWERENG.2009.4915202\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 International Conference on Power Engineering, Energy and Electrical Drives","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/POWERENG.2009.4915202","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

在一个放松管制的电力系统中,发电公司希望最大化他们的利润和电力市场份额。这只有在传输接入和网络可用性令人满意的情况下才能实现。因此,发电和输电规划需要新的数学模型。该问题分为发电和输电两个子问题。然后将这两个子问题组合起来,以提供复合解决方案。发电子问题考虑了投资成本、燃料成本、运行和维护成本、发电限制和未服务能源限制。传输子问题考虑了潮流、增加线路的成本和线路上的电路数量。将传输子问题表述为一个混合整数优化问题。采用分支定界法对所开发的算法进行求解。采用逐次倒推法求解直流潮流输电子问题。这在两个系统上进行了测试,其中包括一个人工IPP寻找合适的位置。结果为IPP提供了一个有足够传输通道的位置,同时将总成本降至最低。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Composite generation and transmission planning in a competitive environment
In a deregulated power system, generation companies would like to maximize their profits and share of the electricity market. This can only be achieved if transmission access and network availability is satisfactory. New mathematical models for generation and transmission planning are thus needed. The problem is divided into two sub-problems of generation and transmission. The two sub-problems will then be combined to provide a composite solution. The generation sub-problem considers investment costs, fuel cost, operation and maintenance costs, generation limits, and limits on unserved energy. The transmission sub-problem takes into consideration power flow, cost of adding lines, number of circuits in a route. The transmission sub-problem is formulated as a mixed integer optimization problem. The developed algorithms were solved using Branch and Bound method. The transmission sub-problem was solved through DC power flow based on a successive backward method. This was tested on two systems including an artificial an IPP seeking an appropriate location. The results provide a location for the IPP with sufficient transmission access and at the same time minimized the overall costs.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
An advanced three phase five level PWM rectifier Game based strategic bidding in pay as bid markets considering incomplete information and risk factor Novel flux weakening control algorithm for PMSMS Dynamics analysis of 220 V DC auxiliary system in power plant using different mathematical models Efficient system parameter selection to prevent oscillatory voltage instability
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1