{"title":"确定保证最高价格(gmp)合同的重大风险因素","authors":"AD Palihakkara, B. Perera","doi":"10.31705/WCS.2021.30","DOIUrl":null,"url":null,"abstract":"The construction industry is a risk-prone industry where projects are implemented in a dynamic environment with frequent exposure to various uncertainties. A construction contract is a document that allocates the risks associated with a construction project among the project stakeholders. Guaranteed Maximum Price (GMP) contracts have become popular as a project delivery method because they provide the client with a high degree of cost certainty through a fixed price cap that the contractor cannot exceed. However, most of the GMP projects are risky. Thus, the significant risk factors of GMP projects have to be identified to ensure their successful completion. This study, therefore, aimed to identify and rank the most significant risk factors present in GMP contracts. The study adopted a quantitative approach, which included a Delphi survey conducted in two rounds and a statistical analysis of the survey data. The most significant risk factors associated with GMP contracts were ranked according to their impact on the projects and their probability of occurrence (severity). Poorly defined scope of work and design changes were found to be the most significant risk factors associated with GMP contracts. The other significant risk factors of the projects are related to the scope of work, design, documentation, unfamiliarity with the GMP concept, agreed GMP value, and financial failures of the client and contractor.","PeriodicalId":320967,"journal":{"name":"Proceedings of the 9th World Construction Symposium 2021 on Reshaping construction: Strategic, Structural and Cultural Transformations towards the 'Next Normal'","volume":"50 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-07-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"IDENTIFICATION OF SIGNIFICANT RISK FACTORS OF GUARANTEED MAXIMUM PRICE (GMP) CONTRACTS\",\"authors\":\"AD Palihakkara, B. Perera\",\"doi\":\"10.31705/WCS.2021.30\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The construction industry is a risk-prone industry where projects are implemented in a dynamic environment with frequent exposure to various uncertainties. A construction contract is a document that allocates the risks associated with a construction project among the project stakeholders. Guaranteed Maximum Price (GMP) contracts have become popular as a project delivery method because they provide the client with a high degree of cost certainty through a fixed price cap that the contractor cannot exceed. However, most of the GMP projects are risky. Thus, the significant risk factors of GMP projects have to be identified to ensure their successful completion. This study, therefore, aimed to identify and rank the most significant risk factors present in GMP contracts. The study adopted a quantitative approach, which included a Delphi survey conducted in two rounds and a statistical analysis of the survey data. The most significant risk factors associated with GMP contracts were ranked according to their impact on the projects and their probability of occurrence (severity). Poorly defined scope of work and design changes were found to be the most significant risk factors associated with GMP contracts. The other significant risk factors of the projects are related to the scope of work, design, documentation, unfamiliarity with the GMP concept, agreed GMP value, and financial failures of the client and contractor.\",\"PeriodicalId\":320967,\"journal\":{\"name\":\"Proceedings of the 9th World Construction Symposium 2021 on Reshaping construction: Strategic, Structural and Cultural Transformations towards the 'Next Normal'\",\"volume\":\"50 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-07-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the 9th World Construction Symposium 2021 on Reshaping construction: Strategic, Structural and Cultural Transformations towards the 'Next Normal'\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.31705/WCS.2021.30\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 9th World Construction Symposium 2021 on Reshaping construction: Strategic, Structural and Cultural Transformations towards the 'Next Normal'","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31705/WCS.2021.30","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

建筑行业是一个风险较高的行业,项目在一个动态的环境中实施,经常面临各种不确定因素。建设合同是在项目干系人之间分配与建设项目有关的风险的文件。保证最高价格(GMP)合同已成为一种流行的项目交付方式,因为它们通过承包商不能超过的固定价格上限为客户提供了高度的成本确定性。然而,大多数GMP项目都存在风险。因此,必须识别GMP项目的重大风险因素,以确保其顺利完成。因此,本研究旨在确定GMP合同中存在的最重要的风险因素并对其进行排序。本研究采用了定量方法,包括进行两轮德尔菲调查和对调查数据进行统计分析。根据其对项目的影响及其发生的概率(严重程度)对与GMP合同相关的最重要风险因素进行排名。不明确的工作范围和设计变更被发现是与GMP合同相关的最重要的风险因素。项目的其他重要风险因素与工作范围、设计、文件、对GMP概念的不熟悉、商定的GMP值以及客户和承包商的财务失败有关。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
IDENTIFICATION OF SIGNIFICANT RISK FACTORS OF GUARANTEED MAXIMUM PRICE (GMP) CONTRACTS
The construction industry is a risk-prone industry where projects are implemented in a dynamic environment with frequent exposure to various uncertainties. A construction contract is a document that allocates the risks associated with a construction project among the project stakeholders. Guaranteed Maximum Price (GMP) contracts have become popular as a project delivery method because they provide the client with a high degree of cost certainty through a fixed price cap that the contractor cannot exceed. However, most of the GMP projects are risky. Thus, the significant risk factors of GMP projects have to be identified to ensure their successful completion. This study, therefore, aimed to identify and rank the most significant risk factors present in GMP contracts. The study adopted a quantitative approach, which included a Delphi survey conducted in two rounds and a statistical analysis of the survey data. The most significant risk factors associated with GMP contracts were ranked according to their impact on the projects and their probability of occurrence (severity). Poorly defined scope of work and design changes were found to be the most significant risk factors associated with GMP contracts. The other significant risk factors of the projects are related to the scope of work, design, documentation, unfamiliarity with the GMP concept, agreed GMP value, and financial failures of the client and contractor.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
EFFECT OF SOCIAL AND ENVIRONMENTAL FACTORS ON EXPRESSWAY CONSTRUCTION IN SRI LANKA ANALYSING THE GAP BETWEEN PREDICTED AND ACTUAL OPERATIONAL ENERGY CONSUMPTION IN BUILDINGS: A REVIEW ACCURACY OF TRADITIONAL CONTINGENCY ESTIMATION IN THE CONSTRUCTION INDUSTRY A framework to measure collaboration in a construction project COMPARISON BETWEEN THE TERMS CONSTRUCTABILITY AND BUILDABILITY: A SYSTEMATIC LITERATURE REVIEW
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1