采用可溶解金属隔离流入控制装置,并提供无冲洗管的深水地面完井解决方案

Kenneth Johnson, V. Okengwu, B. Orluwosu, Ryan Novelen, Jon-Howard Hanson, V. Chaloupka, A. Achich
{"title":"采用可溶解金属隔离流入控制装置,并提供无冲洗管的深水地面完井解决方案","authors":"Kenneth Johnson, V. Okengwu, B. Orluwosu, Ryan Novelen, Jon-Howard Hanson, V. Chaloupka, A. Achich","doi":"10.4043/29705-ms","DOIUrl":null,"url":null,"abstract":"\n The introductory use of existing inflow control devices (ICD’s) fitted with innovative dissolvable metal plugging rods to allow the operator to run washpipe free completions to reduce rig time is discussed. This work discusses an ICD washpipe-free application run in a long, deep water horizontal sandface completion in the Egina development. The completion was successfully installed following existing processes for tasks and sub-tasks applied in previous completions in the field. The washpipe-free solution was tailored to the reservoir, and is field-adjustable.\n The dissolvable plug solution was provided to be used with existing ICD’s available in country, without modification to the ICD housing. Fluid compatibility testing with dissolvable metals was performed establishing dissolution rates under existing reservoir conditions with mud, brine, and cake breaker at field formulations. Introduction of the dissolvable plug solution has provided the operator with an additional option to consider when seeking to further optimize times necessary to run lower completions in deep water wells offshore West Africa. No changes in existing completion procedures were necessary with respect to the procedure for washing down or subsequently placing cake breaker treatment.\n Running ICD’s with dissolvable plugs was identified as an opportunity to eliminate the need for running lower completion with washpipe. The subject well was run with ICD screens equipped with dissolvable plugs while maintaining full compatibility with the existing upper completion design. Once the well was completed and the tree installed, injectivity testing was successfully performed confirming ICD functionality was re-established.\n The ICD completion design saved the operator a minimum of 12 hours online rig time, further simplifying running the completion and associated handling times. Offline savings include (1) racking washpipe before running the lower completion, (2) subsequent racking back and laying washpipe upon completing the lower completion, (3) eliminating mobilization of washpipe to/from the rig, and (4) freeing up deck space typically used to accommodate the washpipe. During this saved offline time the auxiliary derrick could be used for other offline equipment preparation, helping provide further savings. Washpipe rental and maintenance costs were eliminated. An important reduction to safety risks related to extensive pipe handling was also achieved.\n This paper describes laboratory testing, full quality assurance/quality control (QA/QC) and operational procedures, leading to the first successful deployment and excellent functionality of ICD’s with dissolvable plugs in a long deep water horizontal completion eliminating the use of washpipe, while providing associated savings.","PeriodicalId":415055,"journal":{"name":"Day 1 Tue, October 29, 2019","volume":"11 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Implementation of Dissolvable Metals to Isolate Inflow Control Devices and Deliver a Washpipe Free Deep Water Sandface Completion Solution\",\"authors\":\"Kenneth Johnson, V. Okengwu, B. Orluwosu, Ryan Novelen, Jon-Howard Hanson, V. Chaloupka, A. Achich\",\"doi\":\"10.4043/29705-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n The introductory use of existing inflow control devices (ICD’s) fitted with innovative dissolvable metal plugging rods to allow the operator to run washpipe free completions to reduce rig time is discussed. This work discusses an ICD washpipe-free application run in a long, deep water horizontal sandface completion in the Egina development. The completion was successfully installed following existing processes for tasks and sub-tasks applied in previous completions in the field. The washpipe-free solution was tailored to the reservoir, and is field-adjustable.\\n The dissolvable plug solution was provided to be used with existing ICD’s available in country, without modification to the ICD housing. Fluid compatibility testing with dissolvable metals was performed establishing dissolution rates under existing reservoir conditions with mud, brine, and cake breaker at field formulations. Introduction of the dissolvable plug solution has provided the operator with an additional option to consider when seeking to further optimize times necessary to run lower completions in deep water wells offshore West Africa. No changes in existing completion procedures were necessary with respect to the procedure for washing down or subsequently placing cake breaker treatment.\\n Running ICD’s with dissolvable plugs was identified as an opportunity to eliminate the need for running lower completion with washpipe. The subject well was run with ICD screens equipped with dissolvable plugs while maintaining full compatibility with the existing upper completion design. Once the well was completed and the tree installed, injectivity testing was successfully performed confirming ICD functionality was re-established.\\n The ICD completion design saved the operator a minimum of 12 hours online rig time, further simplifying running the completion and associated handling times. Offline savings include (1) racking washpipe before running the lower completion, (2) subsequent racking back and laying washpipe upon completing the lower completion, (3) eliminating mobilization of washpipe to/from the rig, and (4) freeing up deck space typically used to accommodate the washpipe. During this saved offline time the auxiliary derrick could be used for other offline equipment preparation, helping provide further savings. Washpipe rental and maintenance costs were eliminated. An important reduction to safety risks related to extensive pipe handling was also achieved.\\n This paper describes laboratory testing, full quality assurance/quality control (QA/QC) and operational procedures, leading to the first successful deployment and excellent functionality of ICD’s with dissolvable plugs in a long deep water horizontal completion eliminating the use of washpipe, while providing associated savings.\",\"PeriodicalId\":415055,\"journal\":{\"name\":\"Day 1 Tue, October 29, 2019\",\"volume\":\"11 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-10-28\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 1 Tue, October 29, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/29705-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Tue, October 29, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/29705-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

介绍了现有流入控制装置(ICD)的初步应用,该装置配备了创新的可溶解金属堵塞杆,使作业者无需冲洗管即可下完井,从而缩短了钻机时间。本工作讨论了在Egina开发的长深水水平砂面完井中使用ICD洗管的情况。完成完井作业后,完成了之前现场完井作业的任务和子任务的现有流程。无需冲洗管的解决方案是根据储层定制的,并且可以现场调节。该可溶解塞溶液可与国内现有的ICD一起使用,无需修改ICD外壳。在现有油藏条件下,采用泥浆、盐水和破饼剂进行了可溶金属的流体相容性测试,确定了溶解速率。可溶解桥塞解决方案的引入为作业者提供了额外的选择,当他们寻求进一步优化西非海上深水井下完井所需的时间时。现有完井程序不需要改变,例如冲洗或随后放置破饼处理的程序。下入带有可溶解桥塞的ICD,可以避免下入带冲洗管的下部完井作业。该井的ICD筛管配备了可溶解桥塞,同时保持了与现有上部完井设计的完全兼容。完井后,采油树安装完成后,进行了成功的注入能力测试,确认ICD功能恢复正常。ICD完井设计为作业者节省了至少12小时的在线钻机时间,进一步简化了完井作业和相关处理时间。线下节约包括:(1)下完井前安装冲洗管,(2)下完井后安装冲洗管,(3)消除了冲洗管进出钻机的调动,(4)腾出了通常用于容纳冲洗管的甲板空间。在节省的离线时间内,辅助井架可以用于其他离线设备的准备,从而进一步节省成本。消除了冲洗管的租金和维修费用。此外,还显著降低了与大量管道处理相关的安全风险。本文介绍了实验室测试、全面的质量保证/质量控制(QA/QC)和操作流程,从而实现了ICD的首次成功部署和出色的功能,并在深水水平完井中消除了冲洗管的使用,同时节省了相关费用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Implementation of Dissolvable Metals to Isolate Inflow Control Devices and Deliver a Washpipe Free Deep Water Sandface Completion Solution
The introductory use of existing inflow control devices (ICD’s) fitted with innovative dissolvable metal plugging rods to allow the operator to run washpipe free completions to reduce rig time is discussed. This work discusses an ICD washpipe-free application run in a long, deep water horizontal sandface completion in the Egina development. The completion was successfully installed following existing processes for tasks and sub-tasks applied in previous completions in the field. The washpipe-free solution was tailored to the reservoir, and is field-adjustable. The dissolvable plug solution was provided to be used with existing ICD’s available in country, without modification to the ICD housing. Fluid compatibility testing with dissolvable metals was performed establishing dissolution rates under existing reservoir conditions with mud, brine, and cake breaker at field formulations. Introduction of the dissolvable plug solution has provided the operator with an additional option to consider when seeking to further optimize times necessary to run lower completions in deep water wells offshore West Africa. No changes in existing completion procedures were necessary with respect to the procedure for washing down or subsequently placing cake breaker treatment. Running ICD’s with dissolvable plugs was identified as an opportunity to eliminate the need for running lower completion with washpipe. The subject well was run with ICD screens equipped with dissolvable plugs while maintaining full compatibility with the existing upper completion design. Once the well was completed and the tree installed, injectivity testing was successfully performed confirming ICD functionality was re-established. The ICD completion design saved the operator a minimum of 12 hours online rig time, further simplifying running the completion and associated handling times. Offline savings include (1) racking washpipe before running the lower completion, (2) subsequent racking back and laying washpipe upon completing the lower completion, (3) eliminating mobilization of washpipe to/from the rig, and (4) freeing up deck space typically used to accommodate the washpipe. During this saved offline time the auxiliary derrick could be used for other offline equipment preparation, helping provide further savings. Washpipe rental and maintenance costs were eliminated. An important reduction to safety risks related to extensive pipe handling was also achieved. This paper describes laboratory testing, full quality assurance/quality control (QA/QC) and operational procedures, leading to the first successful deployment and excellent functionality of ICD’s with dissolvable plugs in a long deep water horizontal completion eliminating the use of washpipe, while providing associated savings.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
P-67: Review of Dry Transportation of FLNG’s/FSRU’s/FPSO’s Compact Hydrate Dissociation Plant: Combined Direct and Indirect Heating for Increased Efficiency Research on Engineering Technologies to Develop China's Complex Reservoirs and their Feasibility in Development of Marginal Oilfields in South America Efficient Selection of Reservoir Model Outputs within an Emulation Based Iterative Uncertainty Analysis Decommissioning of Subsea Facilities in Brazil
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1