{"title":"Analisis Struktur Terowongan Pengelak Pada Bendungan Kualu Kabupaten Toba Samosir Provinsi Sumatra Utara","authors":"Afan Allail Rofikha, Suwanto Marsudi, Evi Nur Cahya","doi":"10.21776/UB.PENGAIRAN.2019.010.01.3","DOIUrl":null,"url":null,"abstract":"Diversion structure consists of diversion tunnel and Cofferdam. These two contructions should built in the early construction of the dam, have function to divert the river flow during the period of dam construction. The plans of Kualu dam diversion tunnel designed using horseshoe shape F, upstream of the tunnel at a depth of 41.625 m and upstream elevation + 695.5 m. In this study there was flood routing with Q25th which is 709,331 m 3 /s and obtained using 9 m diameter, then a cofferdam is planned to build as high as 15 m. Based on the calculation of loading and calculated four load combinations, they are : after contruction condition, after contruction under earthquake condition, at the operation time condition, and at the operation time under earthquake condition. From the results of the load combinations, the structure was analyzed using Beggs method and Staad Pro method. These two methods were used to figure the maximum moment of the structure and to determine the needed reinforcement in the tunnel construction. After the analysis, it is noticed that there is a difference position of the maximum moment, this is caused by the support in the Beggs method assumed to be a vertical loads.","PeriodicalId":236511,"journal":{"name":"Jurnal Teknik Pengairan","volume":"4 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Pengairan","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21776/UB.PENGAIRAN.2019.010.01.3","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
导流结构由导流隧洞和围堰组成。这两个构筑物应建在大坝建设初期,在大坝建设期间具有分流河水的功能。夸鲁坝引水隧洞方案设计采用马蹄形F形,隧洞上游深度41.625 m,上游标高+ 695.5 m。在本研究中,q25的洪水路径为709,331 m 3 /s,使用9 m直径获得,则计划建造15 m高的围堰。在荷载计算的基础上,计算出四种荷载组合,分别是:施工后工况、地震工况下施工后工况、运行时工况、地震工况下运行时工况。根据荷载组合结果,采用Beggs法和Staad Pro法对结构进行分析。这两种方法用于计算结构的最大弯矩和确定隧道施工中所需的配筋。分析后,注意到最大弯矩的位置存在差异,这是由于Beggs方法中假设的支撑为垂直荷载造成的。
Analisis Struktur Terowongan Pengelak Pada Bendungan Kualu Kabupaten Toba Samosir Provinsi Sumatra Utara
Diversion structure consists of diversion tunnel and Cofferdam. These two contructions should built in the early construction of the dam, have function to divert the river flow during the period of dam construction. The plans of Kualu dam diversion tunnel designed using horseshoe shape F, upstream of the tunnel at a depth of 41.625 m and upstream elevation + 695.5 m. In this study there was flood routing with Q25th which is 709,331 m 3 /s and obtained using 9 m diameter, then a cofferdam is planned to build as high as 15 m. Based on the calculation of loading and calculated four load combinations, they are : after contruction condition, after contruction under earthquake condition, at the operation time condition, and at the operation time under earthquake condition. From the results of the load combinations, the structure was analyzed using Beggs method and Staad Pro method. These two methods were used to figure the maximum moment of the structure and to determine the needed reinforcement in the tunnel construction. After the analysis, it is noticed that there is a difference position of the maximum moment, this is caused by the support in the Beggs method assumed to be a vertical loads.