移相变压器控制和保护设置验证

B. Cook, M. Thompson, K. Garg, M. Malichkar
{"title":"移相变压器控制和保护设置验证","authors":"B. Cook, M. Thompson, K. Garg, M. Malichkar","doi":"10.1109/CPRE.2018.8349815","DOIUrl":null,"url":null,"abstract":"San Diego Gas & Electric (SDG&E) initiated a project to add two parallel 400 MVA (+31.3° to −80.1°) phase-shifting transformers (PSTs) at a 230 kV interconnection substation. California ISO (CAISO) proposed the PST project to provide flow control between SDG&E and Comisión Federal de Electricidad (CFE) 230 kV systems during critical N-1 or N-1-1 500 kV line contingencies. With the need to integrate renewable generation, many utilities are using PSTs to manage the grid (e.g., American Electric Power [AEP] has eight PSTs in their system). SDG&E is presently reviewing the need for additional PST projects. The authors collaborated to address the unique challenges of parallel PST protection and control for this wide-ranging PST application, including implementation of CAISO control and automatic contingency-based tap-changer runback. This paper discusses SDG&E's process to execute the project, including settings development, simulation, lab and field testing, and in-service testing. The authors discuss oscillography analysis used during lab testing, energization, and loading to verify the overall design and programming.","PeriodicalId":285875,"journal":{"name":"2018 71st Annual Conference for Protective Relay Engineers (CPRE)","volume":"PC-25 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-03-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Phase-shifting transformer control and protection settings verification\",\"authors\":\"B. Cook, M. Thompson, K. Garg, M. Malichkar\",\"doi\":\"10.1109/CPRE.2018.8349815\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"San Diego Gas & Electric (SDG&E) initiated a project to add two parallel 400 MVA (+31.3° to −80.1°) phase-shifting transformers (PSTs) at a 230 kV interconnection substation. California ISO (CAISO) proposed the PST project to provide flow control between SDG&E and Comisión Federal de Electricidad (CFE) 230 kV systems during critical N-1 or N-1-1 500 kV line contingencies. With the need to integrate renewable generation, many utilities are using PSTs to manage the grid (e.g., American Electric Power [AEP] has eight PSTs in their system). SDG&E is presently reviewing the need for additional PST projects. The authors collaborated to address the unique challenges of parallel PST protection and control for this wide-ranging PST application, including implementation of CAISO control and automatic contingency-based tap-changer runback. This paper discusses SDG&E's process to execute the project, including settings development, simulation, lab and field testing, and in-service testing. The authors discuss oscillography analysis used during lab testing, energization, and loading to verify the overall design and programming.\",\"PeriodicalId\":285875,\"journal\":{\"name\":\"2018 71st Annual Conference for Protective Relay Engineers (CPRE)\",\"volume\":\"PC-25 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2018-03-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2018 71st Annual Conference for Protective Relay Engineers (CPRE)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/CPRE.2018.8349815\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 71st Annual Conference for Protective Relay Engineers (CPRE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/CPRE.2018.8349815","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

圣地亚哥燃气和电力公司(SDG&E)启动了一个项目,在一个230千伏的互连变电站增加两个并联的400 MVA(+31.3°至- 80.1°)移相变压器(pst)。加州ISO (CAISO)提出了PST项目,在关键的N-1或N-1-1 500千伏线路事故期间,提供SDG&E和Comisión联邦电力公司(CFE) 230千伏系统之间的流量控制。由于需要整合可再生能源发电,许多公用事业公司正在使用pst来管理电网(例如,美国电力公司[AEP]在他们的系统中有八个pst)。SDG&E目前正在审查额外PST项目的需求。作者合作解决了这种广泛的PST应用中并行PST保护和控制的独特挑战,包括实施CAISO控制和基于突发事件的自动分接开关回退。本文讨论了SDG&E执行项目的过程,包括设置开发、模拟、实验室和现场测试以及在用测试。作者讨论了在实验室测试、通电和加载期间使用的示波器分析,以验证整体设计和编程。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Phase-shifting transformer control and protection settings verification
San Diego Gas & Electric (SDG&E) initiated a project to add two parallel 400 MVA (+31.3° to −80.1°) phase-shifting transformers (PSTs) at a 230 kV interconnection substation. California ISO (CAISO) proposed the PST project to provide flow control between SDG&E and Comisión Federal de Electricidad (CFE) 230 kV systems during critical N-1 or N-1-1 500 kV line contingencies. With the need to integrate renewable generation, many utilities are using PSTs to manage the grid (e.g., American Electric Power [AEP] has eight PSTs in their system). SDG&E is presently reviewing the need for additional PST projects. The authors collaborated to address the unique challenges of parallel PST protection and control for this wide-ranging PST application, including implementation of CAISO control and automatic contingency-based tap-changer runback. This paper discusses SDG&E's process to execute the project, including settings development, simulation, lab and field testing, and in-service testing. The authors discuss oscillography analysis used during lab testing, energization, and loading to verify the overall design and programming.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
期刊最新文献
Correlating protective relay reports for system-wide, post-event analysis Back to the basics — Event analysis using symmetrical components Cyber security — Securing the protection and control relay communication in substation Communications assisted islanding detection: Contrasting direct transfer trip and phase comparison methods Applying intelligent fast load shed using IEC 61850 GOOSE
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1