{"title":"Vito项目:海底系统回归基础","authors":"K. Thurston, Karthik R Ramanathan","doi":"10.4043/32318-ms","DOIUrl":null,"url":null,"abstract":"\n In 2009, the Vito field was discovered in more than 4,000 ft of water approximately 150 miles offshore from New Orleans, Louisiana. The project produces from reservoirs nearly 30,000 feet below sea level. The project underwent major redesign to remain competitive, and this paper describes changes within the subsea system. This paper is part of a Vito Project series at OTC 2023, and the other papers are listed in the references.\n As the industry and market began to change in 2015, the project faced significant financial hurdles, and the project team decided to refresh the field development concept to reduce cost and simplify. This paper focuses on the subsea production system and some of the key decisions leading to the selected design and the approach the team used for making these decisions. It also discusses how the project execution model was established, and the modifications made during project execution to react to schedule challenges, the unprecedented impacts of COVID-19, and a tightening offshore market.","PeriodicalId":196855,"journal":{"name":"Day 2 Tue, May 02, 2023","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-04-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":"{\"title\":\"Vito Project: Subsea System Goes Back to Basics\",\"authors\":\"K. Thurston, Karthik R Ramanathan\",\"doi\":\"10.4043/32318-ms\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n In 2009, the Vito field was discovered in more than 4,000 ft of water approximately 150 miles offshore from New Orleans, Louisiana. The project produces from reservoirs nearly 30,000 feet below sea level. The project underwent major redesign to remain competitive, and this paper describes changes within the subsea system. This paper is part of a Vito Project series at OTC 2023, and the other papers are listed in the references.\\n As the industry and market began to change in 2015, the project faced significant financial hurdles, and the project team decided to refresh the field development concept to reduce cost and simplify. This paper focuses on the subsea production system and some of the key decisions leading to the selected design and the approach the team used for making these decisions. It also discusses how the project execution model was established, and the modifications made during project execution to react to schedule challenges, the unprecedented impacts of COVID-19, and a tightening offshore market.\",\"PeriodicalId\":196855,\"journal\":{\"name\":\"Day 2 Tue, May 02, 2023\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-04-24\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"5\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, May 02, 2023\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4043/32318-ms\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, May 02, 2023","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4043/32318-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
In 2009, the Vito field was discovered in more than 4,000 ft of water approximately 150 miles offshore from New Orleans, Louisiana. The project produces from reservoirs nearly 30,000 feet below sea level. The project underwent major redesign to remain competitive, and this paper describes changes within the subsea system. This paper is part of a Vito Project series at OTC 2023, and the other papers are listed in the references.
As the industry and market began to change in 2015, the project faced significant financial hurdles, and the project team decided to refresh the field development concept to reduce cost and simplify. This paper focuses on the subsea production system and some of the key decisions leading to the selected design and the approach the team used for making these decisions. It also discusses how the project execution model was established, and the modifications made during project execution to react to schedule challenges, the unprecedented impacts of COVID-19, and a tightening offshore market.