施工中的任务规划与控制:揭示工人的早、晚计划者

Christopher Görsch, Olli Seppänen, Antti Peltokorpi, Rita Lavikka
{"title":"施工中的任务规划与控制:揭示工人的早、晚计划者","authors":"Christopher Görsch, Olli Seppänen, Antti Peltokorpi, Rita Lavikka","doi":"10.1080/01446193.2023.2270080","DOIUrl":null,"url":null,"abstract":"Production planning and control are critical to project success. They are conventionally understood as linking planning and production by coordinating tasks prior to installation work. However, research has highlighted workers as autonomous and decentralized planners of installation work, which challenges conventional management perspectives. Performing task-level planning and control requires resources and effort, reducing the time spent on installation work. This study explores workers’ planning practices by examining the use of higher-level plans and other information sources and by analyzing workers’ information needs and the factors determining them. A survey of Finnish construction workers was conducted. The results show that some workers prefer planning tasks before arriving at the construction site, while others prefer planning tasks during on-site work preparation. Trade- and crew-specific factors influence planning earlier or later and determine the extent to which centralized and decentralized sources and practices are used. Decentralized sources and practices are most often used to meet workers’ information needs, although centralized sources and practices are also used. These findings may help construction stakeholders better understand the information sources and practices used by workers. Thus, task planning and control activities can better meet workers’ information needs, allowing for more time for installation work.","PeriodicalId":51389,"journal":{"name":"Construction Management and Economics","volume":"69 1","pages":"0"},"PeriodicalIF":3.0000,"publicationDate":"2023-10-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Task planning and control in construction: revealing workers as early and late planners\",\"authors\":\"Christopher Görsch, Olli Seppänen, Antti Peltokorpi, Rita Lavikka\",\"doi\":\"10.1080/01446193.2023.2270080\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Production planning and control are critical to project success. They are conventionally understood as linking planning and production by coordinating tasks prior to installation work. However, research has highlighted workers as autonomous and decentralized planners of installation work, which challenges conventional management perspectives. Performing task-level planning and control requires resources and effort, reducing the time spent on installation work. This study explores workers’ planning practices by examining the use of higher-level plans and other information sources and by analyzing workers’ information needs and the factors determining them. A survey of Finnish construction workers was conducted. The results show that some workers prefer planning tasks before arriving at the construction site, while others prefer planning tasks during on-site work preparation. Trade- and crew-specific factors influence planning earlier or later and determine the extent to which centralized and decentralized sources and practices are used. Decentralized sources and practices are most often used to meet workers’ information needs, although centralized sources and practices are also used. These findings may help construction stakeholders better understand the information sources and practices used by workers. Thus, task planning and control activities can better meet workers’ information needs, allowing for more time for installation work.\",\"PeriodicalId\":51389,\"journal\":{\"name\":\"Construction Management and Economics\",\"volume\":\"69 1\",\"pages\":\"0\"},\"PeriodicalIF\":3.0000,\"publicationDate\":\"2023-10-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Construction Management and Economics\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1080/01446193.2023.2270080\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q2\",\"JCRName\":\"BUSINESS\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction Management and Economics","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1080/01446193.2023.2270080","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"BUSINESS","Score":null,"Total":0}
引用次数: 0

摘要

生产计划和控制是项目成功的关键。它们通常被理解为通过在安装工作之前协调任务来连接计划和生产。然而,研究强调工人是安装工作的自主和分散的规划者,这挑战了传统的管理观点。执行任务级计划和控制需要资源和精力,从而减少了在安装工作上花费的时间。本研究通过检查高层计划和其他信息源的使用,并通过分析工人的信息需求和决定他们的因素,探讨了工人的计划实践。对芬兰建筑工人进行了一项调查。结果表明,一些工人更喜欢在到达施工现场之前进行规划任务,而另一些工人更喜欢在现场工作准备时进行规划任务。特定于贸易和船员的因素对规划的影响或早或晚,并决定使用集中和分散来源和做法的程度。分散的来源和做法最常用于满足工人的信息需求,尽管也使用集中的来源和做法。这些发现可以帮助建筑利益相关者更好地理解工人使用的信息来源和实践。因此,任务规划和控制活动可以更好地满足工人的信息需求,从而为安装工作留出更多的时间。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
Task planning and control in construction: revealing workers as early and late planners
Production planning and control are critical to project success. They are conventionally understood as linking planning and production by coordinating tasks prior to installation work. However, research has highlighted workers as autonomous and decentralized planners of installation work, which challenges conventional management perspectives. Performing task-level planning and control requires resources and effort, reducing the time spent on installation work. This study explores workers’ planning practices by examining the use of higher-level plans and other information sources and by analyzing workers’ information needs and the factors determining them. A survey of Finnish construction workers was conducted. The results show that some workers prefer planning tasks before arriving at the construction site, while others prefer planning tasks during on-site work preparation. Trade- and crew-specific factors influence planning earlier or later and determine the extent to which centralized and decentralized sources and practices are used. Decentralized sources and practices are most often used to meet workers’ information needs, although centralized sources and practices are also used. These findings may help construction stakeholders better understand the information sources and practices used by workers. Thus, task planning and control activities can better meet workers’ information needs, allowing for more time for installation work.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
7.50
自引率
14.70%
发文量
58
期刊介绍: Construction Management and Economics publishes high-quality original research concerning the management and economics of activity in the construction industry. Our concern is the production of the built environment. We seek to extend the concept of construction beyond on-site production to include a wide range of value-adding activities and involving coalitions of multiple actors, including clients and users, that evolve over time. We embrace the entire range of construction services provided by the architecture/engineering/construction sector, including design, procurement and through-life management. We welcome papers that demonstrate how the range of diverse academic and professional disciplines enable robust and novel theoretical, methodological and/or empirical insights into the world of construction. Ultimately, our aim is to inform and advance academic debates in the various disciplines that converge on the construction sector as a topic of research. While we expect papers to have strong theoretical positioning, we also seek contributions that offer critical, reflexive accounts on practice. Construction Management & Economics now publishes the following article types: -Research Papers -Notes - offering a comment on a previously published paper or report a new idea, empirical finding or approach. -Book Reviews -Letters - terse, scholarly comments on any aspect of interest to our readership. Commentaries -Obituaries - welcome in relation to significant figures in our field.
期刊最新文献
Digital platforms and the construction supply chain: trends and emerging themes in extant AEC research Bug or feature? Institutional misalignments between construction technology and venture capital Public clients pursue innovation, but what’s going on at the project level? A case study of infrastructure operation and maintenance Understanding the effect of contractual complexity on regulatory focus in construction projects: the moderating role of organizational culture Making logistics a central core in complex construction projects: a power-dependency analysis
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1