基于时刻表的复杂铁路网设计问题

IF 1.6 4区 计算机科学 Q4 COMPUTER SCIENCE, HARDWARE & ARCHITECTURE Networks Pub Date : 2023-10-12 DOI:10.1002/net.22192
Nadine Friesen, Tim Sander, Christina Büsing, Karl Nachtigall, Nils Nießen
{"title":"基于时刻表的复杂铁路网设计问题","authors":"Nadine Friesen, Tim Sander, Christina Büsing, Karl Nachtigall, Nils Nießen","doi":"10.1002/net.22192","DOIUrl":null,"url":null,"abstract":"Abstract Because of the long planning periods and their long life cycle, railway infrastructure has to be outlined long ahead. At the present, the infrastructure is designed while only little about the intended operation is known. Hence, the timetable and the operation are adjusted to the infrastructure. Since space, time and money for extension measures of railway infrastructure are limited, each modification has to be done carefully and long lasting and should be appropriate for the future unknown demand. To take this into account, we present the robust network design problem for railway infrastructure under capacity constraints and uncertain timetables. Here, we plan the required expansion measures for an uncertain long‐term timetable. We show that this problem is NP‐hard even when restricted to bipartite graphs and very simple timetables and present easier solvable special cases. This problem corresponds to the fixed‐charge network design problem where the expansion costs are minimized such that the timetable is conductible. We model this problem by an integer linear program using time expanded networks. To incorporate the uncertainty of the future timetable, we use a scenario‐based approach. We define scenarios with individual departure and arrival times and optional trains. The network is then optimized such that a given percentage of the scenarios can be operated while minimizing the expansion costs and potential penalty costs for not scheduled optional trains.","PeriodicalId":54734,"journal":{"name":"Networks","volume":"1 1","pages":"0"},"PeriodicalIF":1.6000,"publicationDate":"2023-10-12","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The complexity of the timetable‐based railway network design problem\",\"authors\":\"Nadine Friesen, Tim Sander, Christina Büsing, Karl Nachtigall, Nils Nießen\",\"doi\":\"10.1002/net.22192\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract Because of the long planning periods and their long life cycle, railway infrastructure has to be outlined long ahead. At the present, the infrastructure is designed while only little about the intended operation is known. Hence, the timetable and the operation are adjusted to the infrastructure. Since space, time and money for extension measures of railway infrastructure are limited, each modification has to be done carefully and long lasting and should be appropriate for the future unknown demand. To take this into account, we present the robust network design problem for railway infrastructure under capacity constraints and uncertain timetables. Here, we plan the required expansion measures for an uncertain long‐term timetable. We show that this problem is NP‐hard even when restricted to bipartite graphs and very simple timetables and present easier solvable special cases. This problem corresponds to the fixed‐charge network design problem where the expansion costs are minimized such that the timetable is conductible. We model this problem by an integer linear program using time expanded networks. To incorporate the uncertainty of the future timetable, we use a scenario‐based approach. We define scenarios with individual departure and arrival times and optional trains. The network is then optimized such that a given percentage of the scenarios can be operated while minimizing the expansion costs and potential penalty costs for not scheduled optional trains.\",\"PeriodicalId\":54734,\"journal\":{\"name\":\"Networks\",\"volume\":\"1 1\",\"pages\":\"0\"},\"PeriodicalIF\":1.6000,\"publicationDate\":\"2023-10-12\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Networks\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1002/net.22192\",\"RegionNum\":4,\"RegionCategory\":\"计算机科学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"COMPUTER SCIENCE, HARDWARE & ARCHITECTURE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Networks","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/net.22192","RegionNum":4,"RegionCategory":"计算机科学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"COMPUTER SCIENCE, HARDWARE & ARCHITECTURE","Score":null,"Total":0}
引用次数: 0

摘要

铁路基础设施由于规划周期长、生命周期长,必须提前规划。目前,基础设施正在设计中,而对预期的操作知之甚少。因此,时间表和操作都要根据基础设施进行调整。由于铁路基础设施扩建措施的空间、时间和资金有限,每次改造都必须仔细、持久,并应适合未来未知的需求。考虑到这一点,我们提出了铁路基础设施在容量限制和时间表不确定条件下的鲁棒网络设计问题。在这里,我们为一个不确定的长期时间表计划所需的扩张措施。我们证明了这个问题即使被限制在二部图和非常简单的时间表上也是NP困难的,并给出了更容易解决的特殊情况。这个问题对应于固定收费网络设计问题,其中扩展成本最小化,使得时间表是可传导的。我们用时间扩展网络的整数线性规划来建模这个问题。为了考虑未来时间表的不确定性,我们采用了基于情景的方法。我们用单独的出发和到达时间以及可选的列车来定义场景。然后对网络进行优化,使给定百分比的场景可以运行,同时将扩展成本和未安排的可选列车的潜在惩罚成本降至最低。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
查看原文
分享 分享
微信好友 朋友圈 QQ好友 复制链接
本刊更多论文
The complexity of the timetable‐based railway network design problem
Abstract Because of the long planning periods and their long life cycle, railway infrastructure has to be outlined long ahead. At the present, the infrastructure is designed while only little about the intended operation is known. Hence, the timetable and the operation are adjusted to the infrastructure. Since space, time and money for extension measures of railway infrastructure are limited, each modification has to be done carefully and long lasting and should be appropriate for the future unknown demand. To take this into account, we present the robust network design problem for railway infrastructure under capacity constraints and uncertain timetables. Here, we plan the required expansion measures for an uncertain long‐term timetable. We show that this problem is NP‐hard even when restricted to bipartite graphs and very simple timetables and present easier solvable special cases. This problem corresponds to the fixed‐charge network design problem where the expansion costs are minimized such that the timetable is conductible. We model this problem by an integer linear program using time expanded networks. To incorporate the uncertainty of the future timetable, we use a scenario‐based approach. We define scenarios with individual departure and arrival times and optional trains. The network is then optimized such that a given percentage of the scenarios can be operated while minimizing the expansion costs and potential penalty costs for not scheduled optional trains.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Networks
Networks 工程技术-计算机:硬件
CiteScore
4.40
自引率
9.50%
发文量
46
审稿时长
12 months
期刊介绍: Network problems are pervasive in our modern technological society, as witnessed by our reliance on physical networks that provide power, communication, and transportation. As well, a number of processes can be modeled using logical networks, as in the scheduling of interdependent tasks, the dating of archaeological artifacts, or the compilation of subroutines comprising a large computer program. Networks provide a common framework for posing and studying problems that often have wider applicability than their originating context. The goal of this journal is to provide a central forum for the distribution of timely information about network problems, their design and mathematical analysis, as well as efficient algorithms for carrying out optimization on networks. The nonstandard modeling of diverse processes using networks and network concepts is also of interest. Consequently, the disciplines that are useful in studying networks are varied, including applied mathematics, operations research, computer science, discrete mathematics, and economics. Networks publishes material on the analytic modeling of problems using networks, the mathematical analysis of network problems, the design of computationally efficient network algorithms, and innovative case studies of successful network applications. We do not typically publish works that fall in the realm of pure graph theory (without significant algorithmic and modeling contributions) or papers that deal with engineering aspects of network design. Since the audience for this journal is then necessarily broad, articles that impact multiple application areas or that creatively use new or existing methodologies are especially appropriate. We seek to publish original, well-written research papers that make a substantive contribution to the knowledge base. In addition, tutorial and survey articles are welcomed. All manuscripts are carefully refereed.
期刊最新文献
Finding conserved low‐diameter subgraphs in social and biological networks A survey on optimization studies of group centrality metrics A heuristic with a performance guarantee for the commodity constrained split delivery vehicle routing problem Selecting fast algorithms for the capacitated vehicle routing problem with machine learning techniques Three network design problems for community energy storage
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
现在去查看 取消
×
提示
确定
0
微信
客服QQ
Book学术公众号 扫码关注我们
反馈
×
意见反馈
请填写您的意见或建议
请填写您的手机或邮箱
已复制链接
已复制链接
快去分享给好友吧!
我知道了
×
扫码分享
扫码分享
Book学术官方微信
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术
文献互助 智能选刊 最新文献 互助须知 联系我们:info@booksci.cn
Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。
Copyright © 2023 Book学术 All rights reserved.
ghs 京公网安备 11010802042870号 京ICP备2023020795号-1